← Back
Two family converted from one family
3405 OLINVILLE AVENUE
BRONX ·
Williamsbridge-Olinville
· BIN 2056945
💬 Discuss this project
1925
Year Built
2.5
Stories
B3
Building Class
R5A
Zoning
1,352 sf
Gross Floor Area
2
Units
0 Open Violations
FDNY Report ↗
Two family converted from one family · 3,308 sf lot · 0.41 FAR built · Flood zone X
Floor Stack
0
People & Firms
1
Timeline
1
Permits & Filings
1
Scope of Work
1
Inspections
0
Documents
23
Locations of Work
No floor-level scope or drawing coverage on file for this building.
Contractors
1
▾
Contractors (License-Anchored)
Firm
Trade
Roles
Most Recent
JEFFREY MARINELLO
Electrical
1
03/21/2026
Building Lifecycle
All (1)
Violation (1)
03/28/2012
Violation issued (ECB, closed)
Unknown
Permit / Filing Register
Source
Work Type
Status
Applicant
Issued
BIS
OT
ISSUED
PRO CUSTOM SOLAR LLC
08/29/2018
Electrical
1
1 project · most recent 10/24/2018
Filed
Status
Contractor
Scope
10/24/2018
Complete
ISLAND ELECTRIC CORP
—
Nothing on file for this building.
▾
Documents — 23 on file (BIS + DOB NOW)
▸
Applications & Permits
3
▸
BIS
PLAN / WORK APPROVAL APPLICATION
2
06/12/2019
240234493
Open ↗
08/27/2018
240234493
Open ↗
▸
BIS
WORK PERMIT APPLICATION
1
08/27/2018
240234493
Open ↗
▸
Seals & Professional Certifications
3
▸
BIS
REQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION
1
08/27/2018
240234493
Open ↗
▸
BIS
PROFESSIONAL CERTIFICATION STATEMENT
1
08/27/2018
240234493
Open ↗
▸
BIS
TECHNICAL REPORT STATEMENT OF RESPONSIBILITY
1
08/27/2018
240234493
Open ↗
▸
Safety & Tenant Protection
1
▸
BIS
TENANT PROTECTION PLAN AND NOTES
1
08/27/2018
240234493
Open ↗
▸
Environmental & Asbestos
1
▸
BIS
ASBESTOS: CERTIFICATION (DEP ACP5)
1
08/27/2018
240234493
Open ↗
▸
Energy Compliance
6
▸
BIS
TECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY
2
11/01/2019
240234493
Open ↗
08/27/2018
240234493
Open ↗
▸
BIS
AS-BUILT ENERGY ANALYSIS
1
11/01/2019
240234493
Open ↗
▸
BIS
PTA4: SOLAR TAX ABATEMENT APPLICATION (PRELIMINARY)
1
08/27/2018
240234493
Open ↗
▸
BIS
PTA4: SOLAR TAX ABATEMENT APPLICATION (FINAL)
1
05/12/2020
240234493
Open ↗
▸
BIS
TECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS
1
08/27/2018
240234493
Open ↗
▸
Inspections & Test Reports
3
▸
BIS
TECHNICAL REPORT: RESPONSIBILITY
3
05/12/2020
240234493
Open ↗
11/01/2019
240234493
Open ↗
08/27/2018
240234493
Open ↗
▸
Approvals, Objections & Sign-offs
2
▸
BIS
Utility Company PV System Interconnection Acknowledgement Letter
1
11/01/2019
240234493
Open ↗
▸
BIS
CERTIFICATE OF OCCUPANCY/LOC: REQUEST
1
11/01/2019
240234493
Open ↗
▸
Cost, Insurance & Ownership
2
▸
BIS
COST AFFIDAVIT
2
05/12/2020
240234493
Open ↗
08/27/2018
240234493
Open ↗
▸
Filing & Intake Forms
2
▸
BIS
ADDITIONAL INFORMATION
1
06/12/2019
240234493
Open ↗
▸
BIS
EFILING JOB APPLICATION COVER SHEET
1
08/27/2018
240234493
Open ↗