| Owner | Filings | Most Recent |
|---|---|---|
| 3439 GRACE AVENUE LLC | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| PIROOZ ENGINEERING, P.C. | 7 | 06/17/2026 |
| Representative | Filings | Most Recent |
|---|---|---|
| ROYAL T E | 6 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| ALLIED SAFETY CONSULTANTS | General Contractor | 2 | 04/09/2026 |
| FLOW STATE ELECTRIC, LLC | Electrical | 1 | 03/22/2026 |
| ALL PRO PLBG & HTG INC | Fire Protection | 1 | 07/04/2026 |
| H BUILDING MANAGEMENT INC | General Contractor | 1 | 08/06/2026 |
| ALL PRO PLBG & HTG INC | Plumbing | 1 | 07/04/2026 |
| WATSON'S PLBG, HTG, & BDG | Plumbing | 1 | 07/04/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SJS INSPECTIONS AND CONSU | 8286 | 5 | 06/17/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Curb Cut | Signed-off | H BUILDING MANAGEMENT INC | 08/05/2026 |
| DOB NOW | Plumbing | Permit Issued | ALL PRO PLBG & HTG INC | 03/27/2026 |
| DOB NOW | Plumbing | Permit Issued | ALL PRO PLBG & HTG INC | 03/27/2026 |
| DOB NOW | Plumbing | Permit Issued | WATSON'S PLBG, HTG, & BDG | 12/16/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | ALLIED SAFETY CONSULTANTS | 09/12/2025 |
| DOB NOW | Construction Fence | Signed-off | ALLIED SAFETY CONSULTANTS | 08/27/2025 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 06/17/2026 | Signed-off | H BUILDING MANAGEMENT INC | Heating and Air Conditioning Systems, Ventilation Systems | Heat / Cool Mitsubishi Electric CU-1: MXZ-SM48NAMHZ
AH1, AH-2 & AH-3 & AH-4 :MSZ-GS09
AH-4: MSZ-GS12 48,000 BTU · Split System ×2 Ventilation |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/17/2026 | Permit Issued | ALL PRO PLBG & HTG INC | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/17/2026 | Permit Issued | ALL PRO PLBG & HTG INC | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/31/2026 | Complete | Solar Pro Electric Inc. | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/17/2026 | Signed-off | H BUILDING MANAGEMENT INC | Concrete, Wood |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/17/2026 | Signed-off | H BUILDING MANAGEMENT INC | Fence |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/07/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 05/19/2026 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 05/19/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 05/04/2026 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 05/04/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/04/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 05/01/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 04/24/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 04/10/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/15/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/17/2026 | Preliminary | SERGEY BOLOTOV | progress |
| 07/17/2026 | Footing and Foundation | SERGEY BOLOTOV | progress |
| 07/17/2026 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | SERGEY BOLOTOV | special |
| 07/17/2026 | Subgrade Inspections | SERGEY BOLOTOV | special |
| 07/17/2026 | Excavations - Sheeting, Shoring, and Bracing | SERGEY BOLOTOV | special |
| 07/17/2026 | Mechanical Systems | SERGEY BOLOTOV | special |
| 07/17/2026 | Fire-Resistant Penetrations and Joints | SERGEY BOLOTOV | special |
| 07/17/2026 | Concrete - Cast-In-Place | SERGEY BOLOTOV | special |
| 07/17/2026 | Chimneys and vents | SERGEY BOLOTOV | special |
| 07/17/2026 | Electric vehicle service equipment requirements | SERGEY BOLOTOV | energy_progress |
| 07/17/2026 | Metering | SERGEY BOLOTOV | energy_progress |
| 07/17/2026 | Insulation placement and R values | SERGEY BOLOTOV | energy_progress |
| 07/17/2026 | HVAC-R and service water piping design and insulation | SERGEY BOLOTOV | energy_progress |
| 07/17/2026 | Permanent certificate | SERGEY BOLOTOV | energy_progress |
| 07/17/2026 | HVAC-R and service water heating system controls | SERGEY BOLOTOV | energy_progress |
| 07/17/2026 | Final | SERGEY BOLOTOV | progress |
| 07/17/2026 | Energy Code Compliance Inspections | SERGEY BOLOTOV | progress |
| 07/17/2026 | Fire-Resistance Rated Construction | SERGEY BOLOTOV | progress |
| 07/17/2026 | Duct leakage testing, insulation and design | SERGEY BOLOTOV | energy_progress |
| 07/17/2026 | Ventilation and air distribution system | SERGEY BOLOTOV | energy_progress |
| 07/17/2026 | Air barrier — testing | SERGEY BOLOTOV | energy_progress |
| 07/17/2026 | Air barrier - visual inspection | SERGEY BOLOTOV | energy_progress |
| 07/17/2026 | HVAC-R and service water heating equipment | SERGEY BOLOTOV | energy_progress |
| 07/17/2026 | Fenestration and door U-factor and product ratings | SERGEY BOLOTOV | energy_progress |
| 07/17/2026 | Fenestration air leakage | SERGEY BOLOTOV | energy_progress |