💬 Discuss this project
2022Year Built
2Stories
B2Building Class
R3AZoning
4,107 sfGross Floor Area
2Units
Two family frame · 4,322 sf lot · 0.95 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Floor 210p · 3 filings · 20 docs
Floor 119p · 3 filings · 20 docs
Basement9p · 3 filings · 20 docs
Sub-Basement1 filing · 3 docs
Site & exterior6p · 2 filings · 20 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Joseph M. Morace, A.I.A., Architect609/29/2023
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Patricia L Gass1203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Steadfast ConstructionGeneral Contractor903/21/2026
Flow-Right Plumbing & Heatingspecialty_contractor307/08/2026
Steadfast Constructionspecialty_contractor107/08/2026
Quality PlumbingPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
SRA Planning & Expediting5677309/29/2023
Building Lifecycle
10/11/2023
Permit expired, never signed off — Structural
The city's record still shows this permit as issued, with no sign-off on its filing
S00639838-I1-GC-CX
10/10/2023
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
10/02/2023
Special inspection requirement — Concrete - Cast-In-Place
WILLIAM MONTAGUE
10/02/2023
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
WILLIAM MONTAGUE
10/02/2023
Special inspection requirement — Structural Steel - High Strength Bolting
WILLIAM MONTAGUE
64 history events on file for this building. Sign in free to see the full history. Sign in · Create account
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWCurb CutSigned-offSteadfast Construction06/01/2023
DOB NOWCurb CutSigned-offSteadfast Construction06/01/2023
DOB NOWStructuralPermit IssuedSteadfast Construction10/11/2022
DOB NOWPlumbingSigned-offQuality Plumbing08/31/2022
DOB NOWPlumbingSigned-offFlow-Right Plumbing & Heating08/10/2022
DOB NOWSprinklersSigned-offFlow-Right Fire Supply08/10/2022
DOB NOWPlumbingSigned-offFlow-Right Plumbing & Heating08/08/2022
DOB NOWMechanical SystemsPermit IssuedSteadfast Construction05/23/2022
1 project · most recent 09/29/2023
Gas Storm Water/Sanitary
FiledStatusContractorScope
09/29/2023Signed-offFlow-Right Plumbing & HeatingGas, Storm, Water/Sanitary
1 project · most recent 09/08/2022
General Wiring
FiledStatusContractorScope
09/08/2022CompleteJ.P.E. Electrical ContractorsGeneral Wiring
1 project · most recent 09/29/2023
Concrete
FiledStatusContractorScope
09/29/2023Signed-offSteadfast ConstructionConcrete
1 project · most recent 09/29/2023
Earthwork
FiledStatusContractorScope
09/29/2023Signed-offSteadfast ConstructionEarthwork
▾Field Inspections (DOB CAP) — 12
DateTypeResultReport
10/10/2023Pass-Final CND-Occupancy InspectionPassView ↗
07/12/2023Pass-Final CND-Occupancy InspectionPassView ↗
07/12/2023Pass-Final Curb Cut Non-Directive 14PassView ↗
06/01/2023Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
06/01/2023Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
05/25/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
05/22/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
05/22/2023Pass-Final SP - Up to 3 Requested FloorsPassView ↗
12/21/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
09/14/2022Certified Storm Drainage-ST-Fixtures-FinishCertifiedView ↗
09/13/2022Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
09/13/2022Pass-Final PL - UndergroundPassView ↗
▾Special Inspection Requirements (DOB NOW) — 62
DateRequirementInspectorRole
10/02/2023Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationWILLIAM MONTAGUEspecial
10/02/2023Concrete - Cast-In-PlaceWILLIAM MONTAGUEspecial
10/02/2023Subsurface Investigations (Borings/Test Pits)WILLIAM MONTAGUEspecial
10/02/2023Structural Steel - High Strength BoltingWILLIAM MONTAGUEspecial
10/02/2023Subgrade InspectionsWILLIAM MONTAGUEspecial
10/02/2023Exterior Insulation and Finish Systems (EIFS)WILLIAM MONTAGUEspecial
10/02/2023Fire-Resistant Penetrations and JointsWILLIAM MONTAGUEspecial
10/02/2023Mechanical SystemsWILLIAM MONTAGUEspecial
10/02/2023FinalWILLIAM MONTAGUEprogress
10/02/2023Structural Wood FrameWILLIAM MONTAGUEprogress
10/02/2023Footing and FoundationWILLIAM MONTAGUEprogress
10/02/2023Energy Code Compliance InspectionsWILLIAM MONTAGUEprogress
10/02/2023Fire-Resistance Rated ConstructionWILLIAM MONTAGUEprogress
10/02/2023Air barrier — testing WILLIAM MONTAGUEenergy_progress
10/02/2023Fenestration areasWILLIAM MONTAGUEenergy_progress
10/02/2023HVAC-R and service water piping design and insulationWILLIAM MONTAGUEenergy_progress
10/02/2023Protection of exposed foundation insulationWILLIAM MONTAGUEenergy_progress
10/02/2023Interior lighting powerWILLIAM MONTAGUEenergy_progress
10/02/2023HVAC-R and service water heating equipmentWILLIAM MONTAGUEenergy_progress
10/02/2023Air barrier - visual inspectionWILLIAM MONTAGUEenergy_progress
10/02/2023Electric vehicle service equipment requirementsWILLIAM MONTAGUEenergy_progress
10/02/2023Ventilation and air distribution systemWILLIAM MONTAGUEenergy_progress
10/02/2023HVAC-R and service water heating system controlsWILLIAM MONTAGUEenergy_progress
10/02/2023Permanent certificateWILLIAM MONTAGUEenergy_progress
10/02/2023Fenestration air leakageWILLIAM MONTAGUEenergy_progress
Latest 25 of 62.