← Back
Factory, industrial, semi-fireproof
34-20 64 STREET
QUEENS · BIN 4027183
💬 Discuss this project
1930Year Built
1Stories
F4Building Class
M1-1Zoning
10,000 sfGross Floor Area
1Units
0 Open Violations
Factory, industrial, semi-fireproof · Owner of record: KETCHAM PUMP CO INC · 10,000 sf lot · 1 FAR built · Flood zone X
Locations of Work
ArchitectureMechanical
Roof2p · 1 filing · 19 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
KETCHAM PUMP COMPANY907/08/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
COLOMBO ARCHITECTURAL STUDIO PC208/21/2019
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
INDY ELECTRIC CORP.Electrical103/22/2026
WILLDAN ELECTRICAL OF NYElectrical103/22/2026
R & Z HEATING AND AIRGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
COLOMBO ARCHITECTURAL STU4930208/21/2019
Building Lifecycle
All (21)Filed (2)Permit Issued (1)Signed Off (1)Violation (4)Special Inspection (13)
01/02/2024
Violation issued (ECB, closed)
Construction
11/15/2019
Signed off — Alteration
Direct replacement of split system HVAC unit to supply office space including condenser at roof and air handler at first floor only to connect to existing ductwork. No change in use, egress or occupancy.
Q00189240-I1
08/22/2019
Permit issued — Mechanical Systems
Q00189240-I1-MS
08/21/2019
Filed — Alteration
Direct replacement of split system HVAC unit to supply office space including condenser at roof and air handler at first floor only to connect to existing ductwork. No change in use, egress or occupancy.
Q00189240-P1
08/21/2019
Special inspection requirement — Fire-Resistant Penetrations and Joints
Yahaira Volquez Colombo
08/21/2019
Special inspection requirement — Mechanical Systems
Yahaira Volquez Colombo
08/21/2019
Special inspection requirement — Smoke Control Systems Testing
Yahaira Volquez Colombo
08/21/2019
Special inspection requirement — Final
Yahaira Volquez Colombo
08/21/2019
Special inspection requirement — Energy Code Compliance Inspections
Yahaira Volquez Colombo
08/21/2019
Special inspection requirement — Electrical motors
Yahaira Volquez Colombo
08/21/2019
Special inspection requirement — Maintenance information
Yahaira Volquez Colombo
08/21/2019
Special inspection requirement — HVAC and service water heating system controls
Yahaira Volquez Colombo
08/21/2019
Special inspection requirement — HVAC and service water heating equipment
Yahaira Volquez Colombo
08/21/2019
Special inspection requirement — Permanent certificate
Yahaira Volquez Colombo
08/21/2019
Special inspection requirement — HVAC insulation and sealing
Yahaira Volquez Colombo
08/21/2019
Special inspection requirement — Duct leakage testing
Yahaira Volquez Colombo
08/21/2019
Special inspection requirement — Shutoff dampers
Yahaira Volquez Colombo
07/20/2019
Filed — Alteration
Direct replacement of split system HVAC unit to supply office space including condenser at roof and air handler at first floor only to connect to existing ductwork. No change in use, egress or occupancy.
Q00189240-I1
01/01/2009
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
01/19/2007
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
01/19/2007
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsSigned-offR & Z HEATING AND AIR08/22/2019
BISBLISSUEDSTANDARD HEAT, INC.05/11/2004
BISBLISSUEDWAYWOLFF ASSOCIATES02/15/1995
3 projects · most recent 06/06/2022
General Wiring
FiledStatusContractorScope
06/06/2022CompleteWILLDAN ELECTRICAL OF NYGeneral Wiring
04/06/2022CompleteWILLDAN ELECTRICAL OF NY—
09/24/2019CompleteINDY ELECTRIC CORP.General Wiring
▾Special Inspection Requirements (DOB NOW) — 13
DateRequirementInspectorRole
08/21/2019Fire-Resistant Penetrations and JointsYahaira Volquez Colombospecial
08/21/2019Mechanical SystemsYahaira Volquez Colombospecial
08/21/2019Smoke Control Systems TestingYahaira Volquez Colombospecial
08/21/2019FinalYahaira Volquez Colomboprogress
08/21/2019Energy Code Compliance InspectionsYahaira Volquez Colomboprogress
08/21/2019Electrical motorsYahaira Volquez Colomboenergy_progress
08/21/2019Maintenance informationYahaira Volquez Colomboenergy_progress
08/21/2019HVAC and service water heating system controls Yahaira Volquez Colomboenergy_progress
08/21/2019HVAC and service water heating equipment Yahaira Volquez Colomboenergy_progress
08/21/2019Permanent certificateYahaira Volquez Colomboenergy_progress
08/21/2019HVAC insulation and sealing Yahaira Volquez Colomboenergy_progress
08/21/2019Duct leakage testing Yahaira Volquez Colomboenergy_progress
08/21/2019Shutoff dampersYahaira Volquez Colomboenergy_progress
▾Documents — 19 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch - Mechanical Systems2
08/28/2026Q00189240-I1Request digital key ↗
08/15/2026Q00189240-P1Request digital key ↗
▸Seals & Professional Certifications15
▸DOB NOWProgress Inspector Seal & Signature10
08/30/2026Q00189240-I1Open ↗
08/30/2026Q00189240-I1Open ↗
08/30/2026Q00189240-I1Open ↗
Showing 3 of 10 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature3
08/30/2026Q00189240-I1Open ↗
08/30/2026Q00189240-I1Open ↗
08/30/2026Q00189240-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/28/2026Q00189240-P1Open ↗
08/28/2026Q00189240-I1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/28/2026Q00189240-P1Open ↗
08/28/2026Q00189240-I1Open ↗