Factory, industrial, semi-fireproof
330 MELROSE STREET
BROOKLYN · BIN 3072091
💬 Discuss this project
1931Year Built
3Stories
F4Building Class
R6Zoning
13,500 sfGross Floor Area
4Units
Rent Stabilized6 Open Violations ▸FDNY Report ↗
Factory, industrial, semi-fireproof · Owner of record: THREE THIRTY M LLC · 5,000 sf lot · 2.7 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire Protection
Roof38p · 1 filing · 20 docs
Penthouse39p · 1 filing · 20 docs
Floor 439p · 1 filing · 20 docs
Floor 334p · 1 filing · 20 docs
Floor 236p · 1 filing · 20 docs
Floor 141p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
MELROSE REALTY LLC1703/22/2026
STEFAN FINISHING CORP103/22/2026
TRAVCON DEVELOPMENT CO303/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
05/15/2024$5.5M—— → —$407/sf building
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
PINE NY203/21/2026
EXPRESS FILING INC4003/21/2026
SNR EXPEDITING DESIGN403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
MJH CONSTRUCTION CORPGeneral Contractor704/09/2026
LCS RESTORATION CORPGeneral Contractor507/08/2026
PRIME PIPING & HEATING INFire Protection107/08/2026
PRIME PIPING & HEATING INPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
HRF SERVICES CORP56161606/09/2025
Building Lifecycle
All (147)Filed (23)Permit Issued (10)Signed Off (9)Violation (55)Inspection (10)Objection (10)Special Inspection (30)
07/11/2025
Violation issued (HPD, closed)
A
07/11/2025
Violation issued (HPD, closed)
A
07/11/2025
Violation issued (HPD, closed)
A
07/11/2025
Violation issued (HPD, closed)
A
07/11/2025
Violation issued (HPD, closed)
A
07/11/2025
Violation issued (HPD, closed)
A
07/11/2025
Violation issued (HPD, closed)
A
06/15/2025
Special inspection requirement — Fire-Resistance Rated Construction
FAHAD FATEH
06/15/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
FAHAD FATEH
06/15/2025
Special inspection requirement — Fenestration areas
FAHAD FATEH
06/15/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
FAHAD FATEH
06/15/2025
Special inspection requirement — Air barrier — testing
FAHAD FATEH
06/15/2025
Special inspection requirement — Electrical motors and elevators
FAHAD FATEH
06/15/2025
Special inspection requirement — Protection of exposed foundation insulation
FAHAD FATEH
06/15/2025
Special inspection requirement — Lighting in dwelling units
FAHAD FATEH
06/15/2025
Special inspection requirement — Exterior lighting power
FAHAD FATEH
06/15/2025
Special inspection requirement — Interior lighting power
FAHAD FATEH
06/15/2025
Special inspection requirement — Metering
FAHAD FATEH
06/15/2025
Special inspection requirement — Lighting controls
FAHAD FATEH
06/15/2025
Special inspection requirement — Fenestration air leakage
FAHAD FATEH
06/15/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
FAHAD FATEH
06/15/2025
Special inspection requirement — Insulation placement and R values
FAHAD FATEH
06/15/2025
Special inspection requirement — Maintenance information
FAHAD FATEH
06/15/2025
Special inspection requirement — Energy Code Compliance Inspections
FAHAD FATEH
06/15/2025
Special inspection requirement — Air barrier - visual inspection
FAHAD FATEH
06/10/2025
Violation issued (HPD, closed)
A
06/09/2025
Filed — Alteration CO
PLUMBING SPECIFICATIONS FILED IN CONJUNCTION WITH GC APPLICATION #B00997163-I1.
B00997163-A4
06/09/2025
Special inspection requirement — Fenestration air leakage
FAHAD FATEH
06/09/2025
Special inspection requirement — Exterior lighting power
FAHAD FATEH
06/09/2025
Special inspection requirement — Electrical motors and elevators
FAHAD FATEH
06/09/2025
Special inspection requirement — Metering
FAHAD FATEH
06/09/2025
Special inspection requirement — Interior lighting power
FAHAD FATEH
06/09/2025
Special inspection requirement — Fenestration areas
FAHAD FATEH
06/09/2025
Special inspection requirement — Maintenance information
FAHAD FATEH
06/09/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
FAHAD FATEH
06/09/2025
Special inspection requirement — Lighting in dwelling units
FAHAD FATEH
06/09/2025
Special inspection requirement — Fire-Resistance Rated Construction
FAHAD FATEH
06/09/2025
Special inspection requirement — Insulation placement and R values
FAHAD FATEH
06/09/2025
Special inspection requirement — Energy Code Compliance Inspections
FAHAD FATEH
05/05/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
04/25/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
03/31/2025
Signed off — Alteration CO
PLUMBING SPECIFICATIONS FILED IN CONJUNCTION WITH GC APPLICATION #B00997163-I1.
B00997163-S5
03/07/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
02/28/2025
Signed off — Alteration CO
PLUMBING SPECIFICATIONS FILED IN CONJUNCTION WITH GC APPLICATION #B00997163-I1.
B00997163-S2
02/25/2025
Filed — Alteration CO
PLUMBING SPECIFICATIONS FILED IN CONJUNCTION WITH GC APPLICATION #B00997163-I1.
B00997163-A3
02/10/2025
Filed — Alteration CO
PLUMBING SPECIFICATIONS FILED IN CONJUNCTION WITH GC APPLICATION #B00997163-I1.
B00997163-A2
02/05/2025
Filed — Alteration CO
PLUMBING SPECIFICATIONS FILED IN CONJUNCTION WITH GC APPLICATION #B00997163-I1.
B00997163-A1
01/31/2025
Signed off — Alteration CO
PLUMBING SPECIFICATIONS FILED IN CONJUNCTION WITH GC APPLICATION #B00997163-I1.
B00997163-S3
01/31/2025
Signed off — Alteration CO
PLUMBING SPECIFICATIONS FILED IN CONJUNCTION WITH GC APPLICATION #B00997163-I1.
B00997163-S6
01/27/2025
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
01/27/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
01/24/2025
Signed off — Alteration
INSTALLATION OF TEMPORARY OVERHEAD PROTECTION AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SHALL COMPLY WITH CHAPTER#33 OF 2022 NYC BUILDING CODE.
B01123249-I1
01/24/2025
Signed off — Alteration
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
B01123169-I1
01/24/2025
Signed off — Alteration
PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. LIVE LOAD 300 LBS PER SQUARE FEET. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
B01123160-I1
01/22/2025
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
01/17/2025
Signed off — Alteration CO
PLUMBING SPECIFICATIONS FILED IN CONJUNCTION WITH GC APPLICATION #B00997163-I1.
B00997163-S1
01/17/2025
Filed — Alteration CO
PLUMBING SPECIFICATIONS FILED IN CONJUNCTION WITH GC APPLICATION #B00997163-I1.
B00997163-P9
01/15/2025
Filed — Alteration CO
PLUMBING SPECIFICATIONS FILED IN CONJUNCTION WITH GC APPLICATION #B00997163-I1.
B00997163-P7
01/15/2025
Filed — Alteration CO
PLUMBING SPECIFICATIONS FILED IN CONJUNCTION WITH GC APPLICATION #B00997163-I1.
B00997163-P8
01/15/2025
Signed off — Alteration CO
PLUMBING SPECIFICATIONS FILED IN CONJUNCTION WITH GC APPLICATION #B00997163-I1.
B00997163-S4
Latest 60 of 147 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSupported ScaffoldSigned-offLCS RESTORATION CORP11/19/2024
DOB NOWSidewalk ShedSigned-offLCS RESTORATION CORP11/07/2024
DOB NOWProtection and Mechanical MethodsSigned-offLCS RESTORATION CORP10/22/2024
DOB NOWMechanical SystemsSigned-offMJH CONSTRUCTION CORP08/27/2024
DOB NOWEarth WorkSigned-offMJH CONSTRUCTION CORP08/27/2024
DOB NOWPlumbingSigned-offPRIME PIPING & HEATING IN08/22/2024
DOB NOWSprinklersSigned-offA M B MECHANICAL INC08/22/2024
DOB NOWConstruction FenceSigned-offMJH CONSTRUCTION CORP08/21/2024
DOB NOWGeneral ConstructionPermit IssuedMJH CONSTRUCTION CORP08/06/2024
DOB NOWStructuralSigned-offMJH CONSTRUCTION CORP08/06/2024
BIS—ISSUEDMABE GROUP INC07/07/2022
BISOTISSUEDCAVALRY LLC03/10/2020
BISEQISSUEDADVANCED INSTALLATIONS INC02/01/2008
BISBLISSUEDUNFLAT PEROTTO ASSOCIATES09/14/1998
BISPLISSUEDUNFLAT PEROTTO ASSOCIATES09/14/1998
1 project · most recent 06/09/2025
Heating and Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
06/09/2025Signed-offMJH CONSTRUCTION CORPHeating and Air Conditioning Systems
Heat / Cool
Daikin RXS15LVJU 18,300 BTU · Heat Pump Outdoor ×34
RXS12LVJU 14,400 BTU · Heat Pump Outdoor ×42
RXF18AXVJU 18,300 BTU · Heat Pump Outdoor ×34
2 projects · most recent 06/09/2025
Sprinkler System
FiledStatusContractorScope
06/09/2025Signed-offPRIME PIPING & HEATING INSprinkler System
————
2 projects · most recent 06/09/2025
Gas Storm Water/Sanitary
FiledStatusContractorScope
06/09/2025Signed-offA M B MECHANICAL INCGas, Storm, Water/Sanitary
———Gas, Storm, Water/Sanitary
4 projects · most recent 11/20/2024
General Wiring
FiledStatusContractorScope
11/20/2024CompleteS&R ELECTRICAL & MECHANICGeneral Wiring
10/10/2024CompleteDENALI ELECTRIC CORP—
10/09/2024CompleteRICHARD NEU—
08/09/2024CompleteS&R ELECTRICAL & MECHANICGeneral Wiring
1 project · most recent 06/09/2025
Steel Masonry
FiledStatusContractorScope
06/09/2025Signed-offMJH CONSTRUCTION CORPSteel, Masonry
1 project · most recent 06/09/2025
Fence
FiledStatusContractorScope
06/09/2025Signed-offMJH CONSTRUCTION CORPFence
▾Field Inspections (DOB CAP) — 10
DateTypeResultReport
05/05/2025Pass-Final CND-Occupancy InspectionPassView ↗
04/25/2025Pass-Final CND-Occupancy InspectionPassView ↗
03/07/2025Pass-Final CND-Occupancy InspectionPassView ↗
01/27/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
01/27/2025Pass-Final CND-Occupancy InspectionPassView ↗
01/22/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
11/26/2024Certified Gas-Gas-Piping-RoughingCertifiedView ↗
11/26/2024Certified Storm Drainage-ST-Piping-RoughingCertifiedView ↗
10/15/2024Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
10/15/2024Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 150
DateRequirementInspectorRole
06/15/2025MeteringFAHAD FATEHenergy_progress
06/15/2025Fire-Resistance Rated ConstructionFAHAD FATEHprogress
06/15/2025Energy Code Compliance InspectionsFAHAD FATEHprogress
06/15/2025Structural Stability – Alterations of existing buildingsFAHAD FATEHspecial
06/15/2025Fire-Resistant Penetrations and JointsFAHAD FATEHspecial
06/15/2025Electrical motors and elevatorsFAHAD FATEHenergy_progress
06/15/2025Maintenance informationFAHAD FATEHenergy_progress
06/15/2025Air barrier — testing FAHAD FATEHenergy_progress
06/15/2025Fenestration and door U-factor and product ratingsFAHAD FATEHenergy_progress
06/15/2025Lighting controlsFAHAD FATEHenergy_progress
06/15/2025Protection of exposed foundation insulationFAHAD FATEHenergy_progress
06/15/2025Air barrier - visual inspectionFAHAD FATEHenergy_progress
06/15/2025Lighting in dwelling unitsFAHAD FATEHenergy_progress
06/15/2025Fenestration areasFAHAD FATEHenergy_progress
06/15/2025Exterior lighting powerFAHAD FATEHenergy_progress
06/15/2025Insulation placement and R valuesFAHAD FATEHenergy_progress
06/15/2025Fenestration air leakageFAHAD FATEHenergy_progress
06/15/2025Interior lighting powerFAHAD FATEHenergy_progress
06/09/2025Fenestration air leakageFAHAD FATEHenergy_progress
06/09/2025Fire-Resistant Penetrations and JointsFAHAD FATEHspecial
06/09/2025Structural Stability – Alterations of existing buildingsFAHAD FATEHspecial
06/09/2025Energy Code Compliance InspectionsFAHAD FATEHprogress
06/09/2025Fire-Resistance Rated ConstructionFAHAD FATEHprogress
06/09/2025Lighting in dwelling unitsFAHAD FATEHenergy_progress
06/09/2025Fenestration areasFAHAD FATEHenergy_progress
Latest 25 of 150.
▾Documents — 181 on file (BIS + DOB NOW)
▸Plans & Drawings23
▸DOB NOWPlans/Sketch23
08/24/2026B00997163-P8Request digital key ↗
08/24/2026B00997163-P9Request digital key ↗
08/24/2026B00997163-A1Request digital key ↗
Showing 3 of 23 on file for this type
▸Applications & Permits15
▸BISPLAN / WORK APPROVAL APPLICATION10
01/17/2025321788945Open ↗
01/17/2025300787450Open ↗
01/17/2025300738879Open ↗
Showing 3 of 10 on file for this type
▸BISWORK PERMIT APPLICATION5
02/17/2023321788945Open ↗
02/17/2023322012763Open ↗
07/07/2022322012763Open ↗
Showing 3 of 5 on file for this type
▸Seals & Professional Certifications73
▸DOB NOWDPL-1: Design Professional Seal & Signature23
08/23/2026B01123249-I1Open ↗
08/13/2026B00997163-P8Open ↗
08/13/2026B00997163-P7Open ↗
Showing 3 of 23 on file for this type
▸DOB NOWProgress Inspector Seal & Signature23
09/21/2026B00997163-S1Open ↗
09/01/2026B00997163-A1Open ↗
08/30/2026B00997163-P6Open ↗
Showing 3 of 23 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature16
09/21/2026B00997163-S1Open ↗
09/01/2026B00997163-A1Open ↗
09/01/2026B00997163-S3Open ↗
Showing 3 of 16 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION6
03/17/2020321788945Open ↗
09/25/2019321788945Open ↗
09/11/2019322012763Open ↗
Showing 3 of 6 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST2
10/17/2017321616587Open ↗
01/31/2008310087250Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
10/17/2017321616587Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM1
01/31/2008310087250Open ↗
▸BISPC FULL REPORT1
01/31/2008310087250Open ↗
▸Trade Schedules & Equipment2
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE2
07/05/2019321788945Open ↗
10/17/2017321616587Open ↗
▸Safety & Tenant Protection9
▸DOB NOWStreet Tree Checklist6
08/13/2026B00997163-A4Open ↗
08/13/2026B00997163-P6Open ↗
08/13/2026B00997163-A3Open ↗
Showing 3 of 6 on file for this type
▸BISTenant Protection Plan and Notes1
10/17/2017321616587Open ↗
▸BISSTREET TREE CHECKLIST1
01/14/2021322012763Open ↗
▸BISDEMOLITION SUBMITTAL CERTIFICATION FORM1
07/05/2019321788945Open ↗
▸Environmental & Asbestos23
▸DOB NOWDEP ACP-5: Asbestos Assessment Report19
08/13/2026B00997163-S1Open ↗
08/13/2026B00997163-S2Open ↗
08/13/2026B00997163-S3Open ↗
Showing 3 of 19 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)3
01/14/2021322012763Open ↗
07/05/2019321788945Open ↗
10/17/2017321616587Open ↗
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER1
01/31/2008310087250Open ↗
▸Energy Compliance6
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS4
03/17/2020321788945Open ↗
09/11/2019322012763Open ↗
07/05/2019321788945Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY1
02/22/2022322012763Open ↗
▸DOB NOWPreliminary Commissioning Report Certification1
08/13/2026B00997163-S5Open ↗
▸Inspections & Test Reports3
▸BIS* FINAL INSPECTION DIRECTIVE 14 OF 19752
02/12/2025310087250Open ↗
02/12/2025310087250Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY1
02/22/2022322012763Open ↗
▸Approvals, Objections & Sign-offs4
▸BISSCHEDULE A - OCCUPANCY / USE2
01/11/2021322012763Open ↗
09/11/2019322012763Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
02/13/2025310087250Open ↗
▸BISADMINISTRATIVE OBJECTIONS1
01/31/2008310087250Open ↗
▸Cost, Insurance & Ownership9
▸BISCOST AFFIDAVIT5
02/05/2021322012763Open ↗
09/25/2019321788945Open ↗
09/11/2019322012763Open ↗
Showing 3 of 5 on file for this type
▸BISAcord 25 (Acord Certificate of Liability Insurance)2
06/29/2022322012763Open ↗
02/22/2022322012763Open ↗
▸BISPROJECT-SPECIFIC GL INSURANCE2
06/29/2022322012763Open ↗
02/22/2022322012763Open ↗
▸Filing & Intake Forms3
▸BISEFILING COVER SHEET3
09/11/2019322012763Open ↗
07/05/2019321788945Open ↗
10/17/2017321616587Open ↗
▸Other Documents11
▸DOB NOWProperty Ownership Certification6
08/13/2026B00997163-A4Open ↗
08/13/2026B00997163-A3Open ↗
08/13/2026B00997163-P3Open ↗
Showing 3 of 6 on file for this type
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION2
01/14/2021322012763Open ↗
01/14/2021322012763Open ↗
▸BISPLOT DIAGRAM2
02/05/2021322012763Open ↗
09/11/2019322012763Open ↗
▸DOB NOWAdjoining Owners Notification1
08/13/2026B00997163-S6Open ↗