| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/16/2026 | Permit Issued | GREEN WATER AND POWER NYC | General Wiring |
| 02/26/2026 | Complete | UPTOWN ELECTRICAL INC | General Wiring |
| 09/29/2025 | Complete | W 8 ELECTRIC CORP | General Wiring |
| 08/28/2025 | Complete | W 8 ELECTRIC CORP | General Wiring |
| 08/01/2025 | Complete | W 8 ELECTRIC CORP | General Wiring |
| 12/19/2024 | Complete | HIGH LEG 208 VOLTS ELECL | General Wiring |
| 08/14/2024 | Complete | W 8 ELECTRIC CORP | General Wiring |
| 09/24/2023 | Complete | JUN SAFETY ELECTRICAL INC | General Wiring |
| 09/17/2023 | Complete | ATMOS ELECTRIC SVCE CORP | — |
| 08/02/2023 | Complete | SPECTRUM ON BROADWAY-ELEC | — |
| 07/16/2023 | Complete | JONG HYUN KIM | — |
| 07/12/2023 | Complete | ATMOS ELECTRIC SVCE CORP | — |
| 02/09/2022 | Complete | STANCO SYSTEM ELEC'L CONT | General Wiring |
| 11/12/2021 | Complete | AUR0RA ELECL CONTG INC | — |
| 08/17/2021 | Complete | CITY GRID ELECTRIC CORP | 1 meters, 1 new_meters |
| Owner | Filings | Most Recent |
|---|---|---|
| SCHUMAN PROPERTIES | 65 | 07/08/2026 |
| SCHULMAN 673/16 LLC | 80 | 03/22/2026 |
| SCHUMIN 673/16 LLC | 1 | 03/22/2026 |
| SHUMAN 573116,LLC | 1 | 03/22/2026 |
| COOK & KRUPS LLC | 1 | 03/22/2026 |
| 34-19 ENTERTAINMENT | 2 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| DRAFT MASTER ENGINEERING PC | 4 | 11/04/2024 |
| ALLEN SHINFELD, P.E. PLLC | 10 | 12/01/2023 |
| MARIN ARCHITECTS, P.C. | 4 | 11/13/2023 |
| RICHARD WAINER ARCHITECT, PLLC | 2 | 09/14/2023 |
| PROSPECT ENGINEERING P.C | 1 | 06/19/2023 |
| JFK&M CONSULTING ENGINEERS | 7 | 09/07/2022 |
| YSRAEL A. SEINUK, PC | 2 | 02/17/2022 |
| SPECTOR GROUP II LLP | 2 | 02/16/2022 |
| F.P.VILLANO CONSULTING ENGINEER LLC | 1 | 09/09/2021 |
| CENTURY TESTING & CONSULTING | 1 | 07/24/2020 |
| PAUL DENIS ASSOCIATES | 1 | 02/08/2020 |
| DAVI ARCHITECTURE, PC | 1 | 09/20/2019 |
| ANGELO NG & ANTHONY NG ARCHITECTS S | 1 | 09/18/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| ARCHIEL, LLC | 18 | 03/21/2026 |
| D R BROWN | 4 | 03/21/2026 |
| JMV ASSOCIATES | 22 | 03/21/2026 |
| ANGELO NG + ANTHONY NG ARCHITECTS | 4 | 03/21/2026 |
| LOUIS STRIAR | 2 | 03/21/2026 |
| BMB BUILDING CONSULTING | 2 | 03/21/2026 |
| CANAS SOLUTIONS | 8 | 03/21/2026 |
| ARCOMETRIC DESIGN | 2 | 03/21/2026 |
| YOUN DESIGN CORP | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| ACS SYSTEM ASSOCIATES INC. | General Contractor | 4 | 07/08/2026 |
| ARANDA PLBG & HTG CORP | Plumbing | 4 | 07/08/2026 |
| TRI STATE PLBG & HTG INC | Plumbing | 3 | 07/08/2026 |
| A. M. PLUMBING COMPANY | Plumbing | 3 | 07/08/2026 |
| MEGA MECHANICAL INC | General Contractor | 2 | 03/21/2026 |
| BRICKENS CONSTRUCTION,INC | General Contractor | 2 | 07/08/2026 |
| HAPPY HOUSE CONSTRUCTION | General Contractor | 2 | 07/08/2026 |
| DRILON PLBG & HTG INC | Plumbing | 2 | 07/08/2026 |
| T.N.T. PLBG & HTG, INC | Plumbing | 1 | 07/08/2026 |
| L S SIGN | Scaffold | 1 | 07/08/2026 |
| NEPTUNE SIGNS AWNINGS | Scaffold | 1 | 07/08/2026 |
| N Y SIGN ART | Scaffold | 1 | 07/08/2026 |
| AUR0RA ELECL CONTG INC | Electrical | 1 | 03/22/2026 |
| UNITECH DESIGN | Scaffold | 1 | 07/08/2026 |
| A & F FIRE PROTECTION CO | Fire Protection | 1 | 07/08/2026 |
| FLINT MECHANICAL CORP | Fire Protection | 1 | 07/08/2026 |
| NEW YORK STANDARD MECH CO | Fire Protection | 1 | 07/08/2026 |
| RRP PLUMBING CORP | Fire Protection | 1 | 07/08/2026 |
| BLAKA COOL INC | General Contractor | 1 | 04/09/2026 |
| M-PAK CONSTRUCTION, INC | General Contractor | 1 | 04/09/2026 |
| FRANCO BELLI PLMG&HTG SON | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| DRAFT MASTER ENGINEERING | 701 | 3 | 11/04/2024 |
| RYAN SPECIAL ENGINEERING | 2018 | 2 | 08/19/2024 |
| ALLEN SHINFELD, P.E. PLLC | 1305 | 9 | 12/01/2023 |
| Z & T ENGINEERING, P.C. | 591 | 5 | 11/13/2023 |
| UNIVERSAL TESTING AND INS | 400 | 8 | 02/17/2022 |
| CENTURY TESTING & CONSULT | 4081 | 1 | 07/24/2020 |
| DAVI ARCHITECTURE, PC | 5168 | 1 | 09/20/2019 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | BLETSAS P&H CORP | 05/23/2025 |
| DOB NOW | Mechanical Systems | Signed-off | BLAKA COOL INC | 09/24/2024 |
| DOB NOW | Sprinklers | Signed-off | RALPH W. LANDOLFI JR. | 01/03/2024 |
| DOB NOW | Plumbing | Signed-off | DW PLUMBING INC | 10/18/2023 |
| DOB NOW | Plumbing | Signed-off | DRILON PLBG & HTG INC | 09/06/2023 |
| DOB NOW | Sign | Signed-off | NEPTUNE SIGNS&AWNINGS INC | 08/03/2023 |
| DOB NOW | Sprinklers | Signed-off | NEW YORK STANDARD MECH CO | 07/26/2023 |
| DOB NOW | Plumbing | Signed-off | DW PLUMBING INC | 07/14/2023 |
| DOB NOW | Sign | Signed-off | SKANSKA BUILDING INC | 07/05/2023 |
| DOB NOW | Sign | Signed-off | UNITECH DESIGN INC | 06/26/2023 |
| DOB NOW | Plumbing | Signed-off | DW PLUMBING INC | 06/13/2023 |
| DOB NOW | Sprinklers | Signed-off | DRILON PLBG & HTG INC | 06/12/2023 |
| DOB NOW | Mechanical Systems | Signed-off | HAPPY HOUSE CONSTRUCTION | 06/07/2023 |
| DOB NOW | General Construction | Signed-off | HAPPY HOUSE CONSTRUCTION | 05/09/2023 |
| DOB NOW | Mechanical Systems | Signed-off | M-PAK CONSTRUCTION, INC | 05/08/2023 |
| DOB NOW | Mechanical Systems | Signed-off | ACS SYSTEM ASSOCIATES INC. | 04/26/2023 |
| DOB NOW | Mechanical Systems | Signed-off | ACS SYSTEM ASSOCIATES INC. | 05/05/2022 |
| DOB NOW | Mechanical Systems | Signed-off | ACS SYSTEM ASSOCIATES INC. | 04/04/2022 |
| DOB NOW | Structural | Signed-off | BRICKENS CONSTRUCTION,INC | 03/29/2022 |
| DOB NOW | General Construction | Signed-off | BRICKENS CONSTRUCTION,INC | 03/28/2022 |
| DOB NOW | Plumbing | Signed-off | FRANCO BELLI PLMG&HTG SON | 03/01/2022 |
| DOB NOW | Sprinklers | Signed-off | ADVANCED AUTO SPR.CO.,INC | 02/28/2022 |
| DOB NOW | Mechanical Systems | Signed-off | ACS SYSTEM ASSOCIATES INC. | 02/25/2022 |
| DOB NOW | Plumbing | Signed-off | ARANDA PLBG & HTG CORP | 10/05/2021 |
| DOB NOW | Sign | Signed-off | WEINFELD, ELLIOT | 09/14/2021 |
| DOB NOW | Plumbing | Signed-off | ARANDA PLBG & HTG CORP | 09/01/2021 |
| DOB NOW | Plumbing | Signed-off | ARANDA PLBG & HTG CORP | 06/29/2021 |
| DOB NOW | Mechanical Systems | Signed-off | MEGA MECHANICAL INC | 06/24/2021 |
| DOB NOW | Plumbing | Signed-off | A. M. PLUMBING COMPANY | 12/23/2020 |
| DOB NOW | Plumbing | Signed-off | ARANDA PLBG & HTG CORP | 08/05/2020 |
| DOB NOW | Plumbing | Signed-off | A. M. PLUMBING COMPANY | 02/19/2020 |
| DOB NOW | Plumbing | Signed-off | A. M. PLUMBING COMPANY | 11/25/2019 |
| DOB NOW | Plumbing | Signed-off | T.N.T. PLBG & HTG, INC | 10/16/2019 |
| BIS | OT | ISSUED | JUAHOL CONSTRUCTION INC | 06/15/2020 |
| BIS | PL | ISSUED | BEDROCK PLBG. & HTG., INC | 04/15/2019 |
| BIS | EQ | ISSUED | INTERSYSTEM S&S CORP | 12/05/2018 |
| BIS | FP | ISSUED | METFLOW FIRE CONTROL LLC | 11/13/2018 |
| BIS | SP | ISSUED | CAPITOL FIRE SPRINKLER CO | 10/16/2018 |
| BIS | EQ | ISSUED | INTERSYSTEM S&S CORP | 07/06/2018 |
| BIS | OT | ISSUED | REIDY CONTRACTING GROUP | 06/29/2018 |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/11/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 07/02/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 01/12/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 01/08/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 11/09/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/26/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 10/20/2023 | Certified Sprinkler (PL)-SP-Fixtures (PL)-Finish | Certified | View ↗ |
| 10/18/2023 | Certified Sprinkler (PL)-Sprinkler-Hydro | Certified | View ↗ |
| 09/28/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 09/21/2023 | Pass-Final Sign Permit Inspection | Pass | View ↗ |
| 09/11/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/14/2023 | Pass-Final Sign Permit Inspection | Pass | View ↗ |
| 06/28/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/22/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 09/12/2022 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 09/12/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 08/22/2022 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 08/22/2022 | Certified Sprinkler - SP - Roughing | Certified | View ↗ |
| 08/02/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 06/14/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/27/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 09/28/2021 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/06/2021 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 11/19/2024 | Final | William Ryan | progress |
| 11/19/2024 | HVAC-R and service water piping design and insulation | ANTHONY GURBALL | energy_progress |
| 11/19/2024 | HVAC-R and service water heating system controls | ANTHONY GURBALL | energy_progress |
| 11/19/2024 | HVAC-R and service water heating equipment | ANTHONY GURBALL | energy_progress |
| 11/19/2024 | Maintenance information | ANTHONY GURBALL | energy_progress |
| 11/19/2024 | Mechanical Systems | ANTHONY GURBALL | special |
| 11/19/2024 | Fire-Resistant Penetrations and Joints | ANTHONY GURBALL | special |
| 11/19/2024 | Tenant Protection Plan Compliance | William Ryan | special |
| 11/19/2024 | Energy Code Compliance Inspections | ANTHONY GURBALL | progress |
| 10/30/2024 | HVAC-R and service water piping design and insulation | ANTHONY GURBALL | energy_progress |
| 10/30/2024 | HVAC-R and service water heating system controls | ANTHONY GURBALL | energy_progress |
| 10/30/2024 | HVAC-R and service water heating equipment | ANTHONY GURBALL | energy_progress |
| 10/30/2024 | Final | William Ryan | progress |
| 10/30/2024 | Energy Code Compliance Inspections | ANTHONY GURBALL | progress |
| 10/30/2024 | Fire-Resistant Penetrations and Joints | ANTHONY GURBALL | special |
| 10/30/2024 | Mechanical Systems | ANTHONY GURBALL | special |
| 10/30/2024 | Tenant Protection Plan Compliance | — | special |
| 10/30/2024 | Maintenance information | ANTHONY GURBALL | energy_progress |
| 12/01/2023 | Tenant Protection Plan Compliance | Fei Zeng | special |
| 12/01/2023 | Sprinkler Systems | Fei Zeng | special |
| 11/27/2023 | Fire-Resistant Penetrations and Joints | ALLEN SHINFELD | special |
| 11/27/2023 | Energy Code Compliance Inspections | ALLEN SHINFELD | progress |
| 11/27/2023 | Tenant Protection Plan Compliance | ALLEN SHINFELD | special |
| 11/27/2023 | Sprinkler Systems | ALLEN SHINFELD | special |
| 10/13/2023 | Energy Code Compliance Inspections | ALLEN SHINFELD | progress |