← Back
Two stories - detached, small or mid-size
34 ALLISON AVENUE
STATEN ISLAND · New Dorp-Midland Beach · BIN 5057892
💬 Discuss this project
1945Year Built
2Stories
A1Building Class
R3XZoning
2,702 sfGross Floor Area
1Units
Two stories - detached, small or mid-size · 5,600 sf lot · 0.48 FAR built · Flood zone X
Locations of Work
ArchitectureElectrical
Roof5p · 1 filing · 13 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
NY BUILDING ASSOCIATES INC206/25/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
SUNCO CAPITAL403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SUNCO CAPITAL LLCGeneral Contractor203/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
NKM ENGINEERING PLLC6244206/25/2025
Building Lifecycle
All (14)Filed (2)Permit Issued (1)Signed Off (1)Special Inspection (10)
07/10/2025
Signed off — Alteration
INSTALLATION OF SOLAR PANELS ON ROOF. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
S01228528-I1
06/26/2025
Special inspection requirement — Air barrier - visual inspection
NARESH MAHANGU
06/26/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
NARESH MAHANGU
06/26/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
NARESH MAHANGU
06/26/2025
Special inspection requirement — Final
NARESH MAHANGU
06/26/2025
Special inspection requirement — Energy Code Compliance Inspections
NARESH MAHANGU
06/25/2025
Filed — Alteration
INSTALLATION OF SOLAR PANELS ON ROOF. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
S01228528-P1
06/23/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
NARESH MAHANGU
06/23/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
NARESH MAHANGU
06/23/2025
Special inspection requirement — Energy Code Compliance Inspections
NARESH MAHANGU
06/23/2025
Special inspection requirement — Final
NARESH MAHANGU
06/23/2025
Special inspection requirement — Air barrier - visual inspection
NARESH MAHANGU
05/27/2025
Permit issued — Solar
S01228528-I1-SL
05/21/2025
Filed — Alteration
INSTALLATION OF SOLAR PANELS ON ROOF. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
S01228528-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offSUNCO CAPITAL LLC05/27/2025
2 projects · most recent 06/10/2025
FiledStatusContractorScope
06/10/2025CompleteBERGER QUALITY ELEC'L CON1 meters
05/18/2025CompleteBERGER QUALITY ELEC'L CON—
▾Special Inspection Requirements (DOB NOW) — 10
DateRequirementInspectorRole
06/26/2025Air barrier - visual inspectionNARESH MAHANGUenergy_progress
06/26/2025Structural Stability – Alterations of existing buildingsNARESH MAHANGUspecial
06/26/2025Fire-Resistant Penetrations and JointsNARESH MAHANGUspecial
06/26/2025FinalNARESH MAHANGUprogress
06/26/2025Energy Code Compliance InspectionsNARESH MAHANGUprogress
06/23/2025Fire-Resistant Penetrations and JointsNARESH MAHANGUspecial
06/23/2025Structural Stability – Alterations of existing buildingsNARESH MAHANGUspecial
06/23/2025Energy Code Compliance InspectionsNARESH MAHANGUprogress
06/23/2025FinalNARESH MAHANGUprogress
06/23/2025Air barrier - visual inspectionNARESH MAHANGUenergy_progress
▾Documents — 13 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/19/2026S01228528-I1Request digital key ↗
08/19/2026S01228528-P1Request digital key ↗
▸Seals & Professional Certifications8
▸DOB NOWProgress Inspector Seal & Signature4
09/21/2026S01228528-P1Open ↗
09/21/2026S01228528-P1Open ↗
08/25/2026S01228528-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/19/2026S01228528-I1Open ↗
08/13/2026S01228528-P1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
09/21/2026S01228528-P1Open ↗
08/25/2026S01228528-I1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/19/2026S01228528-I1Open ↗
08/13/2026S01228528-P1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026S01228528-I1Open ↗