STATEN ISLAND · Mariner's Harbor-Arlington-Graniteville · BIN 5028638
💬 Discuss this project
—Year Built
—Stories
—Building Class
—Zoning
—Gross Floor Area
—Units
3 Open Violations ▸FDNY Report ↗
Flood zone X
Locations of Work
ArchitectureElectrical
Permit Issued — active, not yet Signed-off
RoofUnder Construction1p · 1 filing · 6 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
GREEN RIVER ENVIRONMENTAL ENGINEERI112/31/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
NY State Solar LLC203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
NYSS LLCGeneral Contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
GREEN RIVER ENVIRONMENTAL7841112/31/2025
Building Lifecycle
All (14)Filed (1)Permit Issued (1)Violation (7)Special Inspection (5)
01/05/2026
Permit issued — Solar
S01341193-I1-SL
12/31/2025
Filed — Alteration
INSTALLATION OF PHOTOVOLTAIC SOLAR ARRAY ON EXISTING ROOF SYSTEM AS PER PLANS.
S01341193-I1
12/31/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
ROBERT MASONE
12/31/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
ROBERT MASONE
12/31/2025
Special inspection requirement — Energy Code Compliance Inspections
ROBERT MASONE
12/31/2025
Special inspection requirement — Final
ROBERT MASONE
12/31/2025
Special inspection requirement — Air barrier - visual inspection
ROBERT MASONE
10/01/2025
Violation issued (ECB, open)
Construction
10/01/2025
Violation issued (ECB, open)
Construction
10/01/2025
Violation issued (ECB, open)
Construction
04/25/2012
Violation issued (FDNY_NOV, closed)
04/25/2012
Violation issued (FDNY_NOV, closed)
01/25/2001
Violation issued (FDNY_NOV, closed)
04/27/2000
Violation issued (FDNY_NOV, closed)
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarPermit IssuedNYSS LLC01/05/2026
BISFPISSUEDIDEAL FIRE CONTROL INC07/27/2007
1 project · most recent 12/31/2025
FiledStatusContractorScope
12/31/2025Permit IssuedNY SOLAR ELECTRICAL LLC—
1 project · most recent 12/31/2025
FiledStatusContractorScope
12/31/2025Permit IssuedNYSS LLC46 panels, 20.48 kw, 1,983 roof_area_sqft
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
12/31/2025Fire-Resistant Penetrations and JointsROBERT MASONEspecial
12/31/2025Structural Stability – Alterations of existing buildingsROBERT MASONEspecial
12/31/2025Energy Code Compliance InspectionsROBERT MASONEprogress
12/31/2025FinalROBERT MASONEprogress
12/31/2025Air barrier - visual inspectionROBERT MASONEenergy_progress
▾Documents — 6 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/17/2026S01341193-I1Request digital key ↗
▸Seals & Professional Certifications4
▸DOB NOWProgress Inspector Seal & Signature2
08/24/2026S01341193-I1Open ↗
08/24/2026S01341193-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/13/2026S01341193-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/24/2026S01341193-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026S01341193-I1Open ↗