1917Year Built
7Stories
RABuilding Class
R8BZoning
49,335 sfGross Floor Area
2Units
LL97 Covered0 Active Violations
Condo, cultural / medical / educational · Owner of record: 337 Garage · 10,042 sf lot · 4.91 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionEquipmentCivilGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
RoofBrowning School, Verizon16p · 9 filings · 20 docs
Floor 5Browning School3p · 9 filings · 20 docs
Floor 4Browning School8 filings · 20 docs
Floor 3Browning School, Verizon9 filings · 20 docs
Floor 2Browning School8 filings · 20 docs
Floor 1Browning School16p · 9 filings · 20 docs
MezzanineBrowning School1 filing · 20 docs
CellarBrowning School2p · 10 filings · 20 docs
Site & exteriorBrowning School, Verizon24p · 10 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Chapman Consulting3907/08/2026
337 Garage603/21/2026
Minetta Lane Owners308/29/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
William Vitacco Associates5803/21/2026
Spring Scaffolding4603/21/2026
Building Brothers603/21/2026
A1 Expediting Service603/21/2026
Royal Construction Services403/21/2026
AE Design Solution803/21/2026
Construction Permit Services103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Spring ScaffoldingScaffold5207/08/2026
JRM Construction ManagementGeneral Contractor2507/08/2026
Rite-Way Internal RemovalGeneral Contractor603/21/2026
Demar PlumbingFire Protection507/08/2026
JRM Construction Managementspecialty_contractor507/08/2026
Demar MechanicalPlumbing507/08/2026
Active SignsSign hanger307/08/2026
AmokFire Protection207/08/2026
Cogen Electrical ServicesElectrical203/22/2026
Odyssia Global Commercialspecialty_contractor107/08/2026
Tmi ContractingGeneral Contractor103/21/2026
Telcom Engineering GPGeneral Contractor103/21/2026
Everest ScaffoldingGeneral Contractor103/21/2026
Markatos Antoniosspecialty_contractor103/21/2026
Brookside EnvironmetalGeneral Contractor107/17/2013
J T Oronzio GeneralGeneral Contractor112/16/2009
Prestige Interstate PLG and HeatingPlumbing108/04/1992
Prestige TestingFire Protection108/06/1992
RND ServicesGeneral Contractor108/07/2012
Safway AtlanticGeneral Contractor209/29/2016
Tmi ContractingGeneral Contractor111/04/1998
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Domani Inspection Service8432705/20/2026
Leo Y Lee Associates2481410/04/2024
Langan Engineering, Env, Surveyin1265209/07/2023
Scherer Design Group7921108/11/2022
Building Lifecycle
07/16/2026
Signed off — Alteration CO
Filing for the conversion of a garage to a school. Work includes removal and installation of interior non load bearing partitions, doors, floors, finish work on floors Cellar, 1-5, MZ5, Roof.
M00717485-I1
05/27/2026
Objection resolved — Addressed
05/25/2026
Objection raised — Other
05/20/2026
Filed — Alteration CO
Filing for the conversion of a garage to a school. Work includes removal and installation of interior non load bearing partitions, doors, floors, finish work on floors Cellar, 1-5, MZ5, Roof.
M00717485-A4
04/06/2026
Closed: Department of buildings intend to revoke all work and jobs under application #M01266923-I1 unless master rigger obtained required insurance.
DOB violation · closed on the city's record
300 history events on file for this building. Sign in free to see the full history. Sign in · Create account
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSignSigned-offActive Signs10/14/2025
DOB NOWSignSigned-offActive Signs10/06/2025
DOB NOWSignSigned-offActive Signs10/06/2025
DOB NOWSuspended ScaffoldSigned-offUniversal Steeplejack08/08/2025
DOB NOWGeneral ConstructionPermit IssuedJRM Construction Management04/11/2025
DOB NOWMechanical SystemsSigned-offJRM Construction Management03/11/2025
DOB NOWProtection and Mechanical MethodsSigned-offSpring Scaffolding03/11/2025
DOB NOWProtection and Mechanical MethodsSigned-offSpring Scaffolding02/27/2025
DOB NOWConstruction FenceSigned-offSpring Scaffolding02/27/2025
DOB NOWPlumbingSigned-offDemar Mechanical01/24/2025
DOB NOWStandpipeSigned-offDemar Plumbing12/03/2024
DOB NOWSupported ScaffoldSigned-offSpring Scaffolding12/02/2024
DOB NOWPlumbingSigned-offDemar Mechanical12/02/2024
DOB NOWSprinklersSigned-offDemar Plumbing12/02/2024
DOB NOWSuspended ScaffoldPermit IssuedSkytrac Access Group10/18/2024
DOB NOWStructuralSigned-offJRM Construction Management08/15/2024
DOB NOWFoundationSigned-offJRM Construction Management08/15/2024
DOB NOWSupport of ExcavationSigned-offJRM Construction Management08/15/2024
DOB NOWSuspended ScaffoldPermit IssuedSkytrac Access Group08/14/2024
DOB NOWGeneral ConstructionPermit IssuedJRM Construction Management08/14/2024
DOB NOWProtection and Mechanical MethodsSigned-offSpring Scaffolding07/11/2024
DOB NOWProtection and Mechanical MethodsSigned-offSpring Scaffolding07/02/2024
DOB NOWSupported ScaffoldSigned-offSpring Scaffolding06/13/2024
DOB NOWProtection and Mechanical MethodsSigned-offSpring Scaffolding06/13/2024
DOB NOWConstruction FenceSigned-offSpring Scaffolding06/13/2024
DOB NOWProtection and Mechanical MethodsSigned-offSpring Scaffolding06/13/2024
DOB NOWSidewalk ShedSigned-offSpring Scaffolding06/13/2024
DOB NOWSupported ScaffoldSigned-offSpring Scaffolding06/13/2024
DOB NOWProtection and Mechanical MethodsSigned-offSpring Scaffolding06/13/2024
DOB NOWSuspended ScaffoldSigned-offSkytrac Access Group06/12/2024
DOB NOWStandpipeSigned-offAmok05/15/2024
DOB NOWGeneral ConstructionSigned-offJRM Construction Management04/10/2024
DOB NOWSupport of ExcavationSigned-offJRM Construction Management04/10/2024
DOB NOWStructuralSigned-offJRM Construction Management04/10/2024
DOB NOWStructuralSigned-offJRM Construction Management04/10/2024
DOB NOWMechanical SystemsSigned-offJRM Construction Management04/10/2024
DOB NOWGeneral ConstructionPermit IssuedJRM Construction Management04/10/2024
DOB NOWFoundationSigned-offJRM Construction Management04/10/2024
DOB NOWMechanical SystemsSigned-offJRM Construction Management04/10/2024
DOB NOWGeneral ConstructionSigned-offRite-Way Internal Removal04/03/2024
+ 34 more permits on file
1 project · most recent 05/20/2026
Heating and Air Conditioning Systems Heating Systems
FiledStatusContractorScope
05/20/2026Permit IssuedJRM Construction ManagementHeating and Air Conditioning Systems, Heating Systems
1 project · most recent 05/20/2026
Sprinkler System
FiledStatusContractorScope
05/20/2026Signed-offDemar PlumbingSprinkler System
1 project · most recent 05/20/2026
Storm Water/Sanitary
FiledStatusContractorScope
05/20/2026Signed-offDemar MechanicalStorm, Water/Sanitary
9 projects · most recent 05/19/2025
General Wiring
FiledStatusContractorScope
05/19/2025CompleteCogen Electrical ServicesGeneral Wiring
05/19/2025CompleteCogen Electrical ServicesGeneral Wiring
05/19/2025CompleteCogen Electrical ServicesGeneral Wiring
05/05/2025CompleteCogen Electrical ServicesGeneral Wiring
03/12/2024CompleteDenali Electric—
06/15/2023CompleteCogen Electrical Services—
05/30/2023CompleteCogen Electrical Services—
10/25/2022CompleteTop Shelf Electric—
02/25/2022CompleteUsis ElectricGeneral Wiring
1 project · most recent 05/20/2026
Steel Concrete Masonry
FiledStatusContractorScope
05/20/2026Permit IssuedJRM Construction ManagementSteel, Concrete, Masonry
▾Field Inspections (DOB CAP) — 17
DateTypeResultReport
09/11/2025Pass-Final CND-Occupancy InspectionPassView ↗
04/22/2025Pass-Final CND-Occupancy InspectionPassView ↗
03/17/2025Certified StandPipe-SD-Fixtures-Finish-SDCertifiedView ↗
03/10/2025Pass-Final SD - More than 10 Requested FloorsPassView ↗
03/06/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
02/26/2025Fail-Final SD - More than 10 Requested FloorsFailView ↗
10/17/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
10/09/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
08/20/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
08/13/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
08/06/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
07/11/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
06/07/2024Pass-Final PL - UndergroundPassView ↗
05/22/2024Pass-Final PL - UndergroundPassView ↗
04/29/2024Pass-Final PL - UndergroundPassView ↗
03/08/2024Pass-Final PL - UndergroundPassView ↗
05/16/2023Certified StandPipe - SD - Alarm Sys 64/09 - FinishCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 91
DateRequirementInspectorRole
08/22/2025Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationJOHN MCMONAGLEspecial
08/22/2025Fire-Resistant Penetrations and JointsJOHN MCMONAGLEspecial
07/28/2025Fire-Resistance Rated ConstructionJOHN MCMONAGLEprogress
07/28/2025Fenestration areasJOHN MCMONAGLEenergy_progress
07/28/2025Interior lighting powerJOHN MCMONAGLEenergy_progress
07/28/2025Insulation placement and R valuesJOHN MCMONAGLEenergy_progress
07/28/2025Fenestration air leakageJOHN MCMONAGLEenergy_progress
07/28/2025Protection of exposed foundation insulationJOHN MCMONAGLEenergy_progress
07/28/2025Fenestration and door U-factor and product ratingsJOHN MCMONAGLEenergy_progress
07/28/2025Air barrier — testing JOHN MCMONAGLEenergy_progress
07/28/2025Exterior lighting powerJOHN MCMONAGLEenergy_progress
07/28/2025VestibulesJOHN MCMONAGLEenergy_progress
07/28/2025Lighting controlsJOHN MCMONAGLEenergy_progress
07/28/2025Air barrier continuity plan testingJOHN MCMONAGLEenergy_progress
07/28/2025Fire-Resistant Penetrations and JointsJOHN MCMONAGLEspecial
07/22/2025FinalLEON SKVIRSKYprogress
07/15/2025Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationJOHN MCMONAGLEspecial
07/15/2025Fire-Resistant Penetrations and JointsJOHN MCMONAGLEspecial
06/17/2025VestibulesJOHN MCMONAGLEenergy_progress
06/17/2025Fire-Resistance Rated ConstructionJOHN MCMONAGLEprogress
06/17/2025Air barrier continuity plan testingJOHN MCMONAGLEenergy_progress
06/17/2025Lighting controlsJOHN MCMONAGLEenergy_progress
06/17/2025Fenestration air leakageJOHN MCMONAGLEenergy_progress
06/17/2025Air barrier — testing JOHN MCMONAGLEenergy_progress
06/17/2025Fenestration areasJOHN MCMONAGLEenergy_progress
Latest 25 of 91.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Browning SchoolEducationCellar, Floors 1–5, Mezzanine, Roof
Project M01230626 Alteration · LOC Issued · 08/29/2025
Project M01230632 Alteration · LOC Issued · 08/29/2025
Project M01259846 Alteration · LOC Issued · 08/29/2025
Project M01029945 Alteration · LOC Issued · 04/05/2024
Project M00877776 Alteration · Filing Withdrawn · 08/30/2023
Project M00922424 Alteration · LOC Issued · 08/30/2023
Project M00867264 Alteration · LOC Issued · 05/25/2023
Project M00831305 Alteration · LOC Issued · 03/08/2023
Project M00831200 Alteration · LOC Issued · 02/23/2023
Project M00831220 Alteration · LOC Issued · 02/23/2023
Project M00831237 Alteration · LOC Issued · 02/23/2023
Project M00831249 Alteration · LOC Issued · 02/23/2023
VerizonTelecom siteFloor 3, Roof
Project M00784975 Alteration · LOC Issued · 08/11/2022