| Owner | Filings | Most Recent |
|---|---|---|
| JAMAICA EX-POLICE ASSOCIATION | 3 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| STUDIO NYANDAK ARCHITECTURE AND ENG | 4 | 04/15/2026 |
| AHT ENGINEERING PLLC | 1 | 05/15/2025 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| HP SERVICES INC | Plumbing | 3 | 07/08/2026 |
| ALLAN TANG | Electrical | 1 | 03/21/2026 |
| VIKING MECHANICAL INC | General Contractor | 1 | 04/09/2026 |
| WINSON CONSTRUCTION INC | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| STUDIO NYANDAK ARCHITECTU | 8378 | 4 | 04/15/2026 |
| AHT ENGINEERING PLLC | 8836 | 1 | 05/15/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | HP SERVICES INC | 03/23/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | VIKING MECHANICAL INC | 09/19/2025 |
| DOB NOW | Plumbing | Permit Issued | HP SERVICES INC | 03/04/2025 |
| DOB NOW | General Construction | Permit Issued | WINSON CONSTRUCTION INC | 01/16/2025 |
| BIS | PL | ISSUED | ALESSANDRO PLUMBING, INC | 01/22/2019 |
| BIS | PL | ISSUED | ALESSANDRO PLUMBING, INC | 01/22/2019 |
| BIS | FP | ISSUED | MASTER FIRE SYSTEMS, INC | 08/03/2018 |
| BIS | MH | ISSUED | DESIGN CONCEPT TECH INC | 07/31/2018 |
| BIS | PL | ISSUED | ROY B PLUMBING & HEATING | 03/22/2018 |
| BIS | OT | ISSUED | ABSOLUTE CONTRACTING INC | 02/27/2018 |
| BIS | PL | ISSUED | CAPE PLUMBING INC | 08/29/2014 |
| BIS | PL | ISSUED | CAPE PLUMBING INC | 05/21/2013 |
| BIS | PL | ISSUED | MCMILLAN PLBG & HTG.INC | 04/13/2011 |
| BIS | — | ISSUED | W. DESIGNE INC | 02/18/2011 |
| BIS | PL | ISSUED | L.L.G. PLBG & HTG INC | 09/22/2008 |
| BIS | PL | ISSUED | L.L.G. PLBG & HTG INC | 09/16/2008 |
| BIS | — | ISSUED | RUSH CONTRACTING | 01/15/2008 |
| BIS | FP | ISSUED | MASTER FIRE SYSTEMS, INC | 03/14/2007 |
| BIS | OT | ISSUED | GRANT CONSTRUCTION CORP | 01/16/2007 |
| BIS | FP | ISSUED | MASTER FIRE SYSTEMS, INC | 12/05/2002 |
| BIS | PL | ISSUED | CAPE PLUMBING INC | 08/19/1991 |
| BIS | OT | ISSUED | ARROW #1 TRANSMISSION LTD. | 08/19/1991 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 04/15/2026 | Permit Issued | VIKING MECHANICAL INC | Air Conditioning Systems, Ventilation Systems | Cooling Daikin RXB24BXVJU 24,000 BTU · Condensing Unit ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/15/2026 | Permit Issued | HP SERVICES INC | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/17/2026 | Complete | A ELECTRICAL MAIN SVC INC | General Wiring |
| 03/14/2018 | Complete | R.J.ELECTRICAL CONTRACTOR | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 04/03/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/06/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 06/06/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/06/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 06/03/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/14/2026 | Fire-Resistant Penetrations and Joints | TENZIN NYANDAK | special |
| 05/15/2025 | Fire-Resistant Penetrations and Joints | ABRAHAM TAWIL | special |
| 05/12/2025 | Maintenance information | ABRAHAM TAWIL | energy_progress |
| 05/12/2025 | HVAC-R and service water heating equipment | ABRAHAM TAWIL | energy_progress |
| 05/12/2025 | HVAC-R and service water piping design and insulation | ABRAHAM TAWIL | energy_progress |
| 05/12/2025 | Mechanical Systems | ABRAHAM TAWIL | special |
| 05/12/2025 | Final | ABRAHAM TAWIL | progress |
| 05/12/2025 | HVAC-R and service water heating system controls | ABRAHAM TAWIL | energy_progress |
| 04/11/2025 | Fire-Resistant Penetrations and Joints | TENZIN NYANDAK | special |
| 07/23/2024 | Lighting controls | TENZIN NYANDAK | energy_progress |
| 07/23/2024 | Fenestration air leakage | TENZIN NYANDAK | energy_progress |
| 07/23/2024 | Fenestration and door U-factor and product ratings | TENZIN NYANDAK | energy_progress |
| 07/23/2024 | Fenestration areas | TENZIN NYANDAK | energy_progress |
| 07/15/2024 | Fire-Resistant Penetrations and Joints | TENZIN NYANDAK | special |
| 07/15/2024 | Final | TENZIN NYANDAK | progress |
| 07/15/2024 | Fire-Resistance Rated Construction | TENZIN NYANDAK | progress |
| 07/15/2024 | Energy Code Compliance Inspections | TENZIN NYANDAK | progress |
| 07/15/2024 | Structural Stability – Alterations of existing buildings | TENZIN NYANDAK | special |
| 07/15/2024 | Masonry | TENZIN NYANDAK | special |