← Back
Elevator apt, fireproof with stores
331 COLUMBUS AVENUE
MANHATTAN · Upper West Side (Central) · BIN 1028789
💬 Discuss this project
1894Year Built
7Stories
D6Building Class
C1-8AZoning
62,434 sfGross Floor Area
57Units
LL97 CoveredRent Stabilized33 Open Violations ▸FISP: SWARMP
Elevator apt, fireproof with stores · Owner of record: 60 WEST 76TH STREET LLC · 10,217 sf lot · 6.11 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire ProtectionCivilGeneral
Permit Issued — active, not yet Signed-off
Roof4p · 3 filings · 20 docs
Floor 71 filing · 2 docs
Floor 61 filing · 2 docs
Floor 51 filing · 2 docs
Floor 41 filing · 2 docs
Floor 31 filing · 2 docs
Floor 21 filing · 2 docs
Floor 1Under Construction42p · 6 filings · 20 docs
CellarUnder Construction51p · 6 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
OLSHAN PROPERTIES8608/29/2026
TRI BOROUGH SCAFFOLDING2307/08/2026
PHOENIX SUTTON STR INC503/22/2026
60 WEST 76TH STREET1903/22/2026
60 WEST ST LLC103/22/2026
60 WEST 76 ST803/22/2026
KING WORLD ENTERPRISES203/22/2026
60 WEST 76TH1003/22/2026
FISCHER DEVELOPMENT103/22/2026
60 W 76 ST103/22/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
PROJECT TACTICAL SOLUTIONS2103/21/2026
PDG BUILDING CONSULTANTS LLC LLC1903/21/2026
UNITED SAFETY CONSULTANTS303/21/2026
AE DESIGN SOLUTION1403/21/2026
CONAPAC SERVICES DBA103/21/2026
HOVANN203/21/2026
CONAPAC SERVICES103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
TRI BOROUGH SCAFFOLDINGGeneral Contractor2707/08/2026
CREATIVE HANDS RESTORERSGeneral Contractor1207/08/2026
EMPIRE CORE GROUP LLCGeneral Contractor1007/08/2026
TRADITIONAL WATERPROOFINGGeneral Contractor603/21/2026
DOLPHIN CONSTRUCTION MANAGeneral Contractor507/08/2026
SPRING SCAFFOLDING LLCGeneral Contractor507/08/2026
MIKOMA CONSTRUCTION LLCGeneral Contractor407/08/2026
SAMIRO SERVICES INCGeneral Contractor307/08/2026
SAMUEL & SONS P & H INCPlumbing207/08/2026
ULTIMATE P & H CORPFire Protection207/08/2026
PHOENIX SUTTON STR INCGeneral Contractor203/21/2026
ULTIMATE PLBG AND HTG CORPlumbing207/08/2026
PIPESTYLISTS, INCPlumbing207/08/2026
NATIONAL MAINTENANCEScaffold107/08/2026
JIMENEZ LUISElectrical103/21/2026
JTE ELECTRICAL SERVICESElectrical103/22/2026
LUIS JIMENEZElectrical103/21/2026
VAN VASSELLElectrical103/21/2026
DOUG'S PLBG & HTG SERV COFire Protection107/08/2026
F.S. WORKS INCFire Protection107/08/2026
LOWVOLT TECH ENTERPRISESGeneral Contractor104/09/2026
MC SUPERSTRUCTURE INCGeneral Contractor107/08/2026
P.H. WORKS INCPlumbing107/08/2026
ALLSTATE ELEC'L CONT INCElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
JOSEPH MARTINES PE, PLLC14281705/11/2026
PROJECT TACTICAL SOLUTION58592009/10/2025
THE EIPEL ENGINEERING GRO2714110/12/2023
Building Lifecycle
All (300)Filed (50)Permit Issued (55)Signed Off (27)Facade (FISP) (14)Violation (60)Inspection (34)Objection (30)Special Inspection (30)
06/05/2026
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
05/25/2026
Objection resolved — Addressed
05/25/2026
Special inspection requirement — Tenant Protection Plan Compliance
05/25/2026
Special inspection requirement — Fire-Resistance Rated Construction
JOSEPH MARTINES
05/25/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
JOSEPH MARTINES
05/21/2026
Objection raised — Other
05/18/2026
Objection resolved — Addressed
05/12/2026
Objection raised — Other
05/11/2026
Filed — Alteration CO
Change of use from retail to eating and drinking establishment as per plans filed.
M00909782-P4
05/07/2026
Special inspection requirement — Tenant Protection Plan Compliance
05/05/2026
Special inspection requirement — Fire-Resistance Rated Construction
JOSEPH MARTINES
05/05/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
JOSEPH MARTINES
04/29/2026
Violation issued (HPD, closed)
A
02/02/2026
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
01/07/2026
Inspection — Certified Storm Drainage-ST-Piping-Underground
Certified
View inspection ↗
01/07/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
12/30/2025
Inspection — Certified Storm Drainage-ST-Piping-Underground
Certified
View inspection ↗
12/30/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
10/27/2025
Inspection — Certified Storm Drainage-ST-Fixtures-Finish
Certified
View inspection ↗
10/22/2025
Inspection — Certified Storm Drainage-ST-Piping-Underground
Certified
View inspection ↗
10/16/2025
Permit issued — General Construction
M00909782-I1-GC
09/15/2025
Signed off — Alteration
MECHANICAL WORK TO INCLUDE REPLACEMENT OF COOLING TOWER ON ROOF AND INSTALL OF WSHP'S IN 1ST FLOOR COMMERCIAL SPACE AND ASSOCIATED DUCTS AND PIPING. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
M00870129-I1
09/15/2025
Special inspection requirement — Tenant Protection Plan Compliance
Max Lee
09/15/2025
Special inspection requirement — Final
Max Lee
09/15/2025
Special inspection requirement — Heating Systems
Max Lee
09/15/2025
Special inspection requirement — Mechanical Systems
Max Lee
09/11/2025
Special inspection requirement — Tenant Protection Plan Compliance
Max Lee
09/11/2025
Special inspection requirement — Heating Systems
Max Lee
09/10/2025
Filed — Alteration
MECHANICAL WORK TO INCLUDE REPLACEMENT OF COOLING TOWER ON ROOF AND INSTALL OF WSHP'S IN 1ST FLOOR COMMERCIAL SPACE AND ASSOCIATED DUCTS AND PIPING. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
M00870129-P6
09/10/2025
Filed — Alteration
MECHANICAL WORK TO INCLUDE REPLACEMENT OF COOLING TOWER ON ROOF AND INSTALL OF WSHP'S IN 1ST FLOOR COMMERCIAL SPACE AND ASSOCIATED DUCTS AND PIPING. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
M00870129-P5
09/04/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
08/11/2025
Filed — Alteration CO
Change of use from retail to eating and drinking establishment as per plans filed.
M00909782-P3
07/21/2025
Special inspection requirement — Fire-Resistance Rated Construction
JOSEPH MARTINES
07/21/2025
Special inspection requirement — Tenant Protection Plan Compliance
07/21/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
JOSEPH MARTINES
06/23/2025
Special inspection requirement — Final
Max Lee
06/23/2025
Special inspection requirement — Tenant Protection Plan Compliance
Max Lee
06/23/2025
Special inspection requirement — Heating Systems
Max Lee
06/23/2025
Special inspection requirement — Mechanical Systems
Max Lee
06/20/2025
Signed off — Alteration
INTERIOR RENOVATION (INTERIOR PARTITIONS/ LIGHTING/ LOW-VOLTAGE/ HVAC ALTERATIONS) AT PARTIAL CELLAR AND GROUND FLOOR LEVEL ONLY. NO CHANGE IN USE OCCUPANCY OR EGRESS.
M00903549-I1
05/07/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
04/16/2025
Filed — Alteration CO
Change of use from retail to eating and drinking establishment as per plans filed.
M00909782-P2
04/09/2025
Special inspection requirement — Tenant Protection Plan Compliance
04/07/2025
Special inspection requirement — Fire-Resistance Rated Construction
JOSEPH MARTINES
04/07/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
JOSEPH MARTINES
03/26/2025
Signed off — Alteration
Structural steel to support hanging ceiling features, masonry wall openings at cellar, infill of depressed slab at cellar.
M00940394-I1
03/24/2025
Signed off — Alteration
REMOVE NON LOAD BARING PARTITION CEILINGS AND FINSISHES IN THE CELLAR AND GROUND FLOOR LEVEL ONLY. NO CHANGE IN USE OCCUPANCY OR EGRESS.
M00929486-I1
03/18/2025
Signed off — Alteration
INTERIOR RENOVATION (INTERIOR PARTITIONS/ LIGHTING/ LOW-VOLTAGE/ HVAC ALTERATIONS) AT PARTIAL CELLAR AND GROUND FLOOR LEVEL ONLY. NO CHANGE IN USE OCCUPANCY OR EGRESS.
M00903549-S4
03/18/2025
Signed off — Alteration
MH WORK DESIGN INCLUDES THE ALTERATION OF EXIXSTING HVAC SYSTEM AND THE INSTALLATION OF ADDITIONAL HVAC ITEMS INCLUDING FANS, DUCTWOR AND DUCTWORK ACCESORIES Installation of commercial kitchen and hood and duct ventilation system as per plans filed
M00940454-I1
03/18/2025
Signed off — Alteration
install construction fence as per plans filed.
M01030377-I1
03/18/2025
Signed off — Alteration
INTERIOR RENOVATION (INTERIOR PARTITIONS/ LIGHTING/ LOW-VOLTAGE/ HVAC ALTERATIONS) AT PARTIAL CELLAR AND GROUND FLOOR LEVEL ONLY. NO CHANGE IN USE OCCUPANCY OR EGRESS.
M00903549-S3
02/26/2025
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
02/24/2025
Signed off — Alteration
FACADE RESTORATION AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY
M00578752-I1
01/29/2025
Special inspection requirement — Energy Code Compliance Inspections
JOSEPH MARTINES
01/29/2025
Special inspection requirement — Maintenance information
JOSEPH MARTINES
01/29/2025
Special inspection requirement — HVAC-R and service water heating system controls
JOSEPH MARTINES
01/29/2025
Special inspection requirement — HVAC-R and service water heating equipment
JOSEPH MARTINES
01/29/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
JOSEPH MARTINES
01/29/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
JOSEPH MARTINES
01/29/2025
Special inspection requirement — Final
JOSEPH MARTINES
Latest 60 of 300 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedLOWVOLT TECH ENTERPRISES10/16/2025
DOB NOWPlumbingSigned-offSAMUEL & SONS P & H INC11/04/2024
DOB NOWGeneral ConstructionPermit IssuedCREATIVE HANDS RESTORERS08/08/2024
DOB NOWConstruction FenceSigned-offCREATIVE HANDS RESTORERS05/03/2024
DOB NOWSprinklersSigned-offDOUG'S PLBG & HTG SERV CO04/12/2024
DOB NOWGeneral ConstructionSigned-offTRADITIONAL WATERPROOFING04/02/2024
DOB NOWGeneral ConstructionSigned-offCREATIVE HANDS RESTORERS03/29/2024
DOB NOWSupported ScaffoldPermit IssuedSPRING SCAFFOLDING LLC02/15/2024
DOB NOWSupported ScaffoldSigned-offSPRING SCAFFOLDING LLC02/07/2024
DOB NOWSidewalk ShedSigned-offSPRING SCAFFOLDING LLC01/31/2024
DOB NOWMechanical SystemsSigned-offSAMIRO SERVICES INC01/06/2024
DOB NOWMechanical SystemsSigned-offMIKOMA CONSTRUCTION LLC12/23/2023
DOB NOWStructuralSigned-offCREATIVE HANDS RESTORERS11/08/2023
DOB NOWGeneral ConstructionSigned-offCREATIVE HANDS RESTORERS11/06/2023
DOB NOWMechanical SystemsSigned-offSAMIRO SERVICES INC11/06/2023
DOB NOWPlumbingSigned-offSAMUEL & SONS P & H INC10/10/2023
DOB NOWSidewalk ShedSigned-offMC SUPERSTRUCTURE INC10/10/2023
DOB NOWMechanical SystemsSigned-offMIKOMA CONSTRUCTION LLC09/15/2023
DOB NOWPlumbingSigned-offP.H. WORKS INC09/15/2023
DOB NOWSprinklersSigned-offF.S. WORKS INC09/15/2023
DOB NOWGeneral ConstructionSigned-offCREATIVE HANDS RESTORERS09/12/2023
DOB NOWGeneral ConstructionSigned-offDOLPHIN CONSTRUCTION MANA05/03/2023
DOB NOWSupported ScaffoldSigned-offTRI BOROUGH SCAFFOLDING04/07/2023
DOB NOWGeneral ConstructionSigned-offTRADITIONAL WATERPROOFING03/15/2023
DOB NOWSidewalk ShedSigned-offTRI BOROUGH SCAFFOLDING03/01/2023
DOB NOWSprinklersSigned-offULTIMATE P & H CORP09/07/2022
DOB NOWPlumbingSigned-offULTIMATE PLBG AND HTG COR09/07/2022
DOB NOWSupported ScaffoldSigned-offTRI BOROUGH SCAFFOLDING04/11/2022
DOB NOWGeneral ConstructionSigned-offTRADITIONAL WATERPROOFING03/15/2022
DOB NOWSidewalk ShedSigned-offTRI BOROUGH SCAFFOLDING02/11/2022
DOB NOWGeneral ConstructionSigned-offEMPIRE CORE GROUP LLC12/21/2021
DOB NOWGeneral ConstructionSigned-offEMPIRE CORE GROUP LLC12/21/2021
DOB NOWPlumbingSigned-offT & T PLUMBING INC11/22/2021
DOB NOWPlumbingSigned-offT & T PLUMBING INC11/22/2021
DOB NOWPlumbingSigned-offULTIMATE PLBG AND HTG COR08/16/2021
DOB NOWSprinklersSigned-offULTIMATE P & H CORP08/16/2021
DOB NOWGeneral ConstructionSigned-offDOLPHIN CONSTRUCTION MANA08/11/2021
DOB NOWMechanical SystemsSigned-offDOLPHIN CONSTRUCTION MANA08/11/2021
DOB NOWGeneral ConstructionSigned-offEMPIRE CORE GROUP LLC07/29/2021
DOB NOWGeneral ConstructionSigned-offEMPIRE CORE GROUP LLC07/29/2021
+ 60 more permits on file
1 project · most recent 09/10/2025
Cooling Towers Heating and Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
09/10/2025Signed-offMIKOMA CONSTRUCTION LLCCooling Towers, Heating and Air Conditioning Systems
Heat / Cool
Climatemaster TCH048AHC40CLSS 50,400 BTU · Wshp ×6
TCH060AHC40CPSS 59,500 BTU · Wshp ×4
TCH060AHC40CRSS 59,500 BTU · Wshp ×2
TCH060HC40CRSS 59,500 BTU · Wshp ×2
Cooling Tower
Baltimore Aircoil VTO-032-H 27 tons · Cooling Tower ×2
1 project · most recent 09/10/2025
FiledStatusContractorScope
09/10/2025Signed-offF.S. WORKS INC15 heads
1 project · most recent 09/10/2025
Water/Sanitary
FiledStatusContractorScope
09/10/2025Signed-offP.H. WORKS INCWater/Sanitary
7 projects · most recent 11/09/2025
General Wiring
FiledStatusContractorScope
11/09/2025CompleteJTE ELECTRICAL SERVICESGeneral Wiring
04/22/2025CompleteMIKOMA ELECTRIC LLCGeneral Wiring
03/25/2025CompleteKJK ELECTRIC INCGeneral Wiring
10/30/2023CompleteTOP SHELF ELECTRIC CORP—
05/01/2023CompleteNASH ELECTRIC SERVICES IN—
08/23/2021Permit IssuedALLSTATE ELEC'L CONT INC—
05/27/2021Permit IssuedALL CITY ELECTRICAL INC—
2 projects · most recent 02/14/2024
Scaffold Sidewalk Shed
FiledStatusContractorScope
02/14/2024Permit IssuedSPRING SCAFFOLDING LLCScaffold, Sidewalk Shed
12/20/2018Permit IssuedTRI BOROUGH SCAFFOLDING.&Scaffold
▾Field Inspections (DOB CAP) — 34
DateTypeResultReport
06/05/2026Certified Gas-Gas-Piping-RoughingCertifiedView ↗
02/02/2026Pass-Final CND-Occupancy InspectionPassView ↗
01/07/2026Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
01/07/2026Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
12/30/2025Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
12/30/2025Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
10/27/2025Certified Storm Drainage-ST-Fixtures-FinishCertifiedView ↗
10/22/2025Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
09/04/2025Pass-Final CND-Occupancy InspectionPassView ↗
05/07/2025Pass-Final CND-Occupancy InspectionPassView ↗
02/26/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
09/13/2024Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
09/11/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
05/14/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
05/08/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
04/29/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
04/17/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
03/05/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
01/04/2024Pass-Final SP - Up to 3 Requested FloorsPassView ↗
01/02/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
01/02/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
12/28/2023Pass-Final PL - UndergroundPassView ↗
09/15/2022Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
06/16/2022Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
06/16/2022Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
Latest 25 of 34.
▾Special Inspection Requirements (DOB NOW) — 107
DateRequirementInspectorRole
05/25/2026Tenant Protection Plan Compliance—special
05/25/2026Fire-Resistant Penetrations and JointsJOSEPH MARTINESspecial
05/25/2026Fire-Resistance Rated ConstructionJOSEPH MARTINESprogress
05/07/2026Tenant Protection Plan Compliance—special
05/05/2026Fire-Resistant Penetrations and JointsJOSEPH MARTINESspecial
05/05/2026Fire-Resistance Rated ConstructionJOSEPH MARTINESprogress
09/15/2025FinalMax Leeprogress
09/15/2025Heating SystemsMax Leespecial
09/15/2025Tenant Protection Plan ComplianceMax Leespecial
09/15/2025Mechanical SystemsMax Leespecial
09/11/2025Heating SystemsMax Leespecial
09/11/2025Tenant Protection Plan ComplianceMax Leespecial
07/21/2025Fire-Resistance Rated ConstructionJOSEPH MARTINESprogress
07/21/2025Fire-Resistant Penetrations and JointsJOSEPH MARTINESspecial
07/21/2025Tenant Protection Plan Compliance—special
06/23/2025Tenant Protection Plan ComplianceMax Leespecial
06/23/2025FinalMax Leeprogress
06/23/2025Mechanical SystemsMax Leespecial
06/23/2025Heating SystemsMax Leespecial
04/09/2025Tenant Protection Plan Compliance—special
04/07/2025Fire-Resistance Rated ConstructionJOSEPH MARTINESprogress
04/07/2025Fire-Resistant Penetrations and JointsJOSEPH MARTINESspecial
01/29/2025Maintenance informationJOSEPH MARTINESenergy_progress
01/29/2025FinalJOSEPH MARTINESprogress
01/29/2025Tenant Protection Plan ComplianceJOSEPH MARTINESspecial
Latest 25 of 107.
▾Documents — 704 on file (BIS + DOB NOW)
▸Plans & Drawings50
▸DOB NOWPlans/Sketch41
09/06/2026M00045668-I1Request digital key ↗
09/03/2026M00504631-I1Request digital key ↗
09/03/2026M00504632-I1Request digital key ↗
Showing 3 of 41 on file for this type
▸DOB NOWPlans/Sketch - Sidewalk Shed5
09/05/2026M00312324-P4Request digital key ↗
09/05/2026M00312324-P5Request digital key ↗
09/05/2026M00312324-I1Request digital key ↗
Showing 3 of 5 on file for this type
▸DOB NOWPlans/Sketch - Supported Scaffold3
09/06/2026M00112464-I1Request digital key ↗
09/05/2026M00125536-I1Request digital key ↗
09/05/2026M00312326-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Place of Assembly1
08/25/2026M01056747-I1Request digital key ↗
▸Applications & Permits129
▸BISPLAN / WORK APPROVAL APPLICATION51
10/31/2022123379272Open ↗
01/27/2022123379272Open ↗
12/30/2020140994002Open ↗
Showing 3 of 51 on file for this type
▸BISWORK PERMIT APPLICATION48
12/09/2022140621183Open ↗
01/27/2022123379272Open ↗
11/16/2021140621183Open ↗
Showing 3 of 48 on file for this type
▸DOB NOWLPC Approval/Permit30
09/03/2026M00504632-I1Open ↗
09/03/2026M00504634-I1Open ↗
09/02/2026M00578752-I1Open ↗
Showing 3 of 30 on file for this type
▸Seals & Professional Certifications207
▸DOB NOWSpecial Inspector Seal & Signature50
09/28/2026M00543090-I1Open ↗
09/07/2026M00929486-I1Open ↗
09/02/2026M00903549-P2Open ↗
Showing 3 of 50 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature50
09/05/2026M00312326-I1Open ↗
09/05/2026M00312324-P1Open ↗
09/05/2026M00312324-P2Open ↗
Showing 3 of 50 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION34
02/05/2021140993986Open ↗
02/05/2021140993986Open ↗
06/24/2019140384251Open ↗
Showing 3 of 34 on file for this type
▸DOB NOWProgress Inspector Seal & Signature33
09/07/2026M00929486-I1Open ↗
09/01/2026M00940454-I1Open ↗
08/31/2026M00578752-I1Open ↗
Showing 3 of 33 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT16
12/30/2020140994002Open ↗
12/29/2020140993986Open ↗
05/13/2019123659763Open ↗
Showing 3 of 16 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST9
05/13/2019123659763Open ↗
03/25/2019123659772Open ↗
10/22/2018123484372Open ↗
Showing 3 of 9 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION7
12/30/2020140994002Open ↗
12/29/2020140993986Open ↗
Showing 2 of 7 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY7
12/30/2020140994002Open ↗
12/29/2020140993986Open ↗
Showing 2 of 7 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Trade Schedules & Equipment24
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE11
05/13/2019123659763Open ↗
03/25/2019123659772Open ↗
02/16/2018123205325Open ↗
Showing 3 of 11 on file for this type
▸BISSELF-CERT PLUMBING NOTICE5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISSCHEDULE B - PLUMBING4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISBOILERS - SUPPORTING DOCUMENTATION2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Safety & Tenant Protection23
▸BISTenant Protection Plan and Notes12
02/05/2021140993986Open ↗
05/13/2019123659763Open ↗
03/25/2019123659772Open ↗
Showing 3 of 12 on file for this type
▸DOB NOWTenant Protection Plan6
09/05/2026M00312326-I1Open ↗
09/05/2026M00312324-P4Open ↗
09/05/2026M00312324-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWStreet Tree Checklist4
08/14/2026M00909782-P4Open ↗
Showing 1 of 4 on file for this type
▸BISTPP1: TENANT PROTECTION PLAN1
02/11/2021140994002Open ↗
▸Environmental & Asbestos53
▸DOB NOWDEP ACP-5: Asbestos Assessment Report35
09/03/2026M00504632-I1Open ↗
09/03/2026M00504634-I1Open ↗
09/03/2026M00543090-I1Open ↗
Showing 3 of 35 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)16
12/30/2020140994002Open ↗
12/29/2020140993986Open ↗
05/13/2019123659763Open ↗
Showing 3 of 16 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Energy Compliance35
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS17
05/13/2019123659763Open ↗
03/26/2019123484372Open ↗
03/25/2019123659772Open ↗
Showing 3 of 17 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS5
10/25/2023123379272Open ↗
03/26/2019123484372Open ↗
01/08/2019123395511Open ↗
Showing 3 of 5 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY3
10/25/2023123379272Open ↗
02/11/2021140994002Open ↗
Showing 2 of 3 on file for this type
▸BISELECTRICAL APPLICATION FOR SIDEWALK SHED LIGHTING3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISNYCECC EXEMPTION2
12/30/2020140994002Open ↗
12/29/2020140993986Open ↗
▸DOB NOWEN2: As Built Energy Analysis.2
09/03/2026M00504634-I1Open ↗
Showing 1 of 2 on file for this type
▸BISTR8: Energy Code Progress Inspections1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISTECHNICAL REPORT: ENERGY1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Inspections & Test Reports11
▸BISTECHNICAL REPORT: RESPONSIBILITY8
10/25/2023123379272Open ↗
02/11/2021140994002Open ↗
02/11/2021140994002Open ↗
Showing 3 of 8 on file for this type
▸BISCONCRETE DESIGN MIX (TR-3) 27-6051
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Approvals, Objections & Sign-offs62
▸BISLANDMARKS APPROVAL24
12/30/2020140994002Open ↗
12/29/2020140993986Open ↗
05/13/2019123659763Open ↗
Showing 3 of 24 on file for this type
▸BISSHED LETTER11
12/09/2022140621183Open ↗
12/09/2022140621183Open ↗
11/16/2021140621183Open ↗
Showing 3 of 11 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION9
03/13/2019123395511Open ↗
03/12/2019123395511Open ↗
02/13/2019123395511Open ↗
Showing 3 of 9 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST9
03/21/2024140621183Open ↗
10/26/2023123379272Open ↗
06/24/2019140384251Open ↗
Showing 3 of 9 on file for this type
▸BISLANDMARKS SIGNOFF4
03/21/2024140131783Open ↗
03/21/2024140621183Open ↗
10/25/2023123379272Open ↗
Showing 3 of 4 on file for this type
▸BISADMINISTRATIVE OBJECTIONS3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISSUPERSEDING LETTER2
11/26/2019122896223Open ↗
04/25/2019140384251Open ↗
▸Cost, Insurance & Ownership26
▸BISCOST AFFIDAVIT25
10/25/2023123379272Open ↗
12/30/2020140994002Open ↗
12/29/2020140993986Open ↗
Showing 3 of 25 on file for this type
▸BISHIC LICENSE OR AFFIDAVIT1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Filing & Intake Forms54
▸BISBOROUGH INTAKE FORM20
12/09/2022140621183Open ↗
11/16/2021140621183Open ↗
02/05/2021140994002Open ↗
Showing 3 of 20 on file for this type
▸BISEFILING COVER SHEET13
05/13/2019123659763Open ↗
03/25/2019123659772Open ↗
10/22/2018123484372Open ↗
Showing 3 of 13 on file for this type
▸BISADDITIONAL INFORMATION13
12/20/2022123379272Open ↗
02/05/2021140993986Open ↗
12/30/2020140994002Open ↗
Showing 3 of 13 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET8
12/30/2020140994002Open ↗
12/29/2020140993986Open ↗
Showing 2 of 8 on file for this type
▸Other Documents30
▸DOB NOWProof of Historic Building13
08/31/2026M00843662-I1Open ↗
08/27/2026M00870129-I1Open ↗
Showing 2 of 13 on file for this type
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION9
12/09/2022140621183Open ↗
12/09/2022140621183Open ↗
11/16/2021140621183Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWDHCR Document4
09/05/2026M00312324-P4Open ↗
09/05/2026M00312324-I1Open ↗
Showing 2 of 4 on file for this type
▸DOB NOWProperty Ownership Certification4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type