| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 02/19/2026 | Permit Issued | SUPER COOL HVAC, LLC | Heating and Air Conditioning Systems | Heat / Cool |
| 12/24/2025 | Permit Issued | SUPER COOL HVAC, LLC | Heating and Air Conditioning Systems | Heat / Cool Lg ZRNU093SJSA 9,000 BTU · Vrf Indoor ×2 ZRNU183SKSA 18,000 BTU · Vrf Indoor ×1 ZRUM036GSS0 3 tons · Vrf Outdoor ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/02/2026 | Complete | TRUE AMP ELECTRIC CORP | — |
| 05/18/2026 | Complete | TRUE AMP ELECTRIC CORP | — |
| 08/11/2025 | Complete | ASSET ELECTRIC CORP | General Wiring |
| 01/28/2025 | Permit Issued | AURORA ELECL CONTG INC | — |
| 01/21/2024 | Complete | ASSET ELECTRIC CORP | General Wiring |
| 02/22/2023 | Permit Issued | TITAN ELEC'L & ELEV CONTR | General Wiring |
| 09/02/2022 | Cancelled | GOTHAM WIRING LICENSED | General Wiring |
| 10/07/2021 | Complete | ROBERT CHIMENTI | — |
| 07/13/2021 | Complete | POWER SURGE ELECTRIC, INC | General Wiring |
| 06/01/2021 | Complete | ROBERT CHIMENTI | — |
| 05/12/2021 | Complete | APOLLO ELECTRIC NYG, INC | — |
| 05/14/2019 | Complete | AMC ELEC'L SERVICES, INC. | General Wiring |
| 08/30/2018 | Complete | GRAMERCY ELECTRIC INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/11/2023 | Permit Issued | M&A PROJECTS RESTORATION* | Steel |
| Owner | Filings | Most Recent |
|---|---|---|
| 330 WEST END APARTMENTS | 21 | 07/08/2026 |
| ORSID NY | 4 | 04/09/2026 |
| 330 WEST END APT | 3 | 03/22/2026 |
| ORSID REALTY | 5 | 03/22/2026 |
| 330 WEST END AVE APARTMENT | 6 | 03/21/2026 |
| 330 WEST END AVE | 5 | 03/21/2026 |
| 330 WEST END APT CORP C O ORSID | 2 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| NYC ENERGY CONSULTANTS | 1 | 02/19/2026 |
| COLLECTIF ENGINEERING PLLC | 1 | 12/24/2025 |
| RIGID STRUCTURAL DESIGN, LLC | 3 | 02/11/2025 |
| CTA ARCHITECTS | 2 | 11/06/2024 |
| OLD STRUCTURES ENGINEERING, P.C. | 2 | 09/11/2023 |
| LINEA LLP | 6 | 09/08/2023 |
| MICHAEL G. FAHEY ARCHITECT P.C. | 2 | 07/11/2023 |
| ASHRAF CORP | 1 | 04/10/2023 |
| RANDALL P. COLLINS ARCHITECT, PC | 2 | 11/22/2022 |
| JDJ ENGINEERING, DPC | 1 | 11/23/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| PONDOSA DESIGN INC | 2 | 03/21/2026 |
| Rigid Structural Design, LLC | 7 | 03/21/2026 |
| ARCHVISION DESIGN STUDIO | 1 | 03/21/2026 |
| MUNICIPAL BUILDING CONSULTANTS | 4 | 03/21/2026 |
| SYNERGY BUILDING CONSULTANTS | 1 | 03/21/2026 |
| SOL BUILDING CONSULTING SERVICES | 6 | 03/21/2026 |
| BMB BUILDING CONSULTING | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| SUBURBAN SUNROOMS INC | General Contractor | 28 | 07/08/2026 |
| INTERSYSTEMS INSTAL S&S | General Contractor | 10 | 07/08/2026 |
| SUPER COOL HVAC, LLC | General Contractor | 5 | 07/08/2026 |
| INTERSYSTEM CONSTRUCTION | General Contractor | 3 | 03/21/2026 |
| LTI CONSTRUCTION CORP | General Contractor | 2 | 03/21/2026 |
| M&A PROJECTS RESTORATION* | General Contractor | 2 | 07/08/2026 |
| PERMA IRON CRAFT CORP | Electrical | 1 | 03/21/2026 |
| PINNACLE ENVIRONMENTAL CO | Electrical | 1 | 03/21/2026 |
| AMERICAN PRO RESTORATION | General Contractor | 1 | 07/08/2026 |
| INNOVATION PLUMBING LLC | Plumbing | 1 | 07/08/2026 |
| ALEXIS FELIX | Electrical | 1 | 03/21/2026 |
| J&M PLUMBING OF WESTCHESTER | Plumbing | 1 | 07/08/2026 |
| ASSET ELECTRIC CORP | Electrical | 1 | 03/22/2026 |
| FEGOS, GREGORY | Electrical | 1 | 03/21/2026 |
| FELIX ALEXIS | Electrical | 1 | 03/21/2026 |
| GOTHAM WIRING LICENSED | Electrical | 1 | 03/22/2026 |
| ILYA ILIN | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| PONDOSA DESIGN INC. | 5126 | 1 | 02/19/2026 |
| COLLECTIF ENGINEERING, PL | 7799 | 1 | 12/24/2025 |
| METRIC CONSULTING AND INS | 1803 | 1 | 10/15/2024 |
| CATALPA SPECIAL INSPECTIO | 2004 | 2 | 10/15/2024 |
| KZ ENGINEERING, P.C. | 4665 | 1 | 09/03/2024 |
| AUTOGRAPHIC CO | 1579 | 2 | 09/11/2023 |
| RYAN SPECIAL ENGINEERING | 2018 | 2 | 07/11/2023 |
| JDJ ENGINEERING, D.P.C. | 6780 | 1 | 11/23/2020 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | SUPER COOL HVAC, LLC | 04/28/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | SUPER COOL HVAC, LLC | 03/19/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | INTERSYSTEM CONSTRUCTION | 01/21/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | INTERSYSTEMS INSTAL S&S | 12/02/2025 |
| DOB NOW | Suspended Scaffold | Signed-off | M & A PROJECTS INC | 12/02/2025 |
| DOB NOW | General Construction | Signed-off | M&A PROJECTS RESTORATION* | 03/07/2025 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | INTERSYSTEMS INSTAL S&S | 02/11/2025 |
| DOB NOW | Supported Scaffold | Signed-off | INTERSYSTEMS INSTAL S&S | 01/31/2025 |
| DOB NOW | Sidewalk Shed | Permit Issued | INTERSYSTEMS INSTAL S&S | 12/13/2024 |
| DOB NOW | Suspended Scaffold | Signed-off | M & A PROJECTS INC | 09/04/2024 |
| DOB NOW | Supported Scaffold | Signed-off | INTERSYSTEMS INSTAL S&S | 04/09/2024 |
| DOB NOW | Structural | Permit Issued | M&A PROJECTS RESTORATION* | 02/09/2024 |
| DOB NOW | General Construction | Signed-off | SUBURBAN SUNROOMS INC | 12/20/2023 |
| DOB NOW | General Construction | Signed-off | SUBURBAN SUNROOMS INC | 12/20/2023 |
| DOB NOW | General Construction | Signed-off | SUBURBAN SUNROOMS INC | 12/20/2023 |
| DOB NOW | General Construction | Signed-off | SUBURBAN SUNROOMS INC | 12/20/2023 |
| DOB NOW | Plumbing | Signed-off | J&M PLUMBING OF WESTCHEST | 07/29/2023 |
| DOB NOW | General Construction | Signed-off | LTI CONSTRUCTION CORP | 07/26/2023 |
| DOB NOW | General Construction | Signed-off | AMERICAN PRO RESTORATION | 04/28/2023 |
| DOB NOW | General Construction | Signed-off | SUBURBAN SUNROOMS INC | 04/20/2023 |
| DOB NOW | General Construction | Signed-off | SUBURBAN SUNROOMS INC | 04/20/2023 |
| DOB NOW | General Construction | Signed-off | SUBURBAN SUNROOMS INC | 04/20/2023 |
| DOB NOW | General Construction | Signed-off | SUBURBAN SUNROOMS INC | 04/20/2023 |
| DOB NOW | Supported Scaffold | Signed-off | INTERSYSTEMS INSTAL S&S | 04/11/2023 |
| DOB NOW | Plumbing | Signed-off | INNOVATION PLUMBING LLC | 02/02/2023 |
| DOB NOW | General Construction | Signed-off | SUBURBAN SUNROOMS INC | 07/15/2022 |
| DOB NOW | General Construction | Signed-off | SUBURBAN SUNROOMS INC | 07/15/2022 |
| DOB NOW | General Construction | Signed-off | SUBURBAN SUNROOMS INC | 07/15/2022 |
| DOB NOW | General Construction | Signed-off | SUBURBAN SUNROOMS INC | 07/15/2022 |
| DOB NOW | Mechanical Systems | Signed-off | SUPER COOL HVAC, LLC | 02/01/2021 |
| BIS | MH | ISSUED | ICEBERG MECHANICAL CORP | 08/05/2019 |
| BIS | PL | ISSUED | BRANCH PLUMBING LLC | 11/13/2018 |
| BIS | MH | ISSUED | ICEBERG MECHANICAL CORP | 10/18/2018 |
| BIS | MH | ISSUED | ICEBERG MECHANICAL CORP | 05/31/2018 |
| BIS | MH | ISSUED | SAMIRO SERVICES INC | 09/28/2017 |
| BIS | PL | ISSUED | THE PLBG & HTG SPECIALIST | 06/22/2017 |
| BIS | MH | ISSUED | FINESSE FURNITURE DESIGN | 06/13/2017 |
| BIS | OT | ISSUED | FINESSE FURNITURE DESIGN | 06/08/2017 |
| BIS | OT | ISSUED | YG KITCHEN & BATH INC | 04/29/2016 |
| BIS | PL | ISSUED | TMS PLMBG & HTG CORP | 04/29/2016 |
| Date | Type | Result | Report |
|---|---|---|---|
| 05/13/2026 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 05/08/2026 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 03/12/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 01/03/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 11/27/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 11/15/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 09/06/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/11/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/11/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 11/11/2025 | Fire-Resistant Penetrations and Joints | RAFAEL FIGUEROA | special |
| 10/27/2025 | Tenant Protection Plan Compliance | MANG WONG | special |
| 10/27/2025 | Mechanical Systems | MANG WONG | special |
| 10/27/2025 | Final | MANG WONG | progress |
| 10/27/2025 | HVAC-R and service water heating equipment | MANG WONG | energy_progress |
| 10/27/2025 | HVAC-R and service water heating system controls | MANG WONG | energy_progress |
| 10/27/2025 | Permanent certificate | MANG WONG | energy_progress |
| 10/27/2025 | HVAC-R and service water piping design and insulation | MANG WONG | energy_progress |
| 10/27/2025 | Maintenance information | MANG WONG | energy_progress |
| 10/16/2025 | Final | RAFAEL FIGUEROA | progress |
| 10/16/2025 | Mechanical Systems | RAFAEL FIGUEROA | special |
| 11/21/2024 | Post-installed Anchors | SAMI HAJJAR P.E | special |
| 11/21/2024 | Fenestration and door U-factor and product ratings | ERIC BERLENT | energy_progress |
| 11/21/2024 | Fenestration air leakage | ERIC BERLENT | energy_progress |
| 11/21/2024 | Energy Code Compliance Inspections | ERIC BERLENT | progress |
| 11/21/2024 | Tenant Protection Plan Compliance | ERIC BERLENT | special |
| 11/21/2024 | Masonry | SAMI HAJJAR P.E | special |
| 11/21/2024 | Final | Christa Waring | progress |
| 09/03/2024 | Post-installed Anchors | Karol Zdancewicz | special |
| 09/03/2024 | Alternative Materials - OTCR Buildings Bulletin Number | Karol Zdancewicz | special |
| 09/19/2023 | Tenant Protection Plan Compliance | ERIC BERLENT | special |
| 09/19/2023 | Structural Steel - Welding | asghar Ghodsi | special |
| 09/19/2023 | Structural Steel - Details | asghar Ghodsi | special |
| 09/19/2023 | Final | ERIC BERLENT | progress |
| 06/30/2023 | Tenant Protection Plan Compliance | William Ryan | special |