| Owner | Filings | Most Recent |
|---|---|---|
| RELIABLE ENTERPRISES | 4 | 07/08/2026 |
| SHAPRIO & SONS INC | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 04/26/2021 | $1.3M | — | Private party → Private party | $578/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| FLORINELA MURESAN | 2 | 11/23/2022 |
| ENTHINK ENGINEERS LLC | 1 | 08/12/2022 |
| PAUL PERDEK, PROF. ENG. PLLC | 2 | 06/30/2022 |
| KCE CONSULTING ENGINEERING PLLC | 6 | 05/10/2022 |
| PARKBENCH ARCHITECTS | 3 | 02/11/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| EXPEDIENT CONSULTING | 22 | 03/21/2026 |
| AE DESIGN SOLUTION | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| SHAPIRO & SONS INC | General Contractor | 37 | 07/08/2026 |
| POWERS BRIDGING & SCAFFOLDING | General Contractor | 4 | 03/21/2026 |
| COBOT PLUMBING AND HEATING INC | Plumbing | 2 | 07/08/2026 |
| RELIABLE ENTERPRISES INC | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ENVIRONMENTAL CODE CONSUL | 5516 | 3 | 11/23/2022 |
| ENTHINK ENGINEERS LLC | 6247 | 1 | 08/12/2022 |
| KCE CONSULTING ENGINEERIN | 3712 | 6 | 05/10/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | SHAPIRO & SONS INC | 09/20/2023 |
| DOB NOW | General Construction | Signed-off | SHAPIRO & SONS INC | 09/18/2023 |
| DOB NOW | Foundation | Signed-off | SHAPIRO & SONS INC | 05/23/2023 |
| DOB NOW | Plumbing | Signed-off | COBOT PLUMBING AND HEATIN | 05/10/2023 |
| DOB NOW | Mechanical Systems | Signed-off | SHAPIRO & SONS INC | 11/04/2022 |
| DOB NOW | Plumbing | Signed-off | COBOT PLUMBING AND HEATIN | 08/30/2022 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | RELIABLE ENTERPRISES INC | 08/15/2022 |
| DOB NOW | Mechanical Systems | Signed-off | SHAPIRO & SONS INC | 07/13/2022 |
| DOB NOW | Supported Scaffold | Permit Issued | POWERS BRIDGING & SCAFFOL | 07/01/2022 |
| DOB NOW | Sidewalk Shed | Permit Issued | POWERS BRIDGING & SCAFFOL | 06/03/2022 |
| DOB NOW | Foundation | Signed-off | SHAPIRO & SONS INC | 04/27/2022 |
| DOB NOW | Support of Excavation | Signed-off | SHAPIRO & SONS INC | 04/27/2022 |
| DOB NOW | Construction Fence | Signed-off | SHAPIRO & SONS INC | 03/10/2022 |
| DOB NOW | General Construction | Signed-off | SHAPIRO & SONS INC | 03/10/2022 |
| DOB NOW | General Construction | Signed-off | SHAPIRO & SONS INC | 03/10/2022 |
| DOB NOW | Structural | Signed-off | SHAPIRO & SONS INC | 03/10/2022 |
| DOB NOW | Construction Fence | Signed-off | SHAPIRO & SONS INC | 02/17/2022 |
| DOB NOW | Structural | Signed-off | SHAPIRO & SONS INC | 02/14/2022 |
| DOB NOW | Mechanical Systems | Signed-off | SHAPIRO & SONS INC | 01/14/2022 |
| DOB NOW | General Construction | Signed-off | SHAPIRO & SONS INC | 06/01/2021 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/23/2022 | Signed-off | COBOT PLUMBING AND HEATIN | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/20/2022 | Permit Issued | LENS ELECTRIC, INC | General Wiring |
| 05/19/2022 | Complete | OPTIMAL ELECTRIC, INC | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/30/2022 | Permit Issued | POWERS BRIDGING & SCAFFOL | Scaffold |
| 06/02/2022 | Permit Issued | POWERS BRIDGING & SCAFFOL | Sidewalk Shed |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 11/28/2022 | Fire-Resistant Penetrations and Joints | Daniel Karpen | special |
| 11/15/2022 | Fire-Resistant Penetrations and Joints | Daniel Karpen | special |
| 05/17/2022 | Structural Stability – Alterations of existing buildings | Kemba Walcott | special |
| 05/17/2022 | Excavations - Sheeting, Shoring, and Bracing | Kemba Walcott | special |
| 05/17/2022 | Subgrade Inspections | Kemba Walcott | special |
| 05/13/2022 | Final | Kemba Walcott | progress |
| 05/13/2022 | Subgrade Inspections | Kemba Walcott | special |
| 05/13/2022 | Structural Stability – Alterations of existing buildings | Kemba Walcott | special |
| 05/13/2022 | Post-installed Anchors | Kemba Walcott | special |
| 05/13/2022 | Concrete - Cast-In-Place | Kemba Walcott | special |
| 05/13/2022 | Footing and Foundation | Kemba Walcott | progress |
| 05/09/2022 | Concrete - Cast-In-Place | Kemba Walcott | special |
| 05/09/2022 | Post-installed Anchors | Kemba Walcott | special |
| 05/09/2022 | Structural Stability – Alterations of existing buildings | Kemba Walcott | special |
| 05/09/2022 | Subgrade Inspections | Kemba Walcott | special |
| 05/09/2022 | Final | Kemba Walcott | progress |
| 05/09/2022 | Footing and Foundation | Kemba Walcott | progress |
| 05/09/2022 | Excavations - Sheeting, Shoring, and Bracing | Kemba Walcott | special |
| 05/09/2022 | Structural Stability – Alterations of existing buildings | Kemba Walcott | special |
| 05/09/2022 | Subgrade Inspections | Kemba Walcott | special |
| 05/06/2022 | Post-installed Anchors | Kemba Walcott | special |
| 05/06/2022 | Structural Steel - High Strength Bolting | Kemba Walcott | special |
| 05/06/2022 | Final | Kemba Walcott | progress |
| 05/06/2022 | Structural Steel - Details | Kemba Walcott | special |
| 05/06/2022 | Structural Stability – Alterations of existing buildings | Kemba Walcott | special |