| Firm | Filings | Most Recent |
|---|---|---|
| Avid Designs | 3 | 08/31/2022 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| HM Build and Uplift | General Contractor | 2 | 03/21/2026 |
| HM Build and Uplift | Scaffold | 2 | 03/21/2026 |
| DPH Plumbing & Heating | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Avid Designs | 453 | 2 | 03/23/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | DPH Plumbing & Heating | 08/23/2023 |
| DOB NOW | Construction Fence | Permit Issued | HM Build Uplift | 04/04/2023 |
| DOB NOW | Foundation | Permit Issued | HM Build Uplift | 04/03/2023 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/23/2022 | Permit Issued | DPH Plumbing & Heating | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/01/2023 | Permit Issued | High Beam Electric | General Wiring |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/22/2022 | Fire-Resistant Penetrations and Joints | Jeffrey Geary | special |
| 02/03/2022 | Fenestration air leakage | Jeffrey Geary | energy_progress |
| 02/03/2022 | Fenestration and door U-factor and product ratings | Jeffrey Geary | energy_progress |
| 02/03/2022 | Fenestration areas | Jeffrey Geary | energy_progress |
| 02/03/2022 | Air barrier - visual inspection | Jeffrey Geary | energy_progress |
| 02/03/2022 | Insulation placement and R values | Jeffrey Geary | energy_progress |
| 02/03/2022 | Interior lighting power | Jeffrey Geary | energy_progress |
| 01/13/2022 | Fire-Resistant Penetrations and Joints | Jeffrey Geary | special |
| 01/13/2022 | Structural Stability – Alterations of existing buildings | Jeffrey Geary | special |
| 01/13/2022 | Subgrade Inspections | Jeffrey Geary | special |
| 01/13/2022 | Final | Jeffrey Geary | progress |
| 01/13/2022 | Footing and Foundation | Jeffrey Geary | progress |
| 01/13/2022 | Concrete - Cast-In-Place | Jeffrey Geary | special |