💬 Discuss this project
1901Year Built
2Stories
C0Building Class
R5AZoning
4,306 sfGross Floor Area
3Units
Rent Stabilized60 Active Violations ▸
Three families · 3,125 sf lot · 1.38 FAR built · Flood zone X
Locations of Work
ArchitectureElectricalPlumbingCivilGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Floor 2Layout changes as per final built construction15p · 2 filings · 20 docs
Floor 1Layout changes as per final built construction22p · 2 filings · 20 docs
CellarLayout changes as per final built construction16p · 2 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Ecua2310/13/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
10/07/2019$1.1M—Private party → Ecua$247/sf building
10/03/2018$13K—— → —$3/sf building
10/01/2018$20K—— → —$5/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Arcalhek509/14/2026
Salvatore Italiano R.A208/25/2020
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Building803/21/2026
Camg Consultants203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
A&A Building ConsultantsGeneral Contractor403/21/2026
Renew PlumbingPlumbing107/08/2026
Building Lifecycle
All (130)Filed (7)Permit Issued (3)Signed Off (1)Violation (60)Inspection (5)Objection (30)Special Inspection (24)
09/15/2026
Special inspection requirement — Interior lighting power
RAYMOND CALAMARI
09/15/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
RAYMOND CALAMARI
09/15/2026
Special inspection requirement — Fenestration areas
RAYMOND CALAMARI
09/15/2026
Special inspection requirement — Fenestration air leakage
RAYMOND CALAMARI
09/15/2026
Special inspection requirement — Insulation placement and R values
RAYMOND CALAMARI
09/15/2026
Special inspection requirement — Protection of exposed foundation insulation
RAYMOND CALAMARI
09/15/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
09/15/2026
Special inspection requirement — Concrete - Precast
09/15/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
09/15/2026
Special inspection requirement — Concrete - Cast-In-Place
09/15/2026
Special inspection requirement — Energy Code Compliance Inspections
09/15/2026
Special inspection requirement — Fire-Resistance Rated Construction
09/14/2026
Filed — Alteration CO
Propose new curb cut
Q00840170-P3
06/17/2026
Signed off — Alteration CO
Propose new curb cut
Q00840170-S1
06/16/2026
Inspection — Pass-Final Curb Cut Non-Directive 14
Pass
View inspection ↗
05/07/2026
Violation issued (HPD, open)
A
04/15/2026
Inspection — Fail-Final Curb Cut Non-Directive 14
Fail
View inspection ↗
04/09/2026
Inspection — Fail-Final Curb Cut Non-Directive 14
Fail
View inspection ↗
01/06/2026
Permit issued — Curb Cut
Q00840170-S1-CC
12/16/2025
Objection resolved — Addressed
12/16/2025
Objection resolved — Addressed
12/16/2025
Objection resolved — Addressed
12/16/2025
Objection resolved — Addressed
12/11/2025
Objection raised — Zoning
12/11/2025
Objection raised — Scope
12/11/2025
Objection raised — Admin
12/11/2025
Objection raised — Zoning
12/01/2025
Filed — Alteration CO
Propose new curb cut
Q00840170-S1
11/03/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
09/22/2025
Objection resolved — Addressed
09/19/2025
Objection raised — Admin
09/05/2025
Filed — Alteration CO
Propose new curb cut
Q00840170-P2
04/08/2025
Special inspection requirement — Fenestration areas
RAYMOND CALAMARI
04/08/2025
Special inspection requirement — Insulation placement and R values
RAYMOND CALAMARI
04/08/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
RAYMOND CALAMARI
04/08/2025
Special inspection requirement — Protection of exposed foundation insulation
RAYMOND CALAMARI
04/08/2025
Special inspection requirement — Interior lighting power
RAYMOND CALAMARI
04/08/2025
Special inspection requirement — Fenestration air leakage
RAYMOND CALAMARI
12/24/2024
Inspection — Fail-Final CND-Occupancy Inspection
Fail
View inspection ↗
12/02/2024
Violation issued (HPD, closed)
I
09/04/2024
Violation issued (ECB, closed)
Construction
08/27/2024
Permit issued — General Construction
Q00840170-I1-GC
08/01/2024
Objection resolved — Addressed
07/11/2024
Special inspection requirement — Fenestration and door U-factor and product ratings
07/11/2024
Special inspection requirement — Fenestration areas
07/11/2024
Special inspection requirement — Protection of exposed foundation insulation
07/11/2024
Special inspection requirement — Insulation placement and R values
07/11/2024
Special inspection requirement — Interior lighting power
07/11/2024
Special inspection requirement — Fenestration air leakage
06/17/2024
Objection raised — Energy
06/10/2024
Filed — Alteration CO
Propose new curb cut
Q00840170-P1
04/15/2024
Violation issued (HPD, closed)
A
01/09/2024
Violation issued (ECB, closed)
Construction
11/24/2023
Violation issued (HPD, closed)
I
10/16/2023
Objection resolved — Addressed
10/16/2023
Objection resolved — Addressed
10/16/2023
Objection resolved — Addressed
10/16/2023
Objection resolved — Addressed
10/12/2023
Objection resolved — Addressed
10/12/2023
Objection resolved — Addressed
Latest 60 of 130 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWCurb CutSigned-offA&A Building Consultants01/06/2026
DOB NOWGeneral ConstructionPermit IssuedA&A Building Consultants08/27/2024
DOB NOWPlumbingSigned-offRenew Plumbing07/07/2020
BISOTISSUEDSegura Contracting02/20/2020
1 project · most recent 08/25/2020
Gas Water/Sanitary
FiledStatusContractorScope
08/25/2020Signed-offRenew PlumbingGas, Water/Sanitary
1 project · most recent 03/16/2020
General Wiring Lighting
FiledStatusContractorScope
03/16/2020CompleteBDS ElectricGeneral Wiring, Lighting
1 project · most recent 09/14/2026
FiledStatusContractorScope
09/14/2026Signed-offA&A Building Consultants1 scope_items
▾Field Inspections (DOB CAP) — 5
DateTypeResultReport
06/16/2026Pass-Final Curb Cut Non-Directive 14PassView ↗
04/15/2026Fail-Final Curb Cut Non-Directive 14FailView ↗
04/09/2026Fail-Final Curb Cut Non-Directive 14FailView ↗
11/03/2025Pass-Final CND-Occupancy InspectionPassView ↗
12/24/2024Fail-Final CND-Occupancy InspectionFailView ↗
▾Special Inspection Requirements (DOB NOW) — 24
DateRequirementInspectorRole
09/15/2026Interior lighting powerRAYMOND CALAMARIenergy_progress
09/15/2026Fenestration and door U-factor and product ratingsRAYMOND CALAMARIenergy_progress
09/15/2026Fenestration areasRAYMOND CALAMARIenergy_progress
09/15/2026Fenestration air leakageRAYMOND CALAMARIenergy_progress
09/15/2026Insulation placement and R valuesRAYMOND CALAMARIenergy_progress
09/15/2026Protection of exposed foundation insulationRAYMOND CALAMARIenergy_progress
09/15/2026Fire-Resistant Penetrations and Joints—special
09/15/2026Concrete - Precast—special
09/15/2026Structural Stability – Alterations of existing buildings—special
09/15/2026Concrete - Cast-In-Place—special
09/15/2026Energy Code Compliance Inspections—progress
09/15/2026Fire-Resistance Rated Construction—progress
04/08/2025Fenestration areasRAYMOND CALAMARIenergy_progress
04/08/2025Insulation placement and R valuesRAYMOND CALAMARIenergy_progress
04/08/2025Fenestration and door U-factor and product ratingsRAYMOND CALAMARIenergy_progress
04/08/2025Protection of exposed foundation insulationRAYMOND CALAMARIenergy_progress
04/08/2025Interior lighting powerRAYMOND CALAMARIenergy_progress
04/08/2025Fenestration air leakageRAYMOND CALAMARIenergy_progress
07/11/2024Fenestration and door U-factor and product ratings—energy_progress
07/11/2024Fenestration areas—energy_progress
07/11/2024Protection of exposed foundation insulation—energy_progress
07/11/2024Insulation placement and R values—energy_progress
07/11/2024Interior lighting power—energy_progress
07/11/2024Fenestration air leakage—energy_progress
▾Documents — 59 on file (BIS + DOB NOW)
▸Plans & Drawings7
▸DOB NOWPlans/Sketch5
08/19/2026Q00840170-I1Request digital key ↗
08/19/2026Q00840170-P2Request digital key ↗
08/19/2026Q00840170-S1Request digital key ↗
Showing 3 of 5 on file for this type
▸DOB NOWPlans/Sketch - Plumbing2
08/28/2026Q00359294-I1Request digital key ↗
08/15/2026Q00359294-P1Request digital key ↗
▸Applications & Permits4
▸BISPLAN / WORK APPROVAL APPLICATION3
11/17/2020421779203Open ↗
09/28/2020421779203Open ↗
12/19/2019421779203Open ↗
▸BISWORK PERMIT APPLICATION1
03/07/2020421779203Open ↗
▸Zoning, Tax Lot & Property Records1
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026Q00840170-I1Open ↗
▸Seals & Professional Certifications21
▸DOB NOWProgress Inspector Seal & Signature12
10/01/2026Q00840170-I1Open ↗
10/01/2026Q00840170-I1Open ↗
10/01/2026Q00840170-I1Open ↗
Showing 3 of 12 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature7
08/28/2026Q00359294-P1Open ↗
08/28/2026Q00359294-I1Open ↗
08/19/2026Q00840170-P3Open ↗
Showing 3 of 7 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION2
03/07/2020421779203Open ↗
02/14/2020421779203Open ↗
▸Safety & Tenant Protection6
▸DOB NOWStreet Tree Checklist4
08/19/2026Q00840170-P3Open ↗
08/13/2026Q00840170-P1Open ↗
08/13/2026Q00840170-P2Open ↗
Showing 3 of 4 on file for this type
▸BISEXCAVATION OR DEMOLITION: 5-DAY NOTICE1
03/11/2020421779203Open ↗
▸BISDEMOLITION SUBMITTAL CERTIFICATION FORM1
03/07/2020421779203Open ↗
▸Environmental & Asbestos3
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/28/2026Q00359294-P1Open ↗
08/28/2026Q00359294-I1Open ↗
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
02/14/2020421779203Open ↗
▸Energy Compliance2
▸BISAS-BUILT ENERGY ANALYSIS1
12/14/2021421779203Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS1
02/14/2020421779203Open ↗
▸Inspections & Test Reports2
▸BISTECHNICAL REPORT: RESPONSIBILITY2
12/14/2021421779203Open ↗
12/14/2021421779203Open ↗
▸Approvals, Objections & Sign-offs1
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
12/17/2021421779203Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT2
12/14/2021421779203Open ↗
02/14/2020421779203Open ↗
▸Filing & Intake Forms5
▸BISADDITIONAL INFORMATION4
12/17/2021421779203Open ↗
12/17/2020421779203Open ↗
12/10/2020421779203Open ↗
Showing 3 of 4 on file for this type
▸BISEFILING COVER SHEET1
12/19/2019421779203Open ↗
▸Other Documents5
▸DOB NOWProperty Ownership Certification4
08/19/2026Q00840170-P3Open ↗
08/13/2026Q00840170-I1Open ↗
08/13/2026Q00840170-P2Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWFinal Survey1
08/19/2026Q00840170-I1Open ↗