Single or multiple dwelling with stores or offices
349 7 AVENUE
BROOKLYN · BIN 3026127
💬 Discuss this project
1886Year Built
3Stories
S9Building Class
R6AZoning
4,397 sfGross Floor Area
4Units
0 Open ViolationsFDNY Report ↗
Single or multiple dwelling with stores or offices · 1,746 sf lot · 2.52 FAR built · Flood zone X
Locations of Work
Fire Protection
Floor 12p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
BS GROUP807/08/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
CCB ENGINEERING LLC107/09/2026
MSM ENGINEERING SERVICES, PLLC810/31/2024
JOEL PHAGOO P.E. PLLC208/13/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
MODERN BUILDING CONSULTANT803/21/2026
A1 EXPEDITING SERVICE403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
BS GROUP INCGeneral Contractor407/08/2026
JZ CONSTRUCTION GROUP INCGeneral Contractor407/08/2026
GARFIELD MAITLANDElectrical103/21/2026
MAITLAND GARFIELDElectrical103/21/2026
PIPESTYLISTS, INCPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MSM ENGINEERING SERVICES,8449710/31/2024
Building Lifecycle
All (55)Filed (11)Permit Issued (5)Signed Off (2)Violation (1)Inspection (6)Special Inspection (30)
08/01/2026
Signed off — Alteration
Propose Mechanical work at 1st floor commercial space & cellar of existing Eating & Drinking Establishment as per plan. No change in use, egress, or occupancy.
B01061424-S2
07/09/2026
Filed — Alteration
Propose Mechanical work at 1st floor commercial space & cellar of existing Eating & Drinking Establishment as per plan. No change in use, egress, or occupancy.
B01061424-P8
07/09/2026
Special inspection requirement — Maintenance information
George gao
07/09/2026
Special inspection requirement — Tenant Protection Plan Compliance
George gao
07/09/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
George gao
07/09/2026
Special inspection requirement — Mechanical Systems
George gao
07/09/2026
Special inspection requirement — Energy Code Compliance Inspections
George gao
07/09/2026
Special inspection requirement — Final
George gao
07/09/2026
Special inspection requirement — Fire-Resistance Rated Construction
George gao
07/09/2026
Special inspection requirement — Ventilation and air distribution system
George gao
07/09/2026
Special inspection requirement — Duct leakage testing, insulation and design
George gao
12/06/2024
Permit issued — Mechanical Systems
B01061424-S2-MS
11/21/2024
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
11/01/2024
Special inspection requirement — Interior lighting power
MOHAMED MAHMOUD
11/01/2024
Special inspection requirement — Tenant Protection Plan Compliance
11/01/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
MOHAMED MAHMOUD
11/01/2024
Special inspection requirement — Energy Code Compliance Inspections
MOHAMED MAHMOUD
11/01/2024
Special inspection requirement — Fire-Resistance Rated Construction
MOHAMED MAHMOUD
11/01/2024
Special inspection requirement — Lighting in dwelling units
MOHAMED MAHMOUD
10/31/2024
Filed — Alteration
Propose Mechanical work at 1st floor commercial space & cellar of existing Eating & Drinking Establishment as per plan. No change in use, egress, or occupancy.
B01061424-P3
10/05/2024
Special inspection requirement — Energy Code Compliance Inspections
MOHAMED MAHMOUD
10/05/2024
Special inspection requirement — Tenant Protection Plan Compliance
10/05/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
MOHAMED MAHMOUD
10/04/2024
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
10/03/2024
Filed — Alteration
Propose Mechanical work at 1st floor commercial space & cellar of existing Eating & Drinking Establishment as per plan. No change in use, egress, or occupancy.
B01061424-P5
10/03/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
10/01/2024
Special inspection requirement — Energy Code Compliance Inspections
MOHAMED MAHMOUD
10/01/2024
Special inspection requirement — Tenant Protection Plan Compliance
10/01/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
MOHAMED MAHMOUD
09/25/2024
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
08/09/2024
Filed — Alteration
Propose Mechanical work at 1st floor commercial space & cellar of existing Eating & Drinking Establishment as per plan. No change in use, egress, or occupancy.
B01061424-S2
08/07/2024
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
08/07/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
07/30/2024
Filed — Alteration
Propose Mechanical work at 1st floor commercial space & cellar of existing Eating & Drinking Establishment as per plan. No change in use, egress, or occupancy.
B01061424-P4
07/29/2024
Special inspection requirement — Tenant Protection Plan Compliance
07/24/2024
Special inspection requirement — Fire-Resistance Rated Construction
MOHAMED MAHMOUD
07/24/2024
Special inspection requirement — Interior lighting power
MOHAMED MAHMOUD
07/24/2024
Special inspection requirement — Lighting in dwelling units
MOHAMED MAHMOUD
07/24/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
MOHAMED MAHMOUD
07/24/2024
Special inspection requirement — Energy Code Compliance Inspections
MOHAMED MAHMOUD
07/24/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
MOHAMED MAHMOUD
07/24/2024
Special inspection requirement — Energy Code Compliance Inspections
MOHAMED MAHMOUD
07/24/2024
Special inspection requirement — Tenant Protection Plan Compliance
07/23/2024
Filed — Alteration
Propose Mechanical work at 1st floor commercial space & cellar of existing Eating & Drinking Establishment as per plan. No change in use, egress, or occupancy.
B01061424-P1
07/22/2024
Filed — Alteration
Propose Mechanical work at 1st floor commercial space & cellar of existing Eating & Drinking Establishment as per plan. No change in use, egress, or occupancy.
B01061424-P2
06/25/2024
Permit issued — Plumbing
B01061424-S1-PL
06/24/2024
Permit issued — General Construction
B01061424-I1-GC
06/17/2024
Filed — Alteration
Propose Mechanical work at 1st floor commercial space & cellar of existing Eating & Drinking Establishment as per plan. No change in use, egress, or occupancy.
B01061424-S1
06/17/2024
Filed — Alteration
Propose Mechanical work at 1st floor commercial space & cellar of existing Eating & Drinking Establishment as per plan. No change in use, egress, or occupancy.
B01061424-I1
01/06/2022
Signed off — Alteration
B00335003-I1
08/13/2021
Filed — Alteration
B00335003-P1
05/28/2021
Permit issued — Sidewalk Shed
B00335003-I1-SH
06/04/2020
Permit issued — Sidewalk Shed
B00335003-I1-SH
03/20/2020
Filed — Alteration
B00335003-I1
08/08/2013
Violation issued (ECB, closed)
Unknown
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsSigned-offJZ CONSTRUCTION GROUP INC12/06/2024
DOB NOWPlumbingSigned-offT & T PLUMBING INC06/25/2024
DOB NOWGeneral ConstructionSigned-offJZ CONSTRUCTION GROUP INC06/24/2024
DOB NOWSidewalk ShedSigned-offBS GROUP INC05/28/2021
DOB NOWSidewalk ShedSigned-offBS GROUP INC06/04/2020
BISFPISSUEDNEW YORK BUSINESS FIRE SYSTEM12/11/2000
BISFPISSUEDNEW YORK BUSINESS FIRE SYSTEM11/18/1999
BISPLISSUEDLAINLAND PLG HTNG09/23/1999
BISEQISSUEDFIRST FOREMOST CONST INC09/20/1999
BISMHISSUEDFIRST FOREMOST CONST INC09/20/1999
1 project · most recent 07/09/2026
Heating and Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
07/09/2026Signed-offJZ CONSTRUCTION GROUP INCHeating and Air Conditioning Systems
Heat / Cool
Tecumseh AAC5060E1000A 5 tons · Refrigeration Unit ×2
ACCM4860DNOH; AGF96M120D5B 1,200,000 BTU ×2
Tuttokool ACCM4860DNOH 1,850 CFM ×1
1 project · most recent 07/09/2026
Gas Water/Sanitary
FiledStatusContractorScope
07/09/2026Signed-offT & T PLUMBING INCGas, Water/Sanitary
5 projects · most recent 06/26/2024
General Wiring
FiledStatusContractorScope
06/26/2024CompleteKWONG MING ELECTRIC INCGeneral Wiring
10/21/2021CompleteANTONIO CERIELLO ELEC INCGeneral Wiring
07/21/2020CompleteANTONIO CERIELLO ELEC INC—
03/19/2020Permit IssuedGREEN POWER ELECTRIC CORP—
02/18/2020CompleteANTONIO CERIELLO ELEC INC—
▾Field Inspections (DOB CAP) — 6
DateTypeResultReport
11/21/2024Pass-Final General Construction Non-Directive 14PassView ↗
10/04/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
10/03/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
09/25/2024Fail-Final PL - Up to 3 Requested FloorsFailView ↗
08/07/2024Certified Gas-Gas-Piping-RoughingCertifiedView ↗
08/07/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 40
DateRequirementInspectorRole
07/09/2026Maintenance informationGeorge gaoenergy_progress
07/09/2026Tenant Protection Plan ComplianceGeorge gaospecial
07/09/2026Fire-Resistant Penetrations and JointsGeorge gaospecial
07/09/2026Mechanical SystemsGeorge gaospecial
07/09/2026Energy Code Compliance InspectionsGeorge gaoprogress
07/09/2026FinalGeorge gaoprogress
07/09/2026Fire-Resistance Rated ConstructionGeorge gaoprogress
07/09/2026Ventilation and air distribution systemGeorge gaoenergy_progress
07/09/2026Duct leakage testing, insulation and designGeorge gaoenergy_progress
11/01/2024Interior lighting powerMOHAMED MAHMOUDenergy_progress
11/01/2024Tenant Protection Plan Compliance—special
11/01/2024Fire-Resistant Penetrations and JointsMOHAMED MAHMOUDspecial
11/01/2024Energy Code Compliance InspectionsMOHAMED MAHMOUDprogress
11/01/2024Fire-Resistance Rated ConstructionMOHAMED MAHMOUDprogress
11/01/2024Lighting in dwelling unitsMOHAMED MAHMOUDenergy_progress
10/05/2024Energy Code Compliance InspectionsMOHAMED MAHMOUDprogress
10/05/2024Tenant Protection Plan Compliance—special
10/05/2024Fire-Resistant Penetrations and JointsMOHAMED MAHMOUDspecial
10/01/2024Energy Code Compliance InspectionsMOHAMED MAHMOUDprogress
10/01/2024Tenant Protection Plan Compliance—special
10/01/2024Fire-Resistant Penetrations and JointsMOHAMED MAHMOUDspecial
07/29/2024Tenant Protection Plan Compliance—special
07/24/2024Fire-Resistance Rated ConstructionMOHAMED MAHMOUDprogress
07/24/2024Interior lighting powerMOHAMED MAHMOUDenergy_progress
07/24/2024Lighting in dwelling unitsMOHAMED MAHMOUDenergy_progress
Latest 25 of 40.
▾Documents — 69 on file (BIS + DOB NOW)
▸Plans & Drawings11
▸DOB NOWPlans/Sketch9
08/24/2026B01061424-I1Request digital key ↗
08/24/2026B01061424-P8Request digital key ↗
08/24/2026B01061424-P5Request digital key ↗
Showing 3 of 9 on file for this type
▸DOB NOWPlans/Sketch - Sidewalk Shed2
09/02/2026B00335003-I1Request digital key ↗
08/15/2026B00335003-P1Request digital key ↗
▸Applications & Permits9
▸DOB NOWLPC Approval/Permit9
08/24/2026B01061424-S1Open ↗
08/24/2026B01061424-S2Open ↗
08/24/2026B01061424-P2Open ↗
Showing 3 of 9 on file for this type
▸Seals & Professional Certifications36
▸DOB NOWProgress Inspector Seal & Signature14
09/30/2026B01061424-P5Open ↗
09/01/2026B01061424-P4Open ↗
09/01/2026B01061424-S1Open ↗
Showing 3 of 14 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature12
08/24/2026B01061424-I1Open ↗
08/24/2026B01061424-P8Open ↗
08/24/2026B01061424-S2Open ↗
Showing 3 of 12 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature10
09/30/2026B01061424-P5Open ↗
09/01/2026B01061424-P4Open ↗
09/01/2026B01061424-S1Open ↗
Showing 3 of 10 on file for this type
▸Safety & Tenant Protection2
▸DOB NOWTenant Protection Plan2
08/13/2026B00335003-P1Open ↗
08/13/2026B00335003-I1Open ↗
▸Environmental & Asbestos10
▸DOB NOWDEP ACP-5: Asbestos Assessment Report10
08/24/2026B01061424-P8Open ↗
08/24/2026B01061424-S2Open ↗
08/24/2026B01061424-P4Open ↗
Showing 3 of 10 on file for this type
▸Approvals, Objections & Sign-offs1
▸DOB NOWLandmark Approval1
08/13/2026B01061424-P6Open ↗