| Owner | Filings | Most Recent |
|---|---|---|
| DNO EQUIPMENT AND DEVELOPMENT INC. | 4 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 04/29/2021 | $410K | — | NICK VELARDI'S SERVICE STATION, INC. → 7303 AMSTEL BLVD LLC | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| ARCHITECTURE WORK OFFICE PLLC | 8 | 06/09/2026 |
| FLORINELA MURESAN | 4 | 02/28/2025 |
| JO DESIGN | 2 | 03/29/2023 |
| VICTOR A. GORDON, PE PC | 2 | 09/30/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| K M DOB CONSULTING | 24 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| BBB CONSTRUCTION INC | General Contractor | 8 | 07/08/2026 |
| TOP DOG PLBG & HTG CORP | Plumbing | 3 | 07/08/2026 |
| ARSENIO NYC ELECTRICAL IN | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| TRIANGLE INSPECTION & TES | 7495 | 11 | 06/09/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Curb Cut | Signed-off | BBB CONSTRUCTION INC | 09/26/2025 |
| DOB NOW | Mechanical Systems | Signed-off | BBB CONSTRUCTION INC | 09/26/2025 |
| DOB NOW | Plumbing | Signed-off | TOP DOG PLBG & HTG CORP | 01/16/2025 |
| DOB NOW | General Construction | Permit Issued | BBB CONSTRUCTION INC | 11/08/2024 |
| DOB NOW | Plumbing | Signed-off | TOP DOG PLBG & HTG CORP | 10/03/2024 |
| DOB NOW | Construction Fence | Signed-off | BBB CONSTRUCTION INC | 03/28/2024 |
| DOB NOW | Foundation | Permit Issued | BBB CONSTRUCTION INC | 07/28/2023 |
| DOB NOW | Plumbing | Signed-off | TOP DOG PLBG & HTG CORP | 07/14/2023 |
| DOB NOW | Construction Fence | Signed-off | BBB CONSTRUCTION INC | 03/28/2023 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/28/2025 | Signed-off | TOP DOG PLBG & HTG CORP | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/13/2025 | Complete | ARSENIO NYC ELECTRICAL IN | General Wiring, Lighting |
| 09/20/2025 | Complete | ARSENIO NYC ELECTRICAL IN | 1 meters, 1 new_meters |
| 05/01/2025 | Complete | ARSENIO NYC ELECTRICAL IN | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/09/2026 | Permit Issued | BBB CONSTRUCTION INC | 6 scope_items |
| 03/29/2023 | Permit Issued | BBB CONSTRUCTION INC | Steel, Concrete, Masonry |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/09/2026 | Permit Issued | BBB CONSTRUCTION INC | Earthwork |
| Date | Type | Result | Report |
|---|---|---|---|
| 04/20/2026 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 04/07/2026 | Fail-Final Curb Cut Non-Directive 14 | Fail | View ↗ |
| 01/08/2026 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 12/10/2025 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 10/02/2024 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 08/31/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 08/03/2023 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 08/03/2023 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 08/03/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/01/2026 | Lighting controls | Rajasekhar Sakhamuri | energy_progress |
| 07/01/2026 | Insulation placement and R values | Rajasekhar Sakhamuri | energy_progress |
| 07/01/2026 | Maintenance information | Rajasekhar Sakhamuri | energy_progress |
| 07/01/2026 | Exterior lighting power | Rajasekhar Sakhamuri | energy_progress |
| 07/01/2026 | Fenestration air leakage | Rajasekhar Sakhamuri | energy_progress |
| 07/01/2026 | Fenestration and door U-factor and product ratings | Rajasekhar Sakhamuri | energy_progress |
| 07/01/2026 | Protection of exposed foundation insulation | Rajasekhar Sakhamuri | energy_progress |
| 07/01/2026 | Air barrier - visual inspection | Rajasekhar Sakhamuri | energy_progress |
| 07/01/2026 | Fenestration areas | Rajasekhar Sakhamuri | energy_progress |
| 07/01/2026 | Interior lighting power | Rajasekhar Sakhamuri | energy_progress |
| 07/01/2026 | Metering | Rajasekhar Sakhamuri | energy_progress |
| 07/01/2026 | Fire-Resistance Rated Construction | Rajasekhar Sakhamuri | progress |
| 07/01/2026 | Fire-Resistant Penetrations and Joints | Rajasekhar Sakhamuri | special |
| 07/01/2026 | Masonry | Rajasekhar Sakhamuri | special |
| 07/01/2026 | Subgrade Inspections | Rajasekhar Sakhamuri | special |
| 07/01/2026 | Excavations - Sheeting, Shoring, and Bracing | Rajasekhar Sakhamuri | special |
| 07/01/2026 | Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable) | Rajasekhar Sakhamuri | special |
| 07/01/2026 | Exterior Insulation and Finish Systems (EIFS) | Rajasekhar Sakhamuri | special |
| 07/01/2026 | Lowest Floor Elevation | Rajasekhar Sakhamuri | progress |
| 07/01/2026 | Final | Rajasekhar Sakhamuri | progress |
| 07/01/2026 | Energy Code Compliance Inspections | Rajasekhar Sakhamuri | progress |
| 06/05/2026 | Exterior Insulation and Finish Systems (EIFS) | Rajasekhar Sakhamuri | special |
| 06/05/2026 | Air barrier - visual inspection | Rajasekhar Sakhamuri | energy_progress |
| 06/05/2026 | Lighting controls | Rajasekhar Sakhamuri | energy_progress |
| 06/05/2026 | Exterior lighting power | Rajasekhar Sakhamuri | energy_progress |