16 Active Violations 3 unresolved · 13 paperwork only ▸
Miscellaneous outdoor recreational facility · Owner of record: NYC Department of Parks and Recreation · 0 FAR built · Flood zone X
Locations of Work
ArchitecturePlumbing
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
RoofRoof work1p · 1 filing · 5 docs
Floor 1City of New York Parks & Recreation6p · 7 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
NYC Parks804/09/2026
NYC Department of Parks and Recreation803/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Stantec Consulting110/10/2025
David Turner Architect704/01/2024
Bohler Engineering NY103/11/2022
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Bohler Engineering NY203/21/2026
RPO203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
David Turner ArchitectGeneral Contractor203/21/2026
Wynne Plumbing & HeatingPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
David Turner Architect3829405/06/2022
Building Lifecycle
All (70)Filed (9)Permit Issued (2)Violation (19)Objection (31)Special Inspection (9)
10/10/2025
Filed — Alteration
Filing herewith plans for the construction of a new domestic water service line. No change to use, egress, or occupancy.
M01275604-I1
09/09/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
05/01/2024
Permit issued — General Construction
M01028252-I1-GC
04/02/2024
Objection raised — Admin
04/02/2024
Objection resolved — Addressed
04/02/2024
Objection raised — Inspections
04/02/2024
Objection raised — Scope
04/02/2024
Objection resolved — Addressed
04/01/2024
Filed — Alteration
M01028252-I1
04/01/2024
Filed — No Work
M01028247-I1
03/30/2024
Special inspection requirement — Fenestration air leakage
DAVID TURNER
05/06/2022
Filed — Alteration
Temporary glazing of existing metal open air structure for summer use.
M00731624-I1
05/04/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
DAVID TURNER
03/24/2022
Violation issued (ECB, closed)
Construction
03/14/2022
Objection raised — Inspections
03/14/2022
Objection raised — Inspections
03/14/2022
Objection raised — Admin
03/14/2022
Objection raised — Admin
03/14/2022
Objection raised — Inspections
03/14/2022
Objection raised — Admin
03/14/2022
Objection raised — Scope
03/14/2022
Objection raised — Admin
03/14/2022
Objection raised — Other
03/11/2022
Filed — Alteration
Filing herewith plans for the construction of a new 3" domestic water service line. No change to use, egress, or occupancy.
M00657615-I1
02/09/2022
Violation issued (ECB, open)
Construction
12/21/2021
Violation issued (ECB, open)
Construction
11/06/2021
Violation issued (ECB, open)
Construction
09/23/2021
Violation issued (ECB, open)
Construction
01/05/2021
Special inspection requirement — Maintenance information
DAVID TURNER
01/05/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
DAVID TURNER
12/31/2020
Objection resolved — Addressed
12/24/2020
Objection resolved — Addressed
12/24/2020
Objection resolved — Addressed
12/21/2020
Objection raised — Other
12/21/2020
Objection raised — Other
12/21/2020
Objection raised — Other
12/17/2020
Filed — Alteration
Replacement of Hot Water Heater
M00375411-P2
12/12/2020
Special inspection requirement — Fire-Resistant Penetrations and Joints
DAVID TURNER
12/12/2020
Special inspection requirement — Maintenance information
DAVID TURNER
12/08/2020
Filed — Alteration
Replacement of Hot Water Heater
M00375411-P1
11/30/2020
Special inspection requirement — Fire-Resistant Penetrations and Joints
DAVID TURNER
11/30/2020
Special inspection requirement — Maintenance information
DAVID TURNER
10/19/2020
Permit issued — Plumbing
M00375411-I1-PL
07/30/2020
Filed — Alteration
Replacement of Hot Water Heater
M00375411-I1
03/25/2020
Objection raised — Fire_Protection
03/25/2020
Objection raised — Admin
03/25/2020
Objection raised — Inspections
03/25/2020
Objection raised — Mechanical
03/25/2020
Objection raised — Fire_Protection
03/25/2020
Objection raised — Fire_Protection
03/25/2020
Objection raised — Mechanical
03/25/2020
Objection raised — Other
03/25/2020
Objection raised — Fire_Protection
03/25/2020
Objection raised — Structural
03/25/2020
Objection raised — Fire_Protection
03/11/2020
Filed — No Work
M00312816-I1
05/21/2019
Violation issued (ECB, open)
Construction
10/05/2018
Violation issued (ECB, open)
Unknown
10/05/2018
Violation issued (ECB, closed)
Unknown
10/05/2018
Violation issued (ECB, closed)
Unknown
Latest 60 of 70 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedDavid Turner Architect05/01/2024
DOB NOWPlumbingPermit IssuedWynne Plumbing & Heating10/19/2020
BISOTISSUEDBlueshore Engineering03/23/2018
3 projects · most recent 10/10/2025
Water/Sanitary
FiledStatusContractorScope
10/10/2025——Water/Sanitary
03/11/2022——Water/Sanitary
12/17/2020Permit IssuedWynne Plumbing & HeatingWater/Sanitary
3 projects · most recent 09/01/2022
General Wiring
FiledStatusContractorScope
09/01/2022CompleteLion Heart ElectricGeneral Wiring
04/10/2020CompleteE-J Electric Installation CoGeneral Wiring
01/07/2020Permit IssuedGenesis Electrical GroupGeneral Wiring
▾Special Inspection Requirements (DOB NOW) — 9
DateRequirementInspectorRole
09/09/2025Fire-Resistant Penetrations and Joints—special
03/30/2024Fenestration air leakageDAVID TURNERenergy_progress
05/04/2022Fire-Resistant Penetrations and JointsDAVID TURNERspecial
01/05/2021Maintenance informationDAVID TURNERenergy_progress
01/05/2021Fire-Resistant Penetrations and JointsDAVID TURNERspecial
12/12/2020Fire-Resistant Penetrations and JointsDAVID TURNERspecial
12/12/2020Maintenance informationDAVID TURNERenergy_progress
11/30/2020Fire-Resistant Penetrations and JointsDAVID TURNERspecial
11/30/2020Maintenance informationDAVID TURNERenergy_progress
▾Tenants in the building
TenantSpaceFloorsRenovation projects
City of New York Parks & RecreationGovernment / CivicFloor 1
Project M01275604 Alteration · Approved · 10/10/2025
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 52 on file (BIS + DOB NOW)
▸Plans & Drawings9
▸DOB NOWPlans/Sketch4
09/02/2026M00731624-I1Request digital key ↗
08/27/2026M01028252-I1Request digital key ↗
08/21/2026M01275604-I1Request digital key ↗
Showing 3 of 4 on file for this type
▸DOB NOWPlans/Sketch - Plumbing3
09/04/2026M00375411-I1Request digital key ↗
08/15/2026M00375411-P1Request digital key ↗
08/15/2026M00375411-P2Request digital key ↗
▸DOB NOWPlans/Sketch - Place of Assembly1
08/15/2026M00312816-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Temporary Place of Assembly1
08/14/2026M01028247-I1Request digital key ↗
▸Applications & Permits2
▸BISPLAN / WORK APPROVAL APPLICATION1
03/07/2018140743373Open ↗
▸BISWORK PERMIT APPLICATION1
03/07/2018140743373Open ↗
▸Zoning, Tax Lot & Property Records1
▸BISFLOOD ZONE DESIGN CERTIFICATION1
03/07/2018140743373Open ↗
▸Seals & Professional Certifications19
▸DOB NOWDPL-1: Design Professional Seal & Signature9
09/04/2026M00375411-I1Open ↗
09/02/2026M00657615-I1Open ↗
08/27/2026M01028252-I1Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWProgress Inspector Seal & Signature4
09/02/2026M01028252-I1Open ↗
09/01/2026M00375411-P2Open ↗
08/24/2026M00375411-P1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature3
09/01/2026M00375411-P2Open ↗
08/24/2026M00375411-P1Open ↗
08/23/2026M00375411-I1Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
03/07/2018140743373Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
03/07/2018140743373Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
03/07/2018140743373Open ↗
▸Inspections & Test Reports1
▸BISTECHNICAL REPORT: RESPONSIBILITY1
03/07/2018140743373Open ↗
▸Approvals, Objections & Sign-offs18
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter9
09/04/2026M00375411-I1Open ↗
08/15/2026M00657615-I1Open ↗
08/13/2026M01028252-I1Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWDesign Commission Approval City Owned (Exterior Work)6
09/04/2026M00375411-I1Open ↗
08/15/2026M00657615-I1Open ↗
08/13/2026M01028252-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWDesign Commission Sign Off City Owned (Exterior Work)2
08/15/2026M00657615-I1Open ↗
08/13/2026M00375411-I1Open ↗
▸BISDESIGN COMM. APPROVAL: CITY-OWNED PROPERTY (EXTERIOR WORK)1
03/07/2018140743373Open ↗
▸Cost, Insurance & Ownership1
▸BISCOST AFFIDAVIT1
03/07/2018140743373Open ↗
▸Filing & Intake Forms1
▸BISEFILING JOB APPLICATION COVER SHEET1
03/07/2018140743373Open ↗