| Owner | Filings | Most Recent |
|---|---|---|
| New York City Housing Authority | 100 | 10/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| Liro Architects + Planners | 4 | 09/24/2026 |
| The Liro Group | 7 | 11/03/2025 |
| BGM Engineering | 2 | 10/27/2025 |
| Synergic Design Architects | 1 | 03/21/2025 |
| NYMS Consulting | 5 | 10/29/2023 |
| Ventrop Engineering Consulting Group | 1 | 03/03/2023 |
| Liro Engineers | 3 | 01/04/2023 |
| Ysrael A. Seinuk | 2 | 12/07/2022 |
| Arquitectura Varela | 1 | 11/11/2022 |
| Ashraf | 1 | 09/23/2021 |
| Tectonic Engineering | 1 | 01/08/2021 |
| Com-EX Engineering of NY | 1 | 12/02/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| Self Employed | 4 | 03/21/2026 |
| Design Approve Build | 26 | 03/21/2026 |
| GC1 Expediting | 2 | 03/21/2026 |
| Construction Permit Services | 1 | 03/21/2026 |
| KM Associates of New York | 1 | 03/21/2026 |
| K & M Associates | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Maric Mechanical | specialty_contractor | 38 | 07/08/2026 |
| FJP Mechanical | Plumbing | 12 | 10/21/2026 |
| Maric Mechanical | Scaffold | 7 | 07/08/2026 |
| Rennon Construction | Scaffold | 3 | 07/08/2026 |
| Accord Power | General Contractor | 3 | 04/09/2026 |
| Construction Services Con NY | Scaffold | 3 | 03/21/2026 |
| Applied Electric | Electrical | 1 | 03/21/2026 |
| Jacobs Telecommun | General Contractor | 1 | 07/08/2026 |
| HY-Lee Electric Co | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Distinct Engineering Solu | 2641 | 22 | 09/24/2026 |
| Synergic Design | 8561 | 1 | 03/21/2025 |
| Elevated Engineering | 3692 | 1 | 12/02/2019 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Boiler Equipment | Permit Issued | FJP Mechanical | 10/20/2026 |
| DOB NOW | General Construction | Permit Issued | Maric Mechanical | 03/18/2026 |
| DOB NOW | Structural | Permit Issued | Maric Mechanical | 03/18/2026 |
| DOB NOW | Mechanical Systems | Signed-off | Maric Mechanical | 03/18/2026 |
| DOB NOW | Solar | Permit Issued | Accord Power | 03/03/2026 |
| DOB NOW | Boiler Equipment | Signed-off | FJP Mechanical | 10/15/2025 |
| DOB NOW | Plumbing | Permit Issued | FJP Mechanical | 09/15/2025 |
| DOB NOW | Solar | Permit Issued | Accord Power | 04/09/2025 |
| DOB NOW | General Construction | Permit Issued | Maric Mechanical | 03/17/2025 |
| DOB NOW | Structural | Permit Issued | Maric Mechanical | 03/17/2025 |
| DOB NOW | Support of Excavation | Signed-off | Maric Mechanical | 03/17/2025 |
| DOB NOW | Structural | Signed-off | Maric Mechanical | 03/17/2025 |
| DOB NOW | Construction Fence | Signed-off | Maric Mechanical | 03/17/2025 |
| DOB NOW | Mechanical Systems | Signed-off | Maric Mechanical | 03/17/2025 |
| DOB NOW | Plumbing | Signed-off | FJP Mechanical | 03/13/2025 |
| DOB NOW | Structural | Signed-off | Maric Mechanical | 01/08/2025 |
| DOB NOW | General Construction | Permit Issued | Maric Mechanical | 01/06/2025 |
| DOB NOW | Support of Excavation | Signed-off | Maric Mechanical | 01/06/2025 |
| DOB NOW | Mechanical Systems | Signed-off | Maric Mechanical | 01/06/2025 |
| DOB NOW | Construction Fence | Signed-off | Maric Mechanical | 01/06/2025 |
| DOB NOW | Structural | Permit Issued | Maric Mechanical | 01/06/2025 |
| DOB NOW | Boiler Equipment | Signed-off | FJP Mechanical | 11/26/2024 |
| DOB NOW | Plumbing | Permit Issued | FJP Mechanical | 09/10/2024 |
| DOB NOW | Support of Excavation | Signed-off | Maric Mechanical | 07/31/2024 |
| DOB NOW | Construction Fence | Signed-off | Maric Mechanical | 04/04/2024 |
| DOB NOW | Mechanical Systems | Signed-off | Maric Mechanical | 03/20/2024 |
| DOB NOW | Structural | Signed-off | Maric Mechanical | 03/20/2024 |
| DOB NOW | General Construction | Permit Issued | Maric Mechanical | 03/20/2024 |
| DOB NOW | Structural | Permit Issued | Maric Mechanical | 03/19/2024 |
| DOB NOW | Plumbing | Signed-off | FJP Mechanical | 03/11/2024 |
| DOB NOW | Plumbing | Signed-off | FJP Mechanical | 12/11/2023 |
| DOB NOW | Boiler Equipment | Signed-off | FJP Mechanical | 10/11/2023 |
| DOB NOW | Plumbing | Permit Issued | FJP Mechanical | 09/15/2023 |
| DOB NOW | Mechanical Systems | Permit Issued | Maric Mechanical | 08/30/2023 |
| DOB NOW | Boiler Equipment | Signed-off | FJP Mechanical | 06/27/2023 |
| DOB NOW | Structural | Signed-off | Maric Mechanical | 04/03/2023 |
| DOB NOW | Structural | Permit Issued | Maric Mechanical | 03/31/2023 |
| DOB NOW | Mechanical Systems | Signed-off | Maric Mechanical | 03/27/2023 |
| DOB NOW | Construction Fence | Signed-off | Maric Mechanical | 03/23/2023 |
| DOB NOW | General Construction | Permit Issued | Maric Mechanical | 03/22/2023 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 09/24/2026 | Permit Issued | Maric Mechanical | Associated Ducts and Piping, Heating Systems, Ventilation Systems | Heating Johnston pftx-300-4-15 Boiler ×14 Ventilation Loren Cook 100SQN17D 4,200 CFM · Exhaust Fan ×1 Ducts & Piping N/A NA 1 BTU · Ductwork ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/24/2026 | Permit Issued | FJP Mechanical | Gas, Storm, Water/Sanitary |
| 09/13/2023 | Permit Issued | FJP Mechanical | Gas |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/05/2026 | Complete | A.T.J. Electrical Co | General Wiring |
| 03/05/2025 | Permit Issued | Accord Power Electric | 2 meters, 1 new_meters |
| 06/27/2023 | Complete | Tri-State Electrical & Mechanical I | General Wiring |
| 06/23/2023 | Complete | Tri-State Electrical & Mechanical I | General Wiring |
| 03/06/2023 | Permit Issued | Tru-Val Electric | — |
| 09/01/2022 | Permit Issued | Tru-Val Electric | General Wiring, Lighting |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/24/2026 | Permit Issued | FJP Mechanical | Steel, Concrete |
| 03/03/2023 | Signed-off | Maric Mechanical | 1 scope_items |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/21/2025 | Permit Issued | Accord Power | 130 panels, 70.85 kw, 14,265.64 roof_area_sqft |
| Date | Type | Result | Report |
|---|---|---|---|
| 10/28/2025 | Pass-Final Boiler Equipment Inspection | Pass | View ↗ |
| 07/09/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/13/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 04/16/2025 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 02/25/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 02/05/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 09/21/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 09/17/2026 | Fire-Resistant Penetrations and Joints | YAZAN YANES | special |
| 09/17/2026 | Fenestration and door U-factor and product ratings | YAZAN YANES | energy_progress |
| 09/17/2026 | Final | — | progress |
| 09/17/2026 | Fire-Resistance Rated Construction | YAZAN YANES | progress |
| 09/17/2026 | Energy Code Compliance Inspections | YAZAN YANES | progress |
| 11/17/2025 | Tenant Protection Plan Compliance | — | special |
| 11/17/2025 | Structural Steel - Details | Ramnarayan Tirumala | special |
| 11/17/2025 | Excavations - Sheeting, Shoring, and Bracing | Ramnarayan Tirumala | special |
| 11/17/2025 | Structural Steel - Welding | Ramnarayan Tirumala | special |
| 10/29/2025 | HVAC-R and service water heating equipment | Ramnarayan Tirumala | energy_progress |
| 10/29/2025 | Heating Systems | Ramnarayan Tirumala | special |
| 10/29/2025 | Tenant Protection Plan Compliance | — | special |
| 10/29/2025 | HVAC-R and service water heating system controls | — | energy_progress |
| 10/29/2025 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 10/22/2025 | Tenant Protection Plan Compliance | — | special |
| 10/22/2025 | Excavations - Sheeting, Shoring, and Bracing | Ramnarayan Tirumala | special |
| 10/22/2025 | Structural Steel - Details | Ramnarayan Tirumala | special |
| 10/22/2025 | Structural Steel - Welding | Ramnarayan Tirumala | special |
| 09/03/2025 | Tenant Protection Plan Compliance | YAZAN YANES | special |
| 08/08/2025 | Tenant Protection Plan Compliance | YAZAN YANES | special |
| 08/07/2025 | HVAC-R and service water heating equipment | YAZAN YANES | energy_progress |
| 08/07/2025 | HVAC-R and service water heating system controls | YAZAN YANES | energy_progress |
| 08/07/2025 | HVAC-R and service water piping design and insulation | YAZAN YANES | energy_progress |
| 05/28/2025 | Fire-Resistant Penetrations and Joints | YAZAN YANES | special |
| 05/28/2025 | Post-installed Anchors | YAZAN YANES | special |