| Owner | Filings | Most Recent |
|---|---|---|
| COSAN CONSTRUCTION | 6 | 04/09/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| DAGHER ENGINEERING PLLC | 7 | 06/03/2026 |
| GF55 ARCHITECTS LLP | 3 | 03/04/2026 |
| AMM ENGINEERING PC | 1 | 11/24/2025 |
| ASHRAF CORP | 2 | 09/30/2025 |
| PAUL PERDEK, PROF. ENG. PLLC | 4 | 08/28/2025 |
| PILLORI ASSOCIATES | 3 | 06/23/2025 |
| DE NARDIS ENGINEERING, LLC | 4 | 07/29/2024 |
| HANSEN ENGINEERING, PC | 1 | 07/09/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| PRECISION 3SIXTY NYC, INC | 30 | 03/21/2026 |
| JM ZONING, LLC. | 1 | 03/21/2026 |
| A1 EXPEDITING SERVICE | 8 | 03/21/2026 |
| EUROCELT EXPEDITING, INC | 4 | 03/21/2026 |
| LETTIRE CONSTRUCTION | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| LETTIRE CONSTRUCTION CORP | General Contractor | 13 | 07/08/2026 |
| ROCKLEDGE SCAFFOLD CORP | General Contractor | 4 | 07/08/2026 |
| COSAN CONSTRUCTION CORP | General Contractor | 3 | 04/09/2026 |
| DEMAR PLUMBING CORP | Fire Protection | 2 | 07/08/2026 |
| DEMAR PLUMBING CORP | Plumbing | 2 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| PSI AGENCY INC. | 254 | 16 | 06/03/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Protection and Mechanical Methods | Signed-off | ROCKLEDGE SCAFFOLD CORP | 03/23/2026 |
| DOB NOW | Sidewalk Shed | Signed-off | ROCKLEDGE SCAFFOLD CORP | 03/19/2026 |
| DOB NOW | Suspended Scaffold | Permit Issued | COSAN CONSTRUCTION | 11/25/2025 |
| DOB NOW | General Construction | Permit Issued | LETTIRE CONSTRUCTION CORP | 10/23/2025 |
| DOB NOW | Construction Fence | Signed-off | LETTIRE CONSTRUCTION CORP | 09/18/2025 |
| DOB NOW | Plumbing | Permit Issued | DEMAR PLUMBING CORP | 09/11/2025 |
| DOB NOW | Sprinklers | Signed-off | DEMAR PLUMBING CORP | 09/11/2025 |
| DOB NOW | Structural | Signed-off | LETTIRE CONSTRUCTION CORP | 08/25/2025 |
| DOB NOW | Mechanical Systems | Signed-off | LETTIRE CONSTRUCTION CORP | 08/20/2025 |
| DOB NOW | Construction Fence | Signed-off | LETTIRE CONSTRUCTION CORP | 07/21/2025 |
| DOB NOW | Supported Scaffold | Signed-off | COSAN CONSTRUCTION | 06/24/2025 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | ROCKLEDGE SCAFFOLD CORP | 03/20/2025 |
| DOB NOW | Sidewalk Shed | Signed-off | ROCKLEDGE SCAFFOLD CORP | 03/20/2025 |
| DOB NOW | General Construction | Permit Issued | LETTIRE CONSTRUCTION CORP | 11/12/2024 |
| DOB NOW | Support of Excavation | Signed-off | LETTIRE CONSTRUCTION CORP | 08/30/2024 |
| DOB NOW | Structural | Signed-off | LETTIRE CONSTRUCTION CORP | 08/29/2024 |
| DOB NOW | Foundation | Signed-off | LETTIRE CONSTRUCTION CORP | 08/29/2024 |
| DOB NOW | Mechanical Systems | Signed-off | LETTIRE CONSTRUCTION CORP | 08/26/2024 |
| DOB NOW | General Construction | Permit Issued | LETTIRE CONSTRUCTION CORP | 08/26/2024 |
| DOB NOW | Sprinklers | Signed-off | DEMAR PLUMBING CORP | 08/22/2024 |
| DOB NOW | Plumbing | Permit Issued | DEMAR PLUMBING CORP | 08/22/2024 |
| DOB NOW | Construction Fence | Signed-off | LETTIRE CONSTRUCTION CORP | 07/26/2024 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 06/03/2026 | Permit Issued | LETTIRE CONSTRUCTION CORP | Heating and Air Conditioning Systems | Heat / Cool Mitsubishi Electric PUY-A24NHA7 24,000 BTU · Split System ×2 PUZ-HA24NHA1 24,000 BTU · Split System ×2 Islandaire EZ07A2GN1S14AL 7,200 BTU · Ptac ×2 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/03/2026 | Permit Issued | DEMAR PLUMBING CORP | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/26/2026 | Complete | XTREME ELECTRIC INC | General Wiring |
| 02/11/2026 | Permit Issued | TUXEDO ELEC'L CONTR'G INC | — |
| 03/21/2025 | Complete | ANTHONY G FERRY INC | — |
| 08/08/2024 | Complete | XTREME ELECTRIC INC | 1 meters, 1 new_meters |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/03/2026 | Permit Issued | LETTIRE CONSTRUCTION CORP | Steel, Masonry |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/30/2025 | Signed-off | COSAN CONSTRUCTION CORP | Scaffold |
| 08/28/2025 | Signed-off | ROCKLEDGE SCAFFOLD CORP | Sidewalk Shed |
| 07/09/2024 | Signed-off | LETTIRE CONSTRUCTION CORP | Fence |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/14/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 07/07/2026 | Pass-Final SP - Up to 9 Requested Floors | Pass | View ↗ |
| 07/01/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 05/06/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 05/01/2026 | Certified Sprinkler (SP) - Booster Pump Test | Certified | View ↗ |
| 05/01/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 01/15/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 12/22/2025 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 10/16/2025 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 06/28/2025 | Pass-Final PL - Underground | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/08/2026 | Interior lighting power | MAURICIO ANDRADE | energy_progress |
| 05/08/2026 | Metering | MAURICIO ANDRADE | energy_progress |
| 05/08/2026 | Maintenance information | MAURICIO ANDRADE | energy_progress |
| 05/08/2026 | Electrical motors and elevators | MAURICIO ANDRADE | energy_progress |
| 05/08/2026 | Shutoff dampers | MAURICIO ANDRADE | energy_progress |
| 05/08/2026 | HVAC-R and service water piping design and insulation | MAURICIO ANDRADE | energy_progress |
| 05/08/2026 | Lighting in dwelling units | MAURICIO ANDRADE | energy_progress |
| 05/08/2026 | Final | MAURICIO ANDRADE | progress |
| 05/08/2026 | Energy Code Compliance Inspections | MAURICIO ANDRADE | progress |
| 05/08/2026 | Mechanical Systems | MAURICIO ANDRADE | special |
| 05/08/2026 | Heating Systems | MAURICIO ANDRADE | special |
| 05/08/2026 | Fire-Resistant Penetrations and Joints | MAURICIO ANDRADE | special |
| 05/08/2026 | Ventilation and air distribution system | MAURICIO ANDRADE | energy_progress |
| 05/08/2026 | HVAC-R and service water heating system controls | MAURICIO ANDRADE | energy_progress |
| 05/08/2026 | Exterior lighting power | MAURICIO ANDRADE | energy_progress |
| 05/08/2026 | Lighting controls | MAURICIO ANDRADE | energy_progress |
| 05/08/2026 | HVAC-R and service water heating equipment | MAURICIO ANDRADE | energy_progress |
| 03/25/2026 | Air barrier - visual inspection | MAURICIO ANDRADE | energy_progress |
| 03/25/2026 | Protection of exposed foundation insulation | MAURICIO ANDRADE | energy_progress |
| 03/25/2026 | Fenestration and door U-factor and product ratings | MAURICIO ANDRADE | energy_progress |
| 03/25/2026 | Fenestration areas | MAURICIO ANDRADE | energy_progress |
| 03/25/2026 | Vestibules | MAURICIO ANDRADE | energy_progress |
| 03/25/2026 | Fire-Resistant Penetrations and Joints | MAURICIO ANDRADE | special |
| 03/25/2026 | Wall Panels, Curtain Walls, and Veneers | MAURICIO ANDRADE | special |
| 03/25/2026 | Lowest Floor Elevation | MAURICIO ANDRADE | progress |