← Back
Two stories - detached, small or mid-size
34-43 88 STREET
QUEENS · BIN 4035669
💬 Discuss this project
1930Year Built
2.75Stories
A1Building Class
R5Zoning
2,092 sfGross Floor Area
1Units
Two stories - detached, small or mid-size · 2,742 sf lot · 0.76 FAR built · Flood zone X
Locations of Work
MechanicalPlumbing
Floor 32p · 1 filing · 11 docs
Floor 22p · 1 filing · 11 docs
Floor 12p · 1 filing · 11 docs
Cellar1p · 1 filing · 6 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
04/19/2021$1.4M—— → —$645/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
KELLEY DESIGN304/10/2023
TWIG CONSULTING ENGINEERS PC107/24/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
PROGENY MANAGEMENT & EXPEDITING SER603/21/2026
FRANKLYN ESTRELLA ARCHITECT PLLC103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
ROBIN SYSTEMS INCGeneral Contractor403/21/2026
GAUDIOSO CONTRACTING INCGeneral Contractor307/08/2026
L.L.G. PLBG & HTG INCPlumbing207/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
ERIK SUN, ARCHITECT, PLLC3010110/06/2021
AR-TECH ENGINEERING, P.C.6659107/24/2021
Building Lifecycle
All (32)Filed (4)Permit Issued (6)Signed Off (2)Inspection (5)Special Inspection (15)
07/29/2024
Signed off — Alteration
Q00604028-I1
12/07/2023
Signed off — Alteration
CELLAR RELOCATION OF LAUNDRY, REMOVE SHOWER, INSTALL NEW HOT WATER HEATER; FIRST FLOOR NEW GAS LINE; SECOND FLOOR RELOCATE WC, LAV, INSTALL NEW LAV, RELOCATE SHOWER AND INSTALL STEAM UNIT.
Q00607595-I1
04/10/2023
Filed — Alteration
CELLAR RELOCATION OF LAUNDRY, REMOVE SHOWER, INSTALL NEW HOT WATER HEATER; FIRST FLOOR NEW GAS LINE; SECOND FLOOR RELOCATE WC, LAV, INSTALL NEW LAV, RELOCATE SHOWER AND INSTALL STEAM UNIT.
Q00607595-P1
12/14/2022
Permit issued — Plumbing
Q00607595-I1-PL
12/12/2022
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
11/21/2022
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
05/19/2022
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
05/18/2022
Permit issued — General Construction
Q00604028-I1-GC-CX
04/22/2022
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
02/04/2022
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
12/06/2021
Permit issued — Plumbing
Q00607595-I1-PL
10/25/2021
Permit issued — General Construction
Q00604028-I1-GC-CX
10/06/2021
Filed — Alteration
Q00604028-I1
10/06/2021
Filed — Alteration
CELLAR RELOCATION OF LAUNDRY, REMOVE SHOWER, INSTALL NEW HOT WATER HEATER; FIRST FLOOR NEW GAS LINE; SECOND FLOOR RELOCATE WC, LAV, INSTALL NEW LAV, RELOCATE SHOWER AND INSTALL STEAM UNIT.
Q00607595-I1
09/30/2021
Special inspection requirement — Structural Stability – Alterations of existing buildings
ERIK SUN
09/30/2021
Special inspection requirement — Final
Beth Kelley
09/30/2021
Special inspection requirement — Fenestration air leakage
Beth Kelley
09/30/2021
Special inspection requirement — Interior lighting power
Beth Kelley
09/30/2021
Special inspection requirement — Lighting controls
Beth Kelley
09/30/2021
Special inspection requirement — Lighting in dwelling units
Beth Kelley
09/30/2021
Special inspection requirement — Fenestration and door U-factor and product ratings
Beth Kelley
09/07/2021
Permit issued — Mechanical Systems
Q00562490-I1-MS
08/20/2021
Permit issued — Mechanical Systems
Q00562490-I1-MS
07/24/2021
Filed — Alteration
Installation of (2) 5 tons HVAC units at rear of property
Q00562490-I1
07/21/2021
Special inspection requirement — Mechanical Systems
ALBERTO ROMAN
07/21/2021
Special inspection requirement — Energy Code Compliance Inspections
ALBERTO ROMAN
07/21/2021
Special inspection requirement — Final
CALVIN TRAN
07/21/2021
Special inspection requirement — HVAC-R and service water piping design and insulation
ALBERTO ROMAN
07/21/2021
Special inspection requirement — HVAC-R and service water heating equipment
ALBERTO ROMAN
07/21/2021
Special inspection requirement — Maintenance information
ALBERTO ROMAN
07/21/2021
Special inspection requirement — Shutoff dampers
ALBERTO ROMAN
07/21/2021
Special inspection requirement — HVAC-R and service water heating system controls
ALBERTO ROMAN
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offL.L.G. PLBG & HTG INC12/14/2022
DOB NOWGeneral ConstructionSigned-offGAUDIOSO CONTRACTING05/18/2022
DOB NOWPlumbingSigned-offL.L.G. PLBG & HTG INC12/06/2021
DOB NOWGeneral ConstructionSigned-offGAUDIOSO CONTRACTING10/25/2021
DOB NOWMechanical SystemsPermit IssuedROBIN SYSTEMS INC09/07/2021
DOB NOWMechanical SystemsPermit IssuedROBIN SYSTEMS INC08/20/2021
1 project · most recent 07/24/2021
Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
07/24/2021Permit IssuedROBIN SYSTEMS INCAir Conditioning Systems
Cooling
Lg ARUN060GSS4 10 tons · Vrf Outdoor ×2
1 project · most recent 01/03/2022
General Wiring
FiledStatusContractorScope
01/03/2022Permit IssuedCRESCO ELECTRICAL CORPGeneral Wiring
▾Field Inspections (DOB CAP) — 5
DateTypeResultReport
12/12/2022Fail-Final PL - Up to 3 Requested FloorsFailView ↗
11/21/2022Fail-Final PL - Up to 3 Requested FloorsFailView ↗
05/19/2022Certified Gas-Gas-Piping-RoughingCertifiedView ↗
04/22/2022Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
02/04/2022Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 15
DateRequirementInspectorRole
09/30/2021Structural Stability – Alterations of existing buildingsERIK SUNspecial
09/30/2021FinalBeth Kelleyprogress
09/30/2021Fenestration air leakageBeth Kelleyenergy_progress
09/30/2021Interior lighting powerBeth Kelleyenergy_progress
09/30/2021Lighting controlsBeth Kelleyenergy_progress
09/30/2021Lighting in dwelling unitsBeth Kelleyenergy_progress
09/30/2021Fenestration and door U-factor and product ratingsBeth Kelleyenergy_progress
07/21/2021Mechanical SystemsALBERTO ROMANspecial
07/21/2021Energy Code Compliance InspectionsALBERTO ROMANprogress
07/21/2021FinalCALVIN TRANprogress
07/21/2021HVAC-R and service water piping design and insulationALBERTO ROMANenergy_progress
07/21/2021HVAC-R and service water heating equipmentALBERTO ROMANenergy_progress
07/21/2021Maintenance informationALBERTO ROMANenergy_progress
07/21/2021Shutoff dampersALBERTO ROMANenergy_progress
07/21/2021HVAC-R and service water heating system controlsALBERTO ROMANenergy_progress
▾Documents — 25 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch4
08/27/2026Q00562490-I1Request digital key ↗
08/27/2026Q00604028-I1Request digital key ↗
08/27/2026Q00607595-I1Request digital key ↗
Showing 3 of 4 on file for this type
▸Seals & Professional Certifications16
▸DOB NOWProgress Inspector Seal & Signature9
08/31/2026Q00604028-I1Open ↗
08/31/2026Q00604028-I1Open ↗
08/27/2026Q00562490-I1Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature4
08/27/2026Q00562490-I1Open ↗
08/27/2026Q00604028-I1Open ↗
08/13/2026Q00607595-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature3
08/31/2026Q00604028-I1Open ↗
08/31/2026Q00604028-I1Open ↗
08/27/2026Q00562490-I1Open ↗
▸Environmental & Asbestos4
▸DOB NOWDEP ACP-5: Asbestos Assessment Report4
08/27/2026Q00562490-I1Open ↗
08/27/2026Q00604028-I1Open ↗
08/13/2026Q00607595-I1Open ↗
Showing 3 of 4 on file for this type
▸Energy Compliance1
▸DOB NOWEN2: As Built Energy Analysis.1
08/13/2026Q00604028-I1Open ↗