| Owner | Filings | Most Recent |
|---|---|---|
| HOME 93 LLC | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 10/08/2025 | $8.5M | — | — → — | $1,763/sf building |
| 06/27/2022 | $4.5M | — | — → — | $933/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| BADALY ARCHITECTS | 11 | 04/22/2025 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| ZEFI & CO. LLC | General Contractor | 7 | 04/09/2026 |
| AQUEDUCT MECHANICAL CORP | Fire Protection | 2 | 07/08/2026 |
| AQUEDUCT MECHANICAL CORP | Plumbing | 2 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| BADALY ARCHITECT PLLC | 7137 | 11 | 04/22/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | ZEFI & CO. LLC | 02/18/2025 |
| DOB NOW | Plumbing | Signed-off | AQUEDUCT MECHANICAL CORP | 02/03/2025 |
| DOB NOW | Sprinklers | Signed-off | AQUEDUCT MECHANICAL CORP | 02/03/2025 |
| DOB NOW | Structural | Signed-off | ZEFI & CO. LLC | 12/03/2024 |
| DOB NOW | Sprinklers | Signed-off | AQUEDUCT MECHANICAL CORP | 11/20/2023 |
| DOB NOW | Sprinklers | Signed-off | AQUEDUCT MECHANICAL CORP | 11/20/2023 |
| DOB NOW | General Construction | Permit Issued | ZEFI & CO. LLC | 11/09/2023 |
| DOB NOW | Structural | Signed-off | ZEFI & CO. LLC | 11/03/2023 |
| DOB NOW | Mechanical Systems | Permit Issued | ZEFI & CO. LLC | 06/27/2023 |
| DOB NOW | Structural | Signed-off | ZEFI & CO. LLC | 11/14/2022 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 04/22/2025 | Permit Issued | ZEFI & CO. LLC | Heating and Air Conditioning Systems, Ventilation Systems | Heat / Cool Mitsubishi Electric PUMY-HP48NKMU1 48,000 BTU · Vrf Outdoor ×12 Ventilation Mitsubishi Electric PUMY-HP48NKMU1 350 CFM · Vrf Outdoor ×6 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/22/2025 | Signed-off | AQUEDUCT MECHANICAL CORP | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/22/2025 | Signed-off | AQUEDUCT MECHANICAL CORP | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/29/2024 | Complete | AL ELECTRICAL GROUP INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/22/2025 | Permit Issued | ZEFI & CO. LLC | Wood |
| Date | Type | Result | Report |
|---|---|---|---|
| 09/04/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 03/25/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 02/10/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 02/04/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 02/08/2024 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 02/08/2024 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 02/08/2024 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 02/08/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 02/08/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/29/2025 | HVAC-R and service water piping design and insulation | MOHAMMAD BADALY | energy_progress |
| 04/29/2025 | Structural Wood Frame | MOHAMMAD BADALY | progress |
| 04/29/2025 | Fire-Resistance Rated Construction | MOHAMMAD BADALY | progress |
| 04/29/2025 | HVAC-R and service water heating equipment | MOHAMMAD BADALY | energy_progress |
| 04/29/2025 | Fenestration and door U-factor and product ratings | MOHAMMAD BADALY | energy_progress |
| 04/29/2025 | HVAC-R and service water heating system controls | MOHAMMAD BADALY | energy_progress |
| 04/29/2025 | Structural Stability – Alterations of existing buildings | MOHAMMAD BADALY | special |
| 04/29/2025 | Structural Cold-Formed Steel | MOHAMMAD BADALY | special |
| 04/29/2025 | Mechanical Systems | MOHAMMAD BADALY | special |
| 04/29/2025 | Heating Systems | MOHAMMAD BADALY | special |
| 04/29/2025 | Fire-Resistant Penetrations and Joints | MOHAMMAD BADALY | special |
| 04/29/2025 | Construction Operations Influencing Adjacent Structures | MOHAMMAD BADALY | special |
| 04/29/2025 | Final | MOHAMMAD BADALY | progress |
| 04/21/2025 | HVAC-R and service water piping design and insulation | MOHAMMAD BADALY | energy_progress |
| 04/21/2025 | HVAC-R and service water heating system controls | MOHAMMAD BADALY | energy_progress |
| 04/21/2025 | HVAC-R and service water heating equipment | MOHAMMAD BADALY | energy_progress |
| 04/21/2025 | Fenestration and door U-factor and product ratings | MOHAMMAD BADALY | energy_progress |
| 02/19/2025 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 02/19/2025 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 02/19/2025 | HVAC-R and service water heating equipment | — | energy_progress |
| 02/19/2025 | HVAC-R and service water heating system controls | — | energy_progress |
| 02/19/2025 | Fenestration and door U-factor and product ratings | MOHAMMAD BADALY | energy_progress |
| 02/19/2025 | Construction Operations Influencing Adjacent Structures | MOHAMMAD BADALY | special |
| 02/19/2025 | Fire-Resistant Penetrations and Joints | MOHAMMAD BADALY | special |
| 02/19/2025 | Heating Systems | MOHAMMAD BADALY | special |