| Owner | Filings | Most Recent |
|---|---|---|
| PROSPER PROPERTY GROUP | 77 | 09/30/2026 |
| SHAH GROUP ENTERPRISES IN | 11 | 04/09/2026 |
| TOPLINE NYC CONTRACTING | 3 | 04/09/2026 |
| KNOCKOUT CONSTRUCTION | 4 | 03/22/2026 |
| ELTIBER REALTY CORP | 8 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 02/27/2025 | $11.6M | — | ELTIBE REALTY CORP → WALKER STREET OWNER LLC | $778/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| EP ENGINEERING LLC | 8 | 08/24/2026 |
| BLACK SHEEP ENGINEERING GROUP | 12 | 08/05/2026 |
| WEXLER ASSOCIATES | 4 | 08/04/2025 |
| RIGID STRUCTURAL DESIGN, LLC | 2 | 06/13/2025 |
| TURETT COLLABORATIVE ARCHITECTS | 4 | 06/06/2025 |
| PAUL G. JONES, P.E. | 1 | 10/04/2023 |
| SYED ENGINEERING, P.C. | 1 | 01/11/2021 |
| LIGHT HOUSE | 1 | 01/22/2019 |
| ASHRAF CORP | 1 | 01/21/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| JM ZONING, LLC. | 17 | 03/21/2026 |
| Rigid Structural Design, LLC | 4 | 03/21/2026 |
| ADVANCED BUILDERS SERVICES | 3 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| COLGATE ENTERPRISE CORP | General Contractor | 17 | 09/30/2026 |
| FIRST STANDARD CONSTR INC | General Contractor | 16 | 09/15/2026 |
| TOPLINE NYC CONTRACTING | General Contractor | 13 | 04/09/2026 |
| ARMON MECHANICAL INC | Fire Protection | 6 | 09/30/2026 |
| CONSOLIDATED SCAFFOLDING | General Contractor | 2 | 07/08/2026 |
| ARMON MECHANICAL INC | Plumbing | 2 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| DELTA TESTING LABS | 687 | 18 | 08/24/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Standpipe | Permit Issued | ARMON MECHANICAL INC | 09/29/2026 |
| DOB NOW | Standpipe | Permit Issued | ARMON MECHANICAL INC | 09/29/2026 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | COLGATE ENTERPRISE CORP | 09/29/2026 |
| DOB NOW | General Construction | Permit Issued | FIRST STANDARD CONSTR INC | 09/14/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | COLGATE ENTERPRISE CORP | 09/14/2026 |
| DOB NOW | Structural | Permit Issued | FIRST STANDARD CONSTR INC | 09/14/2026 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | COLGATE ENTERPRISE CORP | 08/05/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | COLGATE ENTERPRISE CORP | 06/17/2026 |
| DOB NOW | General Construction | Permit Issued | FIRST STANDARD CONSTR INC | 05/27/2026 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | COLGATE ENTERPRISE CORP | 05/08/2026 |
| DOB NOW | Plumbing | Permit Issued | ARMON MECHANICAL INC | 05/06/2026 |
| DOB NOW | Sprinklers | Permit Issued | ARMON MECHANICAL INC | 04/21/2026 |
| DOB NOW | Construction Fence | Permit Issued | COLGATE ENTERPRISE CORP | 03/26/2026 |
| DOB NOW | Supported Scaffold | Permit Issued | COLGATE ENTERPRISE CORP | 03/25/2026 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | COLGATE ENTERPRISE CORP | 03/25/2026 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | COLGATE ENTERPRISE CORP | 03/25/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | COLGATE ENTERPRISE CORP | 03/25/2026 |
| DOB NOW | Structural | Permit Issued | FIRST STANDARD CONSTR INC | 03/12/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | FIRST STANDARD CONSTR INC | 03/06/2026 |
| DOB NOW | Support of Excavation | Signed-off | FIRST STANDARD CONSTR INC | 03/06/2026 |
| DOB NOW | Foundation | Signed-off | FIRST STANDARD CONSTR INC | 03/05/2026 |
| DOB NOW | General Construction | Permit Issued | FIRST STANDARD CONSTR INC | 02/02/2026 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | COLGATE ENTERPRISE CORP | 10/08/2025 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | COLGATE ENTERPRISE CORP | 05/27/2025 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | COLGATE ENTERPRISE CORP | 04/30/2025 |
| DOB NOW | Supported Scaffold | Permit Issued | COLGATE ENTERPRISE CORP | 04/29/2025 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | COLGATE ENTERPRISE CORP | 04/29/2025 |
| DOB NOW | Construction Fence | Permit Issued | COLGATE ENTERPRISE CORP | 04/28/2025 |
| DOB NOW | Sidewalk Shed | Permit Issued | COLGATE ENTERPRISE CORP | 04/25/2025 |
| DOB NOW | Standpipe | Permit Issued | ARMON MECHANICAL INC | 04/18/2025 |
| DOB NOW | Sprinklers | Permit Issued | ARMON MECHANICAL INC | 04/18/2025 |
| DOB NOW | Standpipe | Permit Issued | ARMON MECHANICAL INC | 04/18/2025 |
| DOB NOW | Plumbing | Permit Issued | ARMON MECHANICAL INC | 04/18/2025 |
| DOB NOW | General Construction | Permit Issued | FIRST STANDARD CONSTR INC | 04/01/2025 |
| DOB NOW | Foundation | Permit Issued | FIRST STANDARD CONSTR INC | 03/31/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | FIRST STANDARD CONSTR INC | 03/31/2025 |
| DOB NOW | Foundation | Signed-off | FIRST STANDARD CONSTR INC | 03/28/2025 |
| DOB NOW | Structural | Permit Issued | FIRST STANDARD CONSTR INC | 03/28/2025 |
| DOB NOW | Support of Excavation | Signed-off | FIRST STANDARD CONSTR INC | 03/28/2025 |
| DOB NOW | Supported Scaffold | Signed-off | CONSOLIDATED SCAFFOLDING | 10/05/2023 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 08/24/2026 | Permit Issued | FIRST STANDARD CONSTR INC | Heating and Air Conditioning Systems | Heat / Cool Daikin FXSQ36TBVJU 36,000 BTU · Vrf Indoor ×20 REYQ96AATJA 96,000 BTU · Vrf Outdoor ×22 REYQ120AATJA 120,000 BTU · Vrf Outdoor ×2 REYQ72AATJA 72,000 BTU · Vrf Outdoor ×2 RXTQ60TBVJUB 60,000 BTU · Vrf Outdoor ×2 RZR24TBVJUB 24,000 BTU · Condensing Unit ×2 RXTQ60TAVJUA 57,500 BTU · Vrf Outdoor ×2 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/24/2026 | Permit Issued | ARMON MECHANICAL INC | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/18/2025 | Permit Issued | NASH ELECTRIC SERVICES IN | — |
| 07/02/2025 | Permit Issued | TF ELECTRICAL CORP | General Wiring |
| 06/16/2025 | Permit Issued | FSM ELECTRICAL CORPORATIO | General Wiring |
| 05/07/2025 | Permit Issued | FSM ELECTRICAL CORPORATIO | — |
| 10/10/2023 | Complete | SOLAS ELECTRICAL CORP | — |
| 01/20/2019 | Complete | RICHARD NEU | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/24/2026 | Permit Issued | ARMON MECHANICAL INC | Steel, Concrete, Masonry |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/04/2025 | Permit Issued | COLGATE ENTERPRISE CORP | Sidewalk Shed |
| 10/07/2025 | Permit Issued | COLGATE ENTERPRISE CORP | Scaffold |
| 08/25/2025 | Permit Issued | COLGATE ENTERPRISE CORP | Fence |
| 01/22/2019 | Permit Issued | TOPLINE NYC CONTRACTING | Scaffold |
| 01/21/2019 | Permit Issued | TOPLINE NYC CONTRACTING | Sidewalk Shed |
| Date | Type | Result | Report |
|---|---|---|---|
| 09/02/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 09/02/2026 | Certified StandPipe-SD-Piping-Hydrostatic Test | Certified | View ↗ |
| 07/29/2026 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 07/29/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 06/02/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/29/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 11/03/2025 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 10/17/2025 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 10/17/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 09/09/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/22/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 07/25/2025 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 07/04/2025 | Certified StandPipe - SD - Alarm Sys 64/09 - Finish | Certified | View ↗ |
| 07/04/2025 | Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet) | Certified | View ↗ |
| 06/18/2025 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 05/22/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 05/19/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 04/25/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/25/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 10/06/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/24/2026 | Metering | RICHARD GREENWALD | energy_progress |
| 08/24/2026 | Maintenance information | RICHARD GREENWALD | energy_progress |
| 08/24/2026 | Duct leakage testing, insulation and design | RICHARD GREENWALD | energy_progress |
| 08/24/2026 | Electrical motors and elevators | RICHARD GREENWALD | energy_progress |
| 08/24/2026 | Shutoff dampers | RICHARD GREENWALD | energy_progress |
| 08/24/2026 | HVAC-R and service water heating equipment | RICHARD GREENWALD | energy_progress |
| 08/24/2026 | HVAC-R and service water heating system controls | RICHARD GREENWALD | energy_progress |
| 08/24/2026 | Exhaust and Vent Systems in Plenums and Ducts | RICHARD GREENWALD | special |
| 08/24/2026 | Fire-Resistant Penetrations and Joints | RICHARD GREENWALD | special |
| 08/24/2026 | Mechanical Systems | RICHARD GREENWALD | special |
| 08/24/2026 | Post-installed Anchors | RICHARD GREENWALD | special |
| 08/24/2026 | Energy Code Compliance Inspections | RICHARD GREENWALD | progress |
| 08/24/2026 | Final | RICHARD GREENWALD | progress |
| 08/24/2026 | HVAC-R and service water piping design and insulation | RICHARD GREENWALD | energy_progress |
| 08/24/2026 | Lighting controls | RICHARD GREENWALD | energy_progress |
| 08/24/2026 | Exterior lighting power | RICHARD GREENWALD | energy_progress |
| 08/24/2026 | Lighting in dwelling units | RICHARD GREENWALD | energy_progress |
| 08/24/2026 | Interior lighting power | RICHARD GREENWALD | energy_progress |
| 08/18/2026 | Final | RICHARD GREENWALD | progress |
| 08/18/2026 | Energy Code Compliance Inspections | RICHARD GREENWALD | progress |
| 08/18/2026 | Lighting controls | RICHARD GREENWALD | energy_progress |
| 08/18/2026 | HVAC-R and service water piping design and insulation | RICHARD GREENWALD | energy_progress |
| 08/18/2026 | Metering | RICHARD GREENWALD | energy_progress |
| 08/18/2026 | Lighting in dwelling units | RICHARD GREENWALD | energy_progress |
| 08/18/2026 | Interior lighting power | RICHARD GREENWALD | energy_progress |