← Back
Five to six families
336 MANHATTAN AVENUE
BROOKLYN · BIN 3068587
💬 Discuss this project
1930Year Built
3Stories
C2Building Class
R6BZoning
3,750 sfGross Floor Area
6Units
Rent Stabilized1 Open Violation ▸FDNY Report ↗
Five to six families · Owner of record: 336 MANHATTAN AVE LLC · 1,875 sf lot · 2 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbing
Permit Issued — active, not yet Signed-off
Floor 3Under Construction10p · 2 filings · 20 docs
Floor 2Under Construction21p · 2 filings · 20 docs
Floor 1Under Construction22p · 2 filings · 20 docs
CellarUnder Construction24p · 2 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
228 SEVENTH AVE2009/12/2026
RELIABLE ENTERPRISE INC904/09/2026
JB CONSTRUCTION DESIGN503/22/2026
336 MANHATTAN AVE LLC103/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
12/30/2024$1.9M—— → —$493/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
CONSULTING ENGINEER705/26/2026
PRAMODRAY SHAH, P.E.101/06/2026
MJE PROFESSIONAL SERVICES211/14/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
NAPHTALI DEUTSCH ARCHITECTURE603/21/2026
SNR EXPEDITING DESIGN403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
JB CONSTRUCTION & DESIGNGeneral Contractor704/09/2026
RELIABLE ENTERPRISES INCGeneral Contractor304/09/2026
VILLAGE P & H NY INCPlumbing106/28/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
CONSULTING ENGINEER5093605/26/2026
SHAHRISH SHUVO ENGINEERIN8524101/06/2026
Building Lifecycle
All (28)Filed (10)Objection (18)
05/31/2026
Objection resolved — Addressed
05/29/2026
Objection raised — Cost
05/26/2026
Filed — Alteration
THIS APPLICATION IS BEING FILED FOR THE INSTALLATION OF KITCHEN & TOILET EXHAUST FANS, (6) NEW HEAT PUMPS AT REAR YARD AND RELATED AIR HANDLING UNITS FROM CELLAR THROUGH THIRD FLOOR.
B01156573-P3
01/21/2026
Objection resolved — Addressed
01/12/2026
Objection raised — Scope
01/06/2026
Filed — Alteration
STRUCTURAL APPLICATION FILED TO REBUILD THE EXPOSURE 3 EXTERIOR WALL WITH CMU. NO CHANGE IN EGRESS, USE OR OCCUPANCY UNDER THIS APPLICATION.
B01342833-I1
01/02/2026
Filed — Alteration
THIS APPLICATION IS BEING FILED FOR THE INSTALLATION OF KITCHEN & TOILET EXHAUST FANS, (6) NEW HEAT PUMPS AT REAR YARD AND RELATED AIR HANDLING UNITS FROM CELLAR THROUGH THIRD FLOOR.
B01156573-P2
12/19/2025
Filed — Alteration
THIS APPLICATION IS BEING FILED FOR THE INSTALLATION OF KITCHEN & TOILET EXHAUST FANS, (6) NEW HEAT PUMPS AT REAR YARD AND RELATED AIR HANDLING UNITS FROM CELLAR THROUGH THIRD FLOOR.
B01156573-S1
11/14/2025
Filed — Alteration
B01319407-I1
11/14/2025
Filed — Alteration
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
B01319431-I1
08/01/2025
Filed — Alteration
THIS APPLICATION IS BEING FILED FOR PLUMBING WORK IN CONJUNCTION WITH GENERAL CONSTRUCTION & STRUCTURAL UNDER APPLICATION #B01156573 WORK TO RENOVATE & REPAIR EXISTING BUILDING
B01167561-P1
03/22/2025
Objection resolved — Addressed
03/13/2025
Objection raised — Scope
03/10/2025
Filed — Alteration
THIS APPLICATION IS BEING FILED FOR THE INSTALLATION OF KITCHEN & TOILET EXHAUST FANS, (6) NEW HEAT PUMPS AT REAR YARD AND RELATED AIR HANDLING UNITS FROM CELLAR THROUGH THIRD FLOOR.
B01156573-P1
02/11/2025
Objection resolved — Addressed
02/11/2025
Objection resolved — Addressed
02/11/2025
Objection resolved — Addressed
02/03/2025
Objection raised — Plumbing
02/03/2025
Objection raised — Plumbing
02/03/2025
Objection raised — Plumbing
01/30/2025
Objection resolved — Addressed
01/29/2025
Filed — Alteration
THIS APPLICATION IS BEING FILED FOR PLUMBING WORK IN CONJUNCTION WITH GENERAL CONSTRUCTION & STRUCTURAL UNDER APPLICATION #B01156573 WORK TO RENOVATE & REPAIR EXISTING BUILDING
B01167561-I1
01/15/2025
Objection resolved — Addressed
01/15/2025
Objection resolved — Addressed
01/09/2025
Objection raised — Scope
01/09/2025
Objection raised — Fire_Protection
01/09/2025
Objection raised — Inspections
01/04/2025
Filed — Alteration
THIS APPLICATION IS BEING FILED FOR THE INSTALLATION OF KITCHEN & TOILET EXHAUST FANS, (6) NEW HEAT PUMPS AT REAR YARD AND RELATED AIR HANDLING UNITS FROM CELLAR THROUGH THIRD FLOOR.
B01156573-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsPermit IssuedJB CONSTRUCTION DESIGN02/18/2026
DOB NOWStructuralSigned-offJB CONSTRUCTION DESIGN01/21/2026
DOB NOWSupported ScaffoldPermit IssuedRELIABLE ENTERPRISES INC11/17/2025
DOB NOWSidewalk ShedPermit IssuedRELIABLE ENTERPRISES INC11/17/2025
DOB NOWGeneral ConstructionPermit IssuedJB CONSTRUCTION DESIGN10/31/2025
DOB NOWPlumbingSigned-offVILLAGE P & H NY INC08/22/2025
DOB NOWStructuralPermit IssuedJB CONSTRUCTION DESIGN07/29/2025
DOB NOWGeneral ConstructionPermit IssuedJB CONSTRUCTION DESIGN04/07/2025
1 project · most recent 05/26/2026
Heating and Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
05/26/2026Permit IssuedJB CONSTRUCTION & DESIGNHeating and Air Conditioning Systems
Heat / Cool
Mitsubishi Electric MXZ-3C30NA3 36,000 BTU · Heat Pump Outdoor ×4
MXZ-5C42NA4 53,600 BTU · Heat Pump Outdoor ×2
1 project · most recent 08/01/2025
Gas Water/Sanitary
FiledStatusContractorScope
08/01/2025Signed-offVILLAGE P & H NY INCGas, Water/Sanitary
2 projects · most recent 11/17/2025
General Wiring
FiledStatusContractorScope
11/17/2025Permit IssuedRICHARD NEU—
09/11/2025Permit IssuedBLU ELECTRICAL SVS INCGeneral Wiring
2 projects · most recent 05/26/2026
Steel Wood Masonry
FiledStatusContractorScope
05/26/2026Permit IssuedJB CONSTRUCTION & DESIGNSteel, Wood
01/06/2026Signed-offJB CONSTRUCTION & DESIGNMasonry
1 project · most recent 11/14/2025
Scaffold
FiledStatusContractorScope
11/14/2025Permit IssuedRELIABLE ENTERPRISES INCScaffold
▾Field Inspections (DOB CAP) — 4
DateTypeResultReport
09/22/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
09/22/2025Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
09/16/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
09/16/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 53
DateRequirementInspectorRole
04/26/2026Tenant Protection Plan Compliance—special
04/24/2026HVAC-R and service water heating system controlsJohn Natolienergy_progress
04/24/2026HVAC-R and service water piping design and insulationJohn Natolienergy_progress
04/24/2026HVAC-R and service water heating equipmentJohn Natolienergy_progress
04/24/2026Fire-Resistance Rated ConstructionJohn Natoliprogress
04/24/2026FinalJohn Natoliprogress
04/24/2026Energy Code Compliance InspectionsJohn Natoliprogress
04/24/2026Mechanical SystemsJohn Natolispecial
04/24/2026Maintenance informationJohn Natolienergy_progress
04/24/2026Fire-Resistant Penetrations and JointsJohn Natolispecial
01/28/2026MeteringJohn Natolienergy_progress
01/28/2026Fenestration areasJohn Natolienergy_progress
01/28/2026Fire-Resistant Penetrations and JointsJohn Natolispecial
01/28/2026Fenestration and door U-factor and product ratingsJohn Natolienergy_progress
01/28/2026Lighting in dwelling unitsJohn Natolienergy_progress
01/28/2026Structural Stability – Alterations of existing buildingsJohn Natolispecial
01/28/2026Exterior Insulation and Finish Systems (EIFS)John Natolispecial
01/28/2026Structural Steel - DetailsJohn Natolispecial
01/28/2026Energy Code Compliance InspectionsJohn Natoliprogress
01/28/2026Fire-Resistance Rated ConstructionJohn Natoliprogress
01/28/2026FinalJohn Natoliprogress
01/28/2026Air barrier - visual inspectionJohn Natolienergy_progress
01/28/2026Insulation placement and R valuesJohn Natolienergy_progress
01/28/2026Fenestration air leakageJohn Natolienergy_progress
01/06/2026MasonryShahrish Shuvospecial
Latest 25 of 53.
▾Documents — 51 on file (BIS + DOB NOW)
▸Plans & Drawings9
▸DOB NOWPlans/Sketch9
08/21/2026B01167561-P1Request digital key ↗
08/21/2026B01167561-I1Request digital key ↗
08/19/2026B01319431-I1Request digital key ↗
Showing 3 of 9 on file for this type
▸Seals & Professional Certifications27
▸DOB NOWDPL-1: Design Professional Seal & Signature9
08/21/2026B01167561-P1Open ↗
08/21/2026B01167561-I1Open ↗
08/19/2026B01319431-I1Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWProgress Inspector Seal & Signature9
09/01/2026B01156573-P3Open ↗
09/01/2026B01156573-P3Open ↗
08/29/2026B01167561-I1Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature9
09/01/2026B01156573-P3Open ↗
08/29/2026B01167561-I1Open ↗
08/29/2026B01156573-I1Open ↗
Showing 3 of 9 on file for this type
▸Environmental & Asbestos7
▸DOB NOWDEP ACP-5: Asbestos Assessment Report7
08/21/2026B01167561-P1Open ↗
08/21/2026B01167561-I1Open ↗
08/16/2026B01156573-S1Open ↗
Showing 3 of 7 on file for this type
▸Other Documents8
▸DOB NOWDHCR Document8
08/15/2026B01156573-P3Open ↗
08/15/2026B01156573-I1Open ↗
08/14/2026B01156573-P2Open ↗
Showing 3 of 8 on file for this type