| Owner | Filings | Most Recent |
|---|---|---|
| WSFSSH | 32 | 09/13/2026 |
| SKYLINE SCAFFOLDING GROUP | 13 | 09/13/2026 |
| BRANDON HOUSING DEVELOPMENT FUND | 5 | 03/22/2026 |
| THREE ARTS CLUB HOUSING DEVELOPM | 3 | 03/21/2026 |
| STEEL SYSTEMS | 2 | 03/21/2026 |
| THREE ARTS CLUB HOUSING | 2 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 05/09/2017 | $42.0M | — | — → — | $815/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| PAUL PERDEK, PROF. ENG. PLLC | 1 | 08/14/2026 |
| THE H ARCHITECTS LLC | 3 | 08/03/2026 |
| SONI ENGINEERING CONSULTING | 1 | 06/08/2026 |
| RIGID STRUCTURAL DESIGN, LLC | 9 | 06/04/2026 |
| CURTIS + GINSBERG ARCHITECTS LLP | 8 | 12/02/2025 |
| OLD STRUCTURES ENGINEERING | 3 | 07/18/2025 |
| SRL ASSOCIATES | 1 | 01/31/2022 |
| KZ ENGINEERING, P.C | 1 | 05/31/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| Rigid Structural Design, LLC | 6 | 03/21/2026 |
| JM ZONING, LLC. | 20 | 03/21/2026 |
| MUNICIPAL BUILDING CONSULTANTS | 1 | 03/21/2026 |
| SYNERGY BUILDING CONSULTANTS | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| MEGA CONTRACTING GP LLC | General Contractor | 8 | 08/21/2026 |
| RCD RESTORATIONS INC | General Contractor | 8 | 03/21/2026 |
| SKYLINE SCAFFOLDING GROUP | General Contractor | 5 | 07/08/2026 |
| ASPRO PLUMBING INC | Fire Protection | 4 | 07/29/2026 |
| ASPRO PLUMBING INC | Plumbing | 2 | 07/02/2026 |
| GOOD-WILL MECHANICAL CORP. | General Contractor | 2 | 07/02/2026 |
| POLTECH INC | General Contractor | 1 | 08/21/2026 |
| CS BRIDGE CORP | General Contractor | 1 | 07/08/2026 |
| ARSENAL SCAFFOLD INC | General Contractor | 1 | 07/08/2026 |
| DOUMAS ELECTRIC INC. | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SONI ENGINEERING CONSULTI | 9819 | 1 | 06/08/2026 |
| METRIC CONSULTING AND INS | 1803 | 9 | 12/02/2025 |
| CHEN ENGINEERING SERVICES | 1826 | 1 | 12/01/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Structural | Permit Issued | MEGA CONTRACTING GP LLC | 08/20/2026 |
| DOB NOW | Supported Scaffold | Permit Issued | POLTECH INC | 08/20/2026 |
| DOB NOW | Construction Fence | Permit Issued | MEGA CONTRACTING GP LLC | 08/20/2026 |
| DOB NOW | Suspended Scaffold | Permit Issued | IDEAL ROOFING & SHEET | 08/17/2026 |
| DOB NOW | Standpipe | Permit Issued | ASPRO PLUMBING INC | 07/28/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | GOOD-WILL MECHANICAL CORP. | 06/30/2026 |
| DOB NOW | Plumbing | Permit Issued | ASPRO PLUMBING INC | 06/30/2026 |
| DOB NOW | General Construction | Permit Issued | MEGA CONTRACTING GP LLC | 06/30/2026 |
| DOB NOW | Suspended Scaffold | Permit Issued | IDEAL ROOFING & SHEET | 06/11/2026 |
| DOB NOW | Supported Scaffold | Permit Issued | SKYLINE SCAFFOLDING GROUP | 05/14/2026 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | SKYLINE SCAFFOLDING GROUP | 05/14/2026 |
| DOB NOW | Standpipe | Permit Issued | ASPRO PLUMBING INC | 12/08/2025 |
| DOB NOW | Sprinklers | Permit Issued | ASPRO PLUMBING INC | 12/05/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | GOODWILL MECHANICAL | 11/21/2025 |
| DOB NOW | Supported Scaffold | Permit Issued | SKYLINE SCAFFOLDING GROUP | 11/06/2025 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | SKYLINE SCAFFOLDING GROUP | 11/06/2025 |
| DOB NOW | Sidewalk Shed | Permit Issued | SKYLINE SCAFFOLDING GROUP | 11/06/2025 |
| DOB NOW | General Construction | Permit Issued | MEGA CONTRACTING GP LLC | 10/07/2025 |
| DOB NOW | Plumbing | Permit Issued | ASPRO PLUMBING INC | 09/30/2025 |
| DOB NOW | Structural | Permit Issued | MEGA CONTRACTING GP LLC | 08/28/2025 |
| DOB NOW | Standpipe | Permit Issued | ASPRO PLUMBING INC | 08/26/2025 |
| DOB NOW | Construction Fence | Permit Issued | MEGA CONTRACTING GP LLC | 07/17/2025 |
| DOB NOW | Structural | Signed-off | RCD RESTORATIONS INC | 03/14/2022 |
| DOB NOW | General Construction | Signed-off | RCD RESTORATIONS INC | 03/14/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | ARSENAL SCAFFOLD INC | 01/31/2022 |
| DOB NOW | Structural | Signed-off | RCD RESTORATIONS INC | 01/31/2022 |
| DOB NOW | Structural | Signed-off | RCD RESTORATIONS INC | 01/28/2022 |
| DOB NOW | Supported Scaffold | Signed-off | CS BRIDGE CORP | 05/31/2018 |
| BIS | PL | ISSUED | CEGF & G PLUMBING CORP | 11/20/2020 |
| BIS | OT | ISSUED | NEW YORK HEATING CORP | 12/21/2019 |
| BIS | PL | ISSUED | CEGF & G PLUMBING CORP | 11/29/2019 |
| BIS | FS | ISSUED | NEW YORK HEATING CORP | 10/14/2019 |
| BIS | OT | ISSUED | NEW YORK HEATING CORP | 08/29/2019 |
| BIS | PL | ISSUED | CEGF & G PLUMBING CORP | 12/08/2018 |
| BIS | OT | ISSUED | FG-PH CORP | 11/17/2018 |
| BIS | FP | ISSUED | ALLIED FIRE CONTROL SVCS | 05/01/2018 |
| BIS | OT | ISSUED | FG-PH CORP | 02/07/2018 |
| BIS | PL | ISSUED | CEGF & G PLUMBING CORP | 12/18/2017 |
| BIS | OT | ISSUED | FG-PH CORP | 12/18/2017 |
| BIS | OT | ISSUED | C.C.C. RENOVATION INC | 09/05/2017 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 12/02/2025 | Permit Issued | MEGA CONTRACTING GP LLC | Heating and Air Conditioning Systems | Heat / Cool Mitsubishi Electric PUY-A18NKA7 18,000 BTU · Vrf Outdoor ×9 PUHY-EP96TNU-A1 96,000 BTU · Vrf Outdoor ×3 PURY-EP192TSNU-A1 192,000 BTU · Vrf Outdoor ×3 SUZ-KA30NAHZ 30,000 BTU · Vrf Outdoor ×3 Ephoca APP-10N-3H2-2 8,900 BTU · Heat Pump Outdoor ×3 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/02/2025 | Permit Issued | ASPRO PLUMBING INC | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/02/2025 | Permit Issued | ASPRO PLUMBING INC | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/25/2026 | Permit Issued | TF ELECTRICAL CORP | General Wiring |
| 01/20/2026 | Permit Issued | MAX ELECTRIC CO., INC | General Wiring |
| 09/03/2025 | Permit Issued | TOP SHELF ELECTRIC CORP | — |
| 12/16/2021 | Complete | NASH ELECTRIC SERVICES IN | — |
| 08/07/2019 | Complete | DOUMAS ELECTRIC INC. | General Wiring |
| 08/05/2019 | Complete | DOUMAS ELECTRIC INC. | General Wiring |
| 05/22/2019 | Permit Issued | DOUMAS ELECTRIC INC. | General Wiring |
| 08/22/2018 | Permit Issued | DOUMAS ELECTRIC INC. | — |
| 01/20/2018 | Permit Issued | T & T ELECTRICAL CORP. | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/02/2025 | Permit Issued | MEGA CONTRACTING GP LLC | Steel, Concrete, Masonry |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/14/2026 | Permit Issued | POLTECH INC | Scaffold |
| 08/03/2026 | Permit Issued | MEGA CONTRACTING GP LLC | Fence |
| 06/04/2026 | Permit Issued | SKYLINE SCAFFOLDING GROUP | Scaffold |
| 06/04/2026 | Permit Issued | SKYLINE SCAFFOLDING GROUP | Sidewalk Shed |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/08/2026 | Permit Issued | IDEAL ROOFING & SHEET | Suspended Scaffold (SC) |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/19/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 08/07/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 08/05/2026 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 08/05/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/03/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 08/03/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 04/24/2026 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 04/24/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 04/13/2026 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 04/13/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 04/02/2026 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 04/02/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/09/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 02/27/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 02/10/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 02/10/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 02/03/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 01/05/2026 | Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet) | Certified | View ↗ |
| 11/25/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 11/25/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 10/08/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 10/01/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/01/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/28/2026 | Post-installed Anchors | nayan soni | special |
| 05/28/2026 | Alternative Materials - OTCR Buildings Bulletin Number | nayan soni | special |
| 09/12/2025 | Exterior Insulation and Finish Systems (EIFS) | SAMI HAJJAR P.E | special |
| 09/12/2025 | Masonry | SAMI HAJJAR P.E | special |
| 09/12/2025 | Fire-Resistant Penetrations and Joints | SAMI HAJJAR P.E | special |
| 09/12/2025 | Structural Stability – Alterations of existing buildings | SAMI HAJJAR P.E | special |
| 09/12/2025 | Post-installed Anchors | SAMI HAJJAR P.E | special |
| 09/12/2025 | Fire-Resistance Rated Construction | SAMI HAJJAR P.E | progress |
| 08/06/2025 | Sprinkler Systems | SAMI HAJJAR P.E | special |
| 08/06/2025 | Standpipe Systems | SAMI HAJJAR P.E | special |
| 07/28/2025 | Structural Stability – Alterations of existing buildings | SAMI HAJJAR P.E | special |
| 07/28/2025 | Mechanical Systems | SAMI HAJJAR P.E | special |
| 07/28/2025 | Final | SAMI HAJJAR P.E | progress |
| 07/28/2025 | Structural Steel - Details | SAMI HAJJAR P.E | special |
| 07/28/2025 | Masonry | SAMI HAJJAR P.E | special |
| 07/28/2025 | Structural Steel - Welding | SAMI HAJJAR P.E | special |
| 07/28/2025 | Sprayed fire-resistant materials | SAMI HAJJAR P.E | special |
| 07/28/2025 | Structural Cold-Formed Steel | SAMI HAJJAR P.E | special |
| 07/28/2025 | Subgrade Inspections | SAMI HAJJAR P.E | special |
| 07/28/2025 | Post-installed Anchors | SAMI HAJJAR P.E | special |
| 07/28/2025 | Structural Steel - High Strength Bolting | SAMI HAJJAR P.E | special |
| 07/28/2025 | Structural Stability – Alterations of existing buildings | SAMI HAJJAR P.E | special |
| 07/28/2025 | Subsurface Conditions – Fill Placement & In-Place Density | SAMI HAJJAR P.E | special |
| 07/28/2025 | Concrete - Cast-In-Place | SAMI HAJJAR P.E | special |
| 07/28/2025 | Final | SAMI HAJJAR P.E | progress |