| Owner | Filings | Most Recent |
|---|---|---|
| MP REALTY HOLDING | 37 | 07/08/2026 |
| HILLSIDE DEVELOPMENT | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| ROGERS CALVANICO GROUP PLLC | 8 | 10/04/2022 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| MP REALTY HOLDING CORP | General Contractor | 17 | 07/08/2026 |
| GOODALL ELECTRIC CORP | Electrical | 1 | 03/22/2026 |
| FLOW-RIGHT PLBG & HTG COR | Plumbing | 1 | 07/08/2026 |
| K.M.D MECHANICAL 1443 LLC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| A TECH ENGINEERING NYC, P | 6738 | 4 | 10/04/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | MP REALTY HOLDING CORP | 10/05/2022 |
| DOB NOW | Mechanical Systems | Signed-off | MP REALTY HOLDING CORP | 10/05/2022 |
| DOB NOW | Foundation | Signed-off | MP REALTY HOLDING CORP | 10/05/2022 |
| DOB NOW | Curb Cut | Signed-off | MP REALTY HOLDING CORP | 09/12/2022 |
| DOB NOW | Earth Work | Signed-off | MP REALTY HOLDING CORP | 09/12/2022 |
| DOB NOW | Curb Cut | Signed-off | MP REALTY HOLDING CORP | 09/12/2022 |
| DOB NOW | Plumbing | Signed-off | K.M.D MECHANICAL 1443 LLC | 01/10/2022 |
| DOB NOW | Plumbing | Signed-off | FLOW-RIGHT PLBG & HTG COR | 12/17/2021 |
| DOB NOW | Mechanical Systems | Permit Issued | MP REALTY HOLDING CORP | 12/07/2021 |
| DOB NOW | Foundation | Permit Issued | MP REALTY HOLDING CORP | 11/22/2021 |
| DOB NOW | Construction Fence | Signed-off | MP REALTY HOLDING CORP | 11/19/2021 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/04/2022 | Signed-off | FLOW-RIGHT PLBG & HTG COR | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/04/2023 | Complete | GOODALL ELECTRIC CORP | 3 meters, 1 new_meters |
| 05/14/2022 | Complete | A. J. CARUSO ELECTRICAL I | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/04/2022 | Signed-off | MP REALTY HOLDING CORP | Wood |
| Date | Type | Result | Report |
|---|---|---|---|
| 10/11/2022 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 09/14/2022 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 09/12/2022 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| 09/12/2022 | Pass-Final Fence Non-Directive 14 | Pass | View ↗ |
| 09/01/2022 | Pass-Final PL - Underground | Pass | View ↗ |
| 08/31/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/17/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/24/2022 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 06/08/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/25/2022 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 02/17/2022 | Pass-Final PL - Underground | Pass | View ↗ |
| 01/27/2022 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 01/19/2022 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 10/05/2022 | Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities | anthony santoro | special |
| 10/04/2022 | Structural Steel - Details | anthony santoro | special |
| 10/04/2022 | Exterior Insulation and Finish Systems (EIFS) | anthony santoro | special |
| 10/04/2022 | Subgrade Inspections | anthony santoro | special |
| 10/04/2022 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | anthony santoro | special |
| 10/04/2022 | Concrete - Cast-In-Place | anthony santoro | special |
| 10/04/2022 | Fire-Resistant Penetrations and Joints | anthony santoro | special |
| 10/04/2022 | Structural Steel - Welding | anthony santoro | special |
| 10/04/2022 | Mechanical Systems | anthony santoro | special |
| 10/04/2022 | Subsurface Investigations (Borings/Test Pits) | anthony santoro | special |
| 10/04/2022 | Energy Code Compliance Inspections | anthony santoro | progress |
| 10/04/2022 | Fire-Resistance Rated Construction | anthony santoro | progress |
| 10/04/2022 | Structural Wood Frame | anthony santoro | progress |
| 10/04/2022 | Footing and Foundation | anthony santoro | progress |
| 10/04/2022 | Final | anthony santoro | progress |
| 10/04/2022 | Fenestration air leakage | anthony santoro | energy_progress |
| 10/04/2022 | Duct leakage testing, insulation and design | anthony santoro | energy_progress |
| 10/04/2022 | Maintenance information | anthony santoro | energy_progress |
| 10/04/2022 | Fenestration areas | anthony santoro | energy_progress |
| 10/04/2022 | Protection of exposed foundation insulation | anthony santoro | energy_progress |
| 10/04/2022 | Permanent certificate | anthony santoro | energy_progress |
| 10/04/2022 | Fenestration and door U-factor and product ratings | anthony santoro | energy_progress |
| 10/04/2022 | Interior lighting power | anthony santoro | energy_progress |
| 10/04/2022 | Air barrier — testing | anthony santoro | energy_progress |
| 10/04/2022 | Air barrier - visual inspection | anthony santoro | energy_progress |