| Owner | Filings | Most Recent |
|---|---|---|
| MJH CONSTRUCTION | 75 | 07/08/2026 |
| PORTLAND RESIDENCE LLC | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 06/09/2022 | $900K | — | Private party → PORTLAND RESIDENCE LLC | $108/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| VASILIOS ARTEMIOU PE | 9 | 05/13/2024 |
| SANDER WILLIAMS ARCHITECT PC | 7 | 05/10/2024 |
| FL&M ENGINEERING DESIGN &INSPECTION | 1 | 02/03/2023 |
| R & O ENGINEERING | 6 | 01/09/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| NYC DESIGN FILE | 22 | 03/21/2026 |
| GREEN STUDIO | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| MJH CONSTRUCTION CORP | General Contractor | 17 | 07/08/2026 |
| PRIME PIPING & HEATING IN | Plumbing | 2 | 07/08/2026 |
| SOLAS ELECTRICAL CORP | Electrical | 1 | 03/22/2026 |
| PRIME PIPING & HEATING IN | Fire Protection | 1 | 07/08/2026 |
| MANHATTAN D ENTERPRISES | General Contractor | 1 | 07/08/2026 |
| MPI PLUMBING CORP | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| REGIONAL TESTING CORP. | 394 | 22 | 05/10/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | PRIME PIPING & HEATING IN | 04/17/2024 |
| DOB NOW | Mechanical Systems | Signed-off | MJH CONSTRUCTION CORP | 06/22/2023 |
| DOB NOW | General Construction | Permit Issued | MJH CONSTRUCTION CORP | 06/16/2023 |
| DOB NOW | Construction Fence | Signed-off | MJH CONSTRUCTION CORP | 05/18/2023 |
| DOB NOW | Sprinklers | Signed-off | A M B MECHANICAL INC | 03/27/2023 |
| DOB NOW | Plumbing | Signed-off | YG SERVICES INC | 03/08/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | MANHATTAN D ENTERPRISES | 02/03/2023 |
| DOB NOW | General Construction | Permit Issued | MJH CONSTRUCTION CORP | 10/20/2022 |
| DOB NOW | Foundation | Permit Issued | MJH CONSTRUCTION CORP | 10/07/2022 |
| DOB NOW | General Construction | Permit Issued | MJH CONSTRUCTION CORP | 08/16/2022 |
| DOB NOW | Structural | Signed-off | MJH CONSTRUCTION CORP | 07/27/2022 |
| DOB NOW | Foundation | Signed-off | MJH CONSTRUCTION CORP | 05/26/2022 |
| DOB NOW | Construction Fence | Signed-off | MJH CONSTRUCTION CORP | 05/20/2022 |
| BIS | EQ | ISSUED | CHESAKL ENTERPRISES INC | 10/31/2022 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 05/10/2024 | Signed-off | MJH CONSTRUCTION CORP | Air Conditioning Systems, Associated Ducts and Piping, Heating Systems, Ventilation Systems | Cooling Daikin 5mxs48tvju 48,000 BTU · Condensing Unit ×3 Heating Daikin 5MXS48TVJU 48,000 BTU ×3 Ventilation Ducts & Piping Masterflow ducts Ductwork ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/10/2024 | Signed-off | YG SERVICES INC | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/17/2023 | Complete | S&R ELECTRICAL & MECHANIC | General Wiring |
| 01/30/2023 | Complete | SOLAS ELECTRICAL CORP | — |
| 10/28/2022 | Complete | POWER DIRECT ELECTRIC INC | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/10/2024 | Signed-off | MJH CONSTRUCTION CORP | Concrete |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/10/2024 | Signed-off | MJH CONSTRUCTION CORP | Fence |
| Date | Type | Result | Report |
|---|---|---|---|
| 06/01/2026 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 05/17/2024 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 05/16/2024 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 05/09/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 05/09/2024 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 11/21/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 11/20/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 11/17/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 11/13/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 06/15/2023 | Pass-Final PL - Underground | Pass | View ↗ |
| 06/14/2023 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 05/08/2023 | Pass-Final PL - Underground | Pass | View ↗ |
| 05/03/2023 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 03/17/2023 | Pass-Final PL - Underground | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/17/2024 | Structural Stability – Alterations of existing buildings | Paul Raymond | special |
| 05/17/2024 | Exterior Insulation and Finish Systems (EIFS) | Paul Raymond | special |
| 05/17/2024 | Wall Panels, Curtain Walls, and Veneers | Paul Raymond | special |
| 05/17/2024 | Fire-Resistant Penetrations and Joints | Paul Raymond | special |
| 05/17/2024 | Energy Code Compliance Inspections | Paul Raymond | progress |
| 05/17/2024 | Exterior lighting power | Paul Raymond | energy_progress |
| 05/17/2024 | Maintenance information | Paul Raymond | energy_progress |
| 05/17/2024 | Lighting controls | Paul Raymond | energy_progress |
| 05/17/2024 | Air barrier - visual inspection | Paul Raymond | energy_progress |
| 05/17/2024 | Insulation placement and R values | Paul Raymond | energy_progress |
| 05/17/2024 | Metering | Paul Raymond | energy_progress |
| 05/17/2024 | Electrical motors and elevators | Paul Raymond | energy_progress |
| 05/17/2024 | Fenestration areas | Paul Raymond | energy_progress |
| 05/17/2024 | Interior lighting power | Paul Raymond | energy_progress |
| 05/17/2024 | Fenestration and door U-factor and product ratings | Paul Raymond | energy_progress |
| 05/17/2024 | Fenestration air leakage | Paul Raymond | energy_progress |
| 05/17/2024 | Lighting in dwelling units | Paul Raymond | energy_progress |
| 05/17/2024 | Structural Stability – Alterations of existing buildings | Paul Raymond | special |
| 05/17/2024 | Wall Panels, Curtain Walls, and Veneers | Paul Raymond | special |
| 05/17/2024 | Exterior Insulation and Finish Systems (EIFS) | Paul Raymond | special |
| 05/17/2024 | Fire-Resistant Penetrations and Joints | Paul Raymond | special |
| 05/17/2024 | Energy Code Compliance Inspections | Paul Raymond | progress |
| 05/17/2024 | Electrical motors and elevators | Paul Raymond | energy_progress |
| 05/17/2024 | Fenestration and door U-factor and product ratings | Paul Raymond | energy_progress |
| 05/17/2024 | Fenestration air leakage | Paul Raymond | energy_progress |