Whole building & multi-floor projectsRudd Realty Mgmt CORP.3 filings
Filing for facade, masonry and exterior repairs as per drawings. No change in use, egress or occupancy is involved under this application.
On file for this project
5 documents
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
5 documents
RoofApplication Filed for Interior Renovation of Apartment 7C atUnder Construction10p · 3 filings · 20 docs
ArchitectureEquipmentGeneralMechanicalStructural
Issued Permit Scope
General Construction · Mechanical Systems · Supported Scaffold
PLUMBING WORK FILED IN CONJUNCTION WITH DOB NOW GC. NO CHANGE TO USE, OCCUPANCY OR EGRESS.
On file for this project
23 documents · 4 drawing sheets
Facade Restoration. Inspection. New Outriggers. Renewal of 23-1401
On file for this project
3 documents · 1 drawing sheet
FACADE AND EXTERIOR REPAIRS AS PER DRAWINGS. NO CHANGE IN USE, EGRESS OR OCCUPANCY IS REQUIRED UNDER THIS APPLICATION.
On file for this project
10 documents · 5 drawing sheets
Floor 9Application Filed for Interior Renovation of Apartment 7C atUnder Construction2 filings · 20 docs
ArchitectureEquipmentGeneralMechanicalStructural
Issued Permit Scope
General Construction · Mechanical Systems · Supported Scaffold
PLUMBING WORK FILED IN CONJUNCTION WITH DOB NOW GC. NO CHANGE TO USE, OCCUPANCY OR EGRESS.
On file for this project
23 documents
FACADE AND EXTERIOR REPAIRS AS PER DRAWINGS. NO CHANGE IN USE, EGRESS OR OCCUPANCY IS REQUIRED UNDER THIS APPLICATION.
On file for this project
10 documents
Floor 8Application Filed for Interior Renovation of Apartment 7C atUnder Construction2 filings · 20 docs
ArchitectureEquipmentGeneralMechanicalStructural
Issued Permit Scope
General Construction · Mechanical Systems · Supported Scaffold
PLUMBING WORK FILED IN CONJUNCTION WITH DOB NOW GC. NO CHANGE TO USE, OCCUPANCY OR EGRESS.
On file for this project
23 documents
FACADE AND EXTERIOR REPAIRS AS PER DRAWINGS. NO CHANGE IN USE, EGRESS OR OCCUPANCY IS REQUIRED UNDER THIS APPLICATION.
On file for this project
10 documents
Floor 7Unit 7C, Unit 6BF, Unit 7ARUnder Construction6p · 5 filings · 20 docs
ArchitectureDMEquipmentGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Supported Scaffold
PLUMBING WORK FILED IN CONJUNCTION WITH DOB NOW GC. NO CHANGE TO USE, OCCUPANCY OR EGRESS.
On file for this project
23 documents · 6 drawing sheets
Renovate existing kitchen and bedroom. Replace washer, dryer, cabinets, flooring, tile, oven. Move kitchen sink. New flooring and lighting.
On file for this project
18 documents
FACADE AND EXTERIOR REPAIRS AS PER DRAWINGS. NO CHANGE IN USE, EGRESS OR OCCUPANCY IS REQUIRED UNDER THIS APPLICATION.
On file for this project
10 documents
Latest 3 of 5 filings on this floor.
Floor 6Brownstone cleaning, repointing, and slate repairs1 filing · 10 docs
ArchitectureEquipmentGeneralStructural
Issued Permit Scope
General Construction · Supported Scaffold
FACADE AND EXTERIOR REPAIRS AS PER DRAWINGS. NO CHANGE IN USE, EGRESS OR OCCUPANCY IS REQUIRED UNDER THIS APPLICATION.
On file for this project
10 documents
Floor 5Unit 5AF2 filings · 20 docs
ArchitectureEquipmentGeneralPlumbingStructural
Issued Permit Scope
General Construction · Plumbing · Supported Scaffold
Replacement of existing kitchen cabinets & bathroom finishes. No changes to use, occupancy or egress.
On file for this project
34 documents
FACADE AND EXTERIOR REPAIRS AS PER DRAWINGS. NO CHANGE IN USE, EGRESS OR OCCUPANCY IS REQUIRED UNDER THIS APPLICATION.
On file for this project
10 documents
Floor 4Brownstone cleaning, repointing, and slate repairs1 filing · 10 docs
ArchitectureEquipmentGeneralStructural
Issued Permit Scope
General Construction · Supported Scaffold
FACADE AND EXTERIOR REPAIRS AS PER DRAWINGS. NO CHANGE IN USE, EGRESS OR OCCUPANCY IS REQUIRED UNDER THIS APPLICATION.
On file for this project
10 documents
Floor 3Unit 3BF2p · 3 filings · 16 docs
ArchitectureDMEquipmentGeneralPlumbingStructural
Issued Permit Scope
General Construction · Plumbing · Supported Scaffold
Plumbing fixture work for apartment renovation at 3rd floor unit 3BF. No change to use, egress or occupancy.
On file for this project
16 documents · 2 drawing sheets
FACADE AND EXTERIOR REPAIRS AS PER DRAWINGS. NO CHANGE IN USE, EGRESS OR OCCUPANCY IS REQUIRED UNDER THIS APPLICATION.
On file for this project
10 documents
PLUMBING WORK IN APARTMENT 3BR FILED IN CONJUNCTION WITH BIS CONSTRUCTION APPLICATION. NO CHANGE TO USE, OCCUPANCY, OR EGRESS.
On file for this project
5 documents
Floor 2
Floor 1Plumbing fixture work in existing apartment1p · 4 filings · 11 docs
ArchitectureEquipmentGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Supported Scaffold
Plumbing fixture work in existing Class A apartment at first floor unit number 1BR. No change to use, egress or occupancy.
On file for this project
11 documents
Plumbing work to accommodate apartment renovation at 1st floor unit. no change to use, egress or occupancy proposed under this application.
On file for this project
4 documents · 1 drawing sheet
Related mechanical work in conjunction with apartment renovation. Exhaust work, duct work, louvre work. New split AC system. No change to use, egress or occupancy filed under this application
On file for this project
12 documents
Latest 3 of 4 filings on this floor.
CellarApartment combination plumbing work1p · 1 filing · 4 docs
ArchitecturePlumbing
Issued Permit Scope
General Construction · Plumbing
Plumbing work to accommodate apartment renovation at 1st floor unit. no change to use, egress or occupancy proposed under this application.
On file for this project
4 documents · 1 drawing sheet
Site & exteriorRudd Realty Mgmt CORP.6 filings · 11 docs
ArchitectureEquipmentGeneralStructural
Issued Permit Scope
General Construction · Protection and Mechanical Methods · Sidewalk Shed · Supported Scaffold
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 8 drawing sheets
INSTALLATION OF TEMPORARY BETAMAX HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents · 3 drawing sheets
INSTALLATION OF TEMPORARY STORAGE OF MATERIALS AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents · 2 drawing sheets
Latest 3 of 6 filings on this floor.