| Owner | Filings | Most Recent |
|---|---|---|
| 334 BEDFORD AVE LLC | 1 | 03/22/2026 |
| SUCCESS DEVELOPERS | 2 | 03/22/2026 |
| HILJO REALTY | 2 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 12/12/2022 | $3.0M | — | HILJO REALTY CORP. → 334 BEDFORD AVE LLC | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| KAO HWA LEE ARCHITECTS PC | 17 | 12/19/2024 |
| FL&M ENGINEERING DESIGN &INSPECTION | 1 | 07/12/2023 |
| STRUCTURAL ENGINEERING TECHNOLOGIES | 1 | 05/31/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| SUNSHINE PLAZA LLC | 18 | 03/21/2026 |
| GREEN STUDIO | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| SUCCESS DEVELOPERS LLC | General Contractor | 36 | 07/08/2026 |
| MANHATTAN D ENTERPRISES | General Contractor | 6 | 03/21/2026 |
| SUNSHINE CONSTR USA INC | General Contractor | 2 | 03/21/2026 |
| GWT ENTERPRISES INC | General Contractor | 2 | 07/08/2026 |
| M.R. ELEC'L SERVICE LLC | Electrical | 1 | 03/22/2026 |
| ARIEL SERVICES INC | Plumbing | 1 | 07/08/2026 |
| POWER DIRECT ELECTRIC INC | Electrical | 1 | 03/22/2026 |
| SOLAS ELECTRICAL CORP | Electrical | 1 | 03/22/2026 |
| METFLOW FIRE CONTROL LLC | Fire Protection | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| HRF SERVICES CORP | 5616 | 16 | 12/19/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sprinklers | Signed-off | METFLOW FIRE CONTROL LLC | 02/07/2024 |
| DOB NOW | Plumbing | Signed-off | DG MECHANICAL HEATING INC | 02/06/2024 |
| DOB NOW | Mechanical Systems | Signed-off | SUCCESS DEVELOPERS LLC | 01/29/2024 |
| DOB NOW | Earth Work | Signed-off | SUCCESS DEVELOPERS LLC | 01/12/2024 |
| DOB NOW | Foundation | Signed-off | SUCCESS DEVELOPERS LLC | 01/12/2024 |
| DOB NOW | Support of Excavation | Signed-off | SUCCESS DEVELOPERS LLC | 01/12/2024 |
| DOB NOW | Structural | Signed-off | SUCCESS DEVELOPERS LLC | 01/12/2024 |
| DOB NOW | General Construction | Permit Issued | SUCCESS DEVELOPERS LLC | 01/11/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | GWT ENTERPRISES INC | 01/09/2024 |
| DOB NOW | Supported Scaffold | Signed-off | GWT ENTERPRISES INC | 01/09/2024 |
| DOB NOW | Support of Excavation | Signed-off | SUCCESS DEVELOPERS LLC | 12/14/2023 |
| DOB NOW | Construction Fence | Signed-off | SUCCESS DEVELOPERS LLC | 12/14/2023 |
| DOB NOW | Foundation | Signed-off | SUCCESS DEVELOPERS LLC | 11/16/2023 |
| DOB NOW | Earth Work | Signed-off | SUCCESS DEVELOPERS LLC | 11/09/2023 |
| DOB NOW | Construction Fence | Signed-off | SUCCESS DEVELOPERS LLC | 10/25/2023 |
| DOB NOW | Supported Scaffold | Signed-off | MANHATTAN D ENTERPRISES | 07/12/2023 |
| DOB NOW | Supported Scaffold | Signed-off | MANHATTAN D ENTERPRISES | 07/12/2023 |
| DOB NOW | Structural | Signed-off | SUCCESS DEVELOPERS LLC | 05/11/2023 |
| DOB NOW | Earth Work | Signed-off | SUCCESS DEVELOPERS LLC | 03/02/2023 |
| DOB NOW | Support of Excavation | Signed-off | SUCCESS DEVELOPERS LLC | 02/09/2023 |
| DOB NOW | Foundation | Signed-off | SUCCESS DEVELOPERS LLC | 11/10/2022 |
| DOB NOW | Construction Fence | Signed-off | SUCCESS DEVELOPERS LLC | 11/04/2022 |
| DOB NOW | Foundation | Signed-off | SUNSHINE CONSTR USA INC | 06/03/2022 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/03/2024 | Complete | M.R. ELEC'L SERVICE LLC | General Wiring |
| 02/02/2024 | Complete | POWER DIRECT ELECTRIC INC | — |
| 12/18/2023 | Complete | M.R. ELEC'L SERVICE LLC | General Wiring |
| 07/09/2023 | Complete | SOLAS ELECTRICAL CORP | — |
| 01/20/2023 | Complete | HIVOLTS ELECTRICAL INC | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 03/25/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 12/26/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 05/21/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 05/16/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 03/15/2024 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 02/15/2024 | Pass-Final PL - Underground | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 12/24/2024 | Air barrier - visual inspection | FAHAD FATEH | energy_progress |
| 12/24/2024 | Fenestration air leakage | FAHAD FATEH | energy_progress |
| 12/24/2024 | Fenestration and door U-factor and product ratings | FAHAD FATEH | energy_progress |
| 12/24/2024 | Exterior lighting power | FAHAD FATEH | energy_progress |
| 12/24/2024 | Maintenance information | FAHAD FATEH | energy_progress |
| 12/24/2024 | Interior lighting power | FAHAD FATEH | energy_progress |
| 12/24/2024 | Fenestration areas | FAHAD FATEH | energy_progress |
| 12/24/2024 | Lighting controls | FAHAD FATEH | energy_progress |
| 12/24/2024 | Insulation placement and R values | FAHAD FATEH | energy_progress |
| 12/24/2024 | Metering | FAHAD FATEH | energy_progress |
| 12/24/2024 | Electrical motors and elevators | FAHAD FATEH | energy_progress |
| 12/24/2024 | Fire-Resistance Rated Construction | FAHAD FATEH | progress |
| 12/24/2024 | Energy Code Compliance Inspections | FAHAD FATEH | progress |
| 12/24/2024 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 12/24/2024 | Subgrade Inspections | FAHAD FATEH | special |
| 12/24/2024 | Exterior Insulation and Finish Systems (EIFS) | FAHAD FATEH | special |
| 12/24/2024 | Subsurface Investigations (Borings/Test Pits) | Daniel Boss | special |
| 12/24/2024 | Concrete - Cast-In-Place | FAHAD FATEH | special |
| 12/24/2024 | Lighting in dwelling units | FAHAD FATEH | energy_progress |
| 12/19/2024 | Fenestration areas | FAHAD FATEH | energy_progress |
| 12/19/2024 | Lighting in dwelling units | FAHAD FATEH | energy_progress |
| 12/19/2024 | Maintenance information | FAHAD FATEH | energy_progress |
| 12/19/2024 | Air barrier - visual inspection | FAHAD FATEH | energy_progress |
| 12/19/2024 | Exterior lighting power | FAHAD FATEH | energy_progress |
| 12/19/2024 | Fenestration air leakage | FAHAD FATEH | energy_progress |