← Back
Five to six families
337 EAST 18 STREET
MANHATTAN · Gramercy · BIN 1020482
💬 Discuss this project
1910Year Built
4Stories
C2Building Class
R7BZoning
3,666 sfGross Floor Area
5Units
Rent Stabilized0 Open Violations
Five to six families · Owner of record: 337 E 18 LLC · 1,840 sf lot · 1.99 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingEquipmentGeneral
Permit Issued — active, not yet Signed-off
RoofUnder Construction5p · 1 filing · 14 docs
Floor 3Under Construction20p · 2 filings · 20 docs
Floor 2Under Construction26p · 2 filings · 20 docs
Floor 1Under Construction15p · 1 filing · 14 docs
CellarUnder Construction19p · 2 filings · 20 docs
Sub-BasementUnder Construction21p · 2 filings · 20 docs
Site & exterior9p · 3 filings · 8 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
337 E 18 St1907/08/2026
J G CONSTRUCTION SRVCS803/22/2026
ELITE CONTRACTING & DESIGN LLC407/08/2026
337 E 18 LLC103/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
08/11/2025$3.9M—— → —$1,073/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
LEVIN ENGINEERING PLLC302/17/2026
EDIFICE DRAFTING AND SERVICES311/10/2025
BANGASH ASSOCIATES INC.107/21/2024
ASHRAF CORP107/17/2024
NEW AGE ENGINEERING PLLC104/19/2022
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
4444 PPPP CORP1103/21/2026
KMA DESIGNS LLC203/21/2026
SHEIKH EXPEDITING203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
METHOD GENERAL CONTRACTORGeneral Contractor807/08/2026
J & G CONSTRUCTION SVCSGeneral Contractor603/21/2026
M&N CONSTR SERVICES INCGeneral Contractor504/09/2026
ELITE CONTRACTING & DESGeneral Contractor107/08/2026
RICHARD NEUElectrical103/22/2026
P.H. WORKS INCPlumbing107/08/2026
SIDERIS PLBG & HTG CORPPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
CITY-WIDE TESTING INC416502/17/2026
BANGASH ASSOCIATES INC8488107/21/2024
Building Lifecycle
All (97)Filed (9)Permit Issued (16)Signed Off (3)Violation (5)Inspection (4)Objection (30)Special Inspection (30)
05/06/2026
Inspection — Pass-Final PL - Up to 9 Requested Floors
Pass
View inspection ↗
05/01/2026
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
03/02/2026
Permit issued — General Construction
M01298287-I1-GC
03/02/2026
Permit issued — General Construction
M01298299-I1-GC
03/02/2026
Permit issued — Construction Fence
M01314928-I1-FN
03/02/2026
Permit issued — Mechanical Systems
M01312640-S1-MS
02/17/2026
Filed — Alteration
Installation of new heating and cooling equipment
M01312640-P1
02/10/2026
Permit issued — Mechanical Systems
M01312640-S1-MS
02/05/2026
Permit issued — Plumbing
M01312640-I1-PL
01/12/2026
Permit issued — Construction Fence
M01314928-I1-FN
01/12/2026
Permit issued — General Construction
M01298287-I1-GC
01/12/2026
Permit issued — General Construction
M01298299-I1-GC
12/24/2025
Permit issued — General Construction
M01298299-I1-GC
12/23/2025
Permit issued — General Construction
M01298287-I1-GC
12/23/2025
Permit issued — Construction Fence
M01314928-I1-FN
12/09/2025
Filed — Alteration
Installation of new heating and cooling equipment
M01312640-S1
12/08/2025
Special inspection requirement — Mechanical Systems
ELIAS RASABI
12/08/2025
Special inspection requirement — Final
ELIAS RASABI
12/08/2025
Special inspection requirement — HVAC-R and service water heating system controls
ELIAS RASABI
12/08/2025
Special inspection requirement — Maintenance information
ELIAS RASABI
12/08/2025
Special inspection requirement — HVAC-R and service water heating equipment
ELIAS RASABI
12/08/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
ELIAS RASABI
12/08/2025
Special inspection requirement — Shutoff dampers
ELIAS RASABI
12/02/2025
Filed — Alteration
Installation of new heating and cooling equipment
M01312640-I1
12/02/2025
Objection resolved — Addressed
11/24/2025
Objection raised — Other
11/17/2025
Violation issued (HPD, closed)
I
11/10/2025
Filed — Alteration
Temporary Construction Fence
M01314928-I1
11/07/2025
Objection resolved — Addressed
11/07/2025
Objection resolved — Addressed
11/07/2025
Objection resolved — Addressed
11/07/2025
Objection resolved — Addressed
11/07/2025
Objection resolved — Addressed
11/07/2025
Objection resolved — Addressed
11/06/2025
Objection raised — Mechanical
11/06/2025
Objection resolved — Addressed
11/06/2025
Objection resolved — Addressed
11/06/2025
Objection resolved — Addressed
11/06/2025
Objection resolved — Addressed
11/06/2025
Special inspection requirement — Metering
ELIAS RASABI
11/05/2025
Objection resolved — Addressed
11/05/2025
Objection resolved — Addressed
11/05/2025
Objection resolved — Addressed
11/05/2025
Objection resolved — Addressed
11/05/2025
Special inspection requirement — Maintenance information
ELIAS RASABI
11/05/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
ELIAS RASABI
11/05/2025
Special inspection requirement — Energy Code Compliance Inspections
ELIAS RASABI
11/05/2025
Special inspection requirement — Fire-Resistance Rated Construction
ELIAS RASABI
11/05/2025
Special inspection requirement — Fenestration air leakage
ELIAS RASABI
11/05/2025
Special inspection requirement — Interior lighting power
ELIAS RASABI
11/05/2025
Special inspection requirement — Fenestration areas
ELIAS RASABI
11/05/2025
Special inspection requirement — Lighting controls
ELIAS RASABI
11/05/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
ELIAS RASABI
11/05/2025
Special inspection requirement — Lighting in dwelling units
ELIAS RASABI
10/15/2025
Objection raised — Inspections
10/15/2025
Objection raised — Structural
10/15/2025
Objection raised — Admin
10/15/2025
Objection raised — Cost
10/15/2025
Objection raised — Scope
10/15/2025
Objection raised — Structural
Latest 60 of 97 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedMETHOD GENERAL CONTRACTOR03/02/2026
DOB NOWGeneral ConstructionPermit IssuedMETHOD GENERAL CONTRACTOR03/02/2026
DOB NOWConstruction FenceSigned-offMETHOD GENERAL CONTRACTOR03/02/2026
DOB NOWMechanical SystemsPermit IssuedMETHOD GENERAL CONTRACTOR03/02/2026
DOB NOWMechanical SystemsPermit IssuedMETHOD GENERAL CONTRACTOR02/10/2026
DOB NOWPlumbingPermit IssuedP.H. WORKS INC02/05/2026
DOB NOWConstruction FenceSigned-offMETHOD GENERAL CONTRACTOR01/12/2026
DOB NOWGeneral ConstructionPermit IssuedMETHOD GENERAL CONTRACTOR01/12/2026
DOB NOWGeneral ConstructionPermit IssuedMETHOD GENERAL CONTRACTOR01/12/2026
DOB NOWGeneral ConstructionPermit IssuedM&N CONSTR SERVICES INC12/24/2025
DOB NOWGeneral ConstructionPermit IssuedM&N CONSTR SERVICES INC12/23/2025
DOB NOWConstruction FenceSigned-offM&N CONSTR SERVICES INC12/23/2025
DOB NOWGeneral ConstructionSigned-offELITE CONTRACTING & DES07/30/2024
DOB NOWSupported ScaffoldSigned-offJ & G CONSTRUCTION SVCS07/18/2024
DOB NOWSupported ScaffoldSigned-offJ & G CONSTRUCTION SVCS07/18/2024
DOB NOWPlumbingSigned-offSIDERIS PLBG & HTG CORP04/20/2022
1 project · most recent 02/17/2026
Heating and Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
02/17/2026Permit IssuedMETHOD GENERAL CONTRACTORHeating and Air Conditioning Systems
Heat / Cool
Daikin Daikin RXTA36AAVJU 40,000 BTU · Vrf Outdoor ×2
Daikin RXTA60AAVJU 60,000 BTU · Vrf Outdoor ×1
1 project · most recent 02/17/2026
Gas Storm Water/Sanitary
FiledStatusContractorScope
02/17/2026Permit IssuedP.H. WORKS INCGas, Storm, Water/Sanitary
2 projects · most recent 06/24/2026
General Wiring
FiledStatusContractorScope
06/24/2026Permit IssuedMETHOD ELECTRIC LLCGeneral Wiring
07/19/2024CompleteRICHARD NEU—
1 project · most recent 11/10/2025
Fence
FiledStatusContractorScope
11/10/2025Signed-offMETHOD GENERAL CONTRACTORFence
▾Field Inspections (DOB CAP) — 4
DateTypeResultReport
05/06/2026Pass-Final PL - Up to 9 Requested FloorsPassView ↗
05/01/2026Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
05/10/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
05/04/2022Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 36
DateRequirementInspectorRole
12/08/2025Mechanical SystemsELIAS RASABIspecial
12/08/2025FinalELIAS RASABIprogress
12/08/2025HVAC-R and service water heating system controlsELIAS RASABIenergy_progress
12/08/2025Maintenance informationELIAS RASABIenergy_progress
12/08/2025HVAC-R and service water heating equipmentELIAS RASABIenergy_progress
12/08/2025HVAC-R and service water piping design and insulationELIAS RASABIenergy_progress
12/08/2025Shutoff dampersELIAS RASABIenergy_progress
11/06/2025MeteringELIAS RASABIenergy_progress
11/05/2025Maintenance informationELIAS RASABIenergy_progress
11/05/2025Fire-Resistant Penetrations and JointsELIAS RASABIspecial
11/05/2025Energy Code Compliance InspectionsELIAS RASABIprogress
11/05/2025Fire-Resistance Rated ConstructionELIAS RASABIprogress
11/05/2025Fenestration air leakageELIAS RASABIenergy_progress
11/05/2025Interior lighting powerELIAS RASABIenergy_progress
11/05/2025Fenestration areasELIAS RASABIenergy_progress
11/05/2025Lighting controlsELIAS RASABIenergy_progress
11/05/2025Fenestration and door U-factor and product ratingsELIAS RASABIenergy_progress
11/05/2025Lighting in dwelling unitsELIAS RASABIenergy_progress
10/06/2025Lighting controlsELIAS RASABIenergy_progress
10/06/2025Fenestration areasELIAS RASABIenergy_progress
10/06/2025Lighting in dwelling unitsELIAS RASABIenergy_progress
10/06/2025Maintenance informationELIAS RASABIenergy_progress
10/06/2025Fenestration and door U-factor and product ratingsELIAS RASABIenergy_progress
10/06/2025Interior lighting powerELIAS RASABIenergy_progress
10/06/2025FinalELIAS RASABIprogress
Latest 25 of 36.
▾Documents — 43 on file (BIS + DOB NOW)
▸Plans & Drawings10
▸DOB NOWPlans/Sketch10
09/02/2026M00713492-I1Request digital key ↗
08/26/2026M01081783-I1Request digital key ↗
08/26/2026M01083252-I1Request digital key ↗
Showing 3 of 10 on file for this type
▸Seals & Professional Certifications25
▸DOB NOWProgress Inspector Seal & Signature11
09/29/2026M00713492-I1Open ↗
09/29/2026M00713492-I1Open ↗
09/29/2026M00713492-I1Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature10
09/02/2026M00713492-I1Open ↗
08/26/2026M01081783-I1Open ↗
08/26/2026M01083252-I1Open ↗
Showing 3 of 10 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
09/23/2026M01312640-S1Open ↗
09/02/2026M01298299-I1Open ↗
09/02/2026M01298287-I1Open ↗
Showing 3 of 4 on file for this type
▸Environmental & Asbestos7
▸DOB NOWDEP ACP-5: Asbestos Assessment Report7
09/02/2026M00713492-I1Open ↗
08/21/2026M01298287-I1Open ↗
08/19/2026M01312640-P2Open ↗
Showing 3 of 7 on file for this type
▸Energy Compliance1
▸DOB NOWEN2: As Built Energy Analysis1
09/02/2026M00713492-I1Open ↗