RoofSuspended scaffold system for facade restoration3p · 1 filing · 3 docs
Equipment
SUSPENDED SCAFFOLD OUTRIGGER SYSTEM AT 332 EAST 19 STREET MANHATTAN 10003 FOR EXTERIOR FACADE RESTORATION WORK.
On file for this project
3 documents · 3 drawing sheets
Floor 6Cosmetic work in 1st-6th floor hallways30p · 5 filings · 20 docs
ArchitectureDMGeneralMechanicalPlumbing
Issued Permit Scope
General Construction · Plumbing
Interior renovation as shown on plans filed herewith.
On file for this project
3 documents · 4 drawing sheets
Interior renovation as shown on plans filed herewith.
On file for this project
4 documents · 4 drawing sheets
Installation, relocation, removal of plumbing fixtures.
On file for this project
6 documents · 1 drawing sheet
Latest 3 of 5 filings on this floor.
Floor 5Cosmetic work in 1st-6th floor hallways32p · 5 filings · 20 docs
ArchitectureDMGeneralMechanicalPlumbing
Issued Permit Scope
General Construction · Plumbing
Interior renovation as shown on plans filed herewith.
On file for this project
3 documents · 4 drawing sheets
Interior renovation as shown on plans filed herewith.
On file for this project
14 documents · 9 drawing sheets
Installation, relocation, removal of plumbing fixtures as shown plans filed herewith.
On file for this project
8 documents · 3 drawing sheets
Latest 3 of 5 filings on this floor.
Floor 4Cosmetic work in 1st-6th floor hallways24p · 5 filings · 20 docs
ArchitectureDMGeneralPlumbing
Issued Permit Scope
General Construction · Plumbing
Interior renovation as shown on plans filed herewith.
On file for this project
3 documents · 4 drawing sheets
Interior renovation as shown on plans filed herewith.
On file for this project
14 documents · 2 drawing sheets
Installation, relocation, removal of plumbing fixtures as shown plans filed herewith.
On file for this project
8 documents
Latest 3 of 5 filings on this floor.
Floor 3Cosmetic work in 1st-6th floor hallways21p · 5 filings · 20 docs
ArchitectureDMGeneralPlumbing
Issued Permit Scope
General Construction · Plumbing
Interior renovation as shown on plans filed herewith.
On file for this project
3 documents · 4 drawing sheets
Installation, relocation, removal of plumbing fixtures.
On file for this project
6 documents
Interior renovation as shown on plans filed herewith.
On file for this project
12 documents
Latest 3 of 5 filings on this floor.
Floor 2Cosmetic work in 1st-6th floor hallways28p · 5 filings · 20 docs
ArchitectureDMGeneralPlumbing
Issued Permit Scope
General Construction · Plumbing
Interior renovation as shown on plans filed herewith.
On file for this project
3 documents · 4 drawing sheets
Installation, relocation, removal of plumbing fixtures.
On file for this project
6 documents
Interior renovation as shown on plans filed herewith.
On file for this project
12 documents
Latest 3 of 5 filings on this floor.
Floor 1Cosmetic work in 1st-6th floor hallways22p · 6 filings · 20 docs
ArchitectureDMEquipmentGeneralLandscapeMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Plumbing · Sidewalk Shed · Supported Scaffold
Interior renovation as shown on plans filed herewith.
On file for this project
3 documents · 4 drawing sheets
INSTALLATION OF 300PSF SIDEWALK SHED AND PIPE SCAFFOLDING AS PER PLANS. ALL EQUIPMENT SHALL COMPLY WITH CH #33 OF THE NYC CODE 2022. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
2 documents
Installation, replacement and relocation of plumbing fixtures.
On file for this project
4 documents
Latest 3 of 6 filings on this floor.
CellarBoiler room and tenant protection22p · 5 filings · 20 docs
ArchitectureDMGeneralMechanicalPlumbing
Issued Permit Scope
Boiler Equipment · General Construction · Plumbing
REPLACE BOILER AND GAS/OIL BURNER.
On file for this project
10 documents
GAS CONNECTION TO REPLACEMENT GAS/OIL BURNER.
On file for this project
3 documents
Installation, replacement and relocation of plumbing fixtures.
On file for this project
4 documents · 1 drawing sheet
Latest 3 of 5 filings on this floor.
Site & exteriorDemolition12p · 4 filings · 18 docs
ArchitectureStructural
Issued Permit Scope
Foundation · General Construction · Structural
1. BRICK JOINT RE-POINTING AT REAR OF THE BUILDING=40,000 SF 2. WINDOWSILLS REPLACEMENT APPROXIMATELY =15 PCS
On file for this project
3 documents · 5 drawing sheets
TEMPORARY SHORING OF EXISTING RUBBLE RETAINING WALL. WORK FILED IN CONJUNCTION WITH EMERGENCY WORK VIOLATION # 16917 AND TO RESOLVE ECB VIOLATION 39062396M & 39062395K
On file for this project
5 documents · 5 drawing sheets
Propose new retaining wall at rear yard
On file for this project
7 documents · 7 drawing sheets
Latest 3 of 4 filings on this floor.