35-10 12TH STREET
QUEENS · BIN 4436744
💬 Discuss this project
2024Year Built
8Stories
D3Building Class
R6AZoning
139,119 sfGross Floor Area
152Units
Rent Stabilized5 Active Violations ▸FDNY Report ↗
Elevator apt, fireproof without stores · Owner of record: Point Property Lic · 28,965 sf lot · 4.8 FAR built · Flood zone X500
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionLandscapeCivilGeneralOther
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Whole building & multi-floor projectsThe Vaja Group3 filings
RoofSidewalk shed and pipe scaffolding1p · 1 filing
Floor 1The Vaja Group1 filing
Site & exteriorProposed 8 story residential new building2 filings
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Vaja Group7510/13/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
01/25/2024$17.6M—Private party → POINT PROPERTY LIC LLC$127/sf building
03/18/2015$4.8M—— → —— not available
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
YG Expediting2403/21/2026
Geiger E A Group203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
City Wide Builders GroupGeneral Contractor1407/08/2026
Target Piping NYFire Protection307/08/2026
City Wide Builders GroupScaffold303/21/2026
GWT EnterprisesScaffold204/09/2026
Power Direct ElectricElectrical103/22/2026
Solas ElectricalElectrical103/21/2026
B&B Mechanical Plumbing & HeatingPlumbing107/08/2026
Solas ElectricalElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Big Apple Group NY A Rma91682009/14/2026
HRF Services5616108/26/2024
Building Lifecycle
All (170)Filed (28)Permit Issued (6)Signed Off (10)Violation (8)Inspection (5)Objection (80)Special Inspection (30)Tax Incentive (3)
09/14/2026
Filed — New Building
Sprinkler & Standpipe work type filed in conjunction with NB application #Q00650506-I1
Q00650506-A6
08/10/2026
Signed off — Alteration
Curb Cut application filed herewith in conjunction with New Building, Job #Q00650506.
Q00669259-I1
08/01/2026
421-a(16) construction completed
06/09/2026
Filed — New Building
Sprinkler & Standpipe work type filed in conjunction with NB application #Q00650506-I1
Q00650506-A5
05/20/2026
Filed — New Building
Sprinkler & Standpipe work type filed in conjunction with NB application #Q00650506-I1
Q00650506-A4
05/18/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
SOORJBALLY HARILALL
05/18/2026
Special inspection requirement — Air barrier continuity plan testing
SOORJBALLY HARILALL
05/18/2026
Special inspection requirement — Insulation placement and R values
SOORJBALLY HARILALL
05/18/2026
Special inspection requirement — Maintenance information
SOORJBALLY HARILALL
05/18/2026
Special inspection requirement — Fenestration air leakage
SOORJBALLY HARILALL
05/18/2026
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
SOORJBALLY HARILALL
05/18/2026
Special inspection requirement — Exterior lighting power
SOORJBALLY HARILALL
05/18/2026
Special inspection requirement — Fenestration areas
SOORJBALLY HARILALL
05/18/2026
Special inspection requirement — Lighting in dwelling units
SOORJBALLY HARILALL
05/18/2026
Special inspection requirement — Metering
SOORJBALLY HARILALL
05/18/2026
Special inspection requirement — Energy Code Compliance Inspections
SOORJBALLY HARILALL
05/18/2026
Special inspection requirement — Fire-Resistance Rated Construction
SOORJBALLY HARILALL
05/18/2026
Special inspection requirement — Protection of exposed foundation insulation
SOORJBALLY HARILALL
05/18/2026
Special inspection requirement — Interior lighting power
SOORJBALLY HARILALL
05/18/2026
Special inspection requirement — Wall Panels, Curtain Walls, and Veneers
SOORJBALLY HARILALL
05/18/2026
Special inspection requirement — Air barrier - visual inspection
SOORJBALLY HARILALL
05/18/2026
Special inspection requirement — Electrical motors and elevators
SOORJBALLY HARILALL
05/18/2026
Special inspection requirement — Lighting controls
SOORJBALLY HARILALL
05/18/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
SOORJBALLY HARILALL
04/17/2026
Inspection — Fail-Final Curb Cut Non-Directive 14
Fail
View inspection ↗
03/19/2026
Filed — Alteration
Curb Cut application filed herewith in conjunction with New Building, Job #Q00650506.
Q00669259-P2
03/19/2026
Signed off — New Building
Sprinkler & Standpipe work type filed in conjunction with NB application #Q00650506-I1
Q00650506-S4
03/13/2026
Special inspection requirement — Fenestration areas
SOORJBALLY HARILALL
03/13/2026
Special inspection requirement — Air barrier - visual inspection
SOORJBALLY HARILALL
03/13/2026
Special inspection requirement — Protection of exposed foundation insulation
SOORJBALLY HARILALL
03/13/2026
Special inspection requirement — Fire-Resistance Rated Construction
SOORJBALLY HARILALL
03/13/2026
Special inspection requirement — Metering
SOORJBALLY HARILALL
03/13/2026
Special inspection requirement — Energy Code Compliance Inspections
SOORJBALLY HARILALL
03/13/2026
Special inspection requirement — Exterior lighting power
SOORJBALLY HARILALL
03/13/2026
Special inspection requirement — Air barrier continuity plan testing
SOORJBALLY HARILALL
03/13/2026
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
SOORJBALLY HARILALL
03/13/2026
Special inspection requirement — Lighting controls
SOORJBALLY HARILALL
03/13/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
SOORJBALLY HARILALL
03/12/2026
Inspection — Fail-Final Curb Cut Non-Directive 14
Fail
View inspection ↗
01/30/2026
Filed — New Building
Sprinkler & Standpipe work type filed in conjunction with NB application #Q00650506-I1
Q00650506-A3
12/12/2025
Signed off — Alteration
PLUMBING APPLICATION FILED IN CONJUNCTION WITH NEW BUILDING JOB #Q00650506
Q00688635-I1
12/11/2025
Signed off — New Building
Sprinkler & Standpipe work type filed in conjunction with NB application #Q00650506-I1
Q00650506-S5
12/04/2025
Signed off — Alteration
MECHANICAL APPLICATION FILED IN CONJUNCTION WITH NEW BUILDING JOB #Q00650506-I1
Q00688569-I1
11/18/2025
Signed off — Alteration
Q01154928-I1
11/12/2025
Objection resolved — Addressed
11/11/2025
Signed off — New Building
Sprinkler & Standpipe work type filed in conjunction with NB application #Q00650506-I1
Q00650506-S2
11/11/2025
Signed off — New Building
Sprinkler & Standpipe work type filed in conjunction with NB application #Q00650506-I1
Q00650506-S3
11/07/2025
Filed — New Building
Sprinkler & Standpipe work type filed in conjunction with NB application #Q00650506-I1
Q00650506-A2
11/07/2025
Objection raised — Other
10/21/2025
Signed off — Alteration
Q00669283-I1
09/10/2025
Permit issued — Curb Cut
Q00669259-I1-CC
08/25/2025
Violation issued (ECB, closed)
Unknown
08/25/2025
Violation issued (ECB, closed)
Unknown
08/11/2025
Filed — New Building
Sprinkler & Standpipe work type filed in conjunction with NB application #Q00650506-I1
Q00650506-P9
07/10/2025
Permit issued — Construction Fence
Q00669283-I1-FN
06/11/2025
Permit issued — Mechanical Systems
Q00688569-I1-MS
06/07/2025
Violation issued (ECB, closed)
Construction
06/07/2025
Violation issued (ECB, closed)
Construction
06/07/2025
Violation issued (ECB, closed)
Unknown
06/05/2025
Violation issued (ECB, closed)
Unknown
Latest 60 of 170 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWCurb CutSigned-offCity Wide Builders Group09/10/2025
DOB NOWConstruction FenceSigned-offCity Wide Builders Group07/10/2025
DOB NOWMechanical SystemsSigned-offCity Wide Builders Group06/11/2025
DOB NOWSupported ScaffoldSigned-offGWT Enterprises12/26/2024
DOB NOWSidewalk ShedSigned-offGWT Enterprises12/26/2024
DOB NOWPlumbingSigned-offTarget Piping NY11/08/2024
BISEQISSUEDN Tech Design of America05/19/2022
BIS—ISSUEDN Tech Design of America05/19/2022
7 projects · most recent 08/12/2026
General Wiring
FiledStatusContractorScope
08/12/2026CompleteForsure Electric NY—
12/02/2025CompleteSolas Electrical—
08/27/2025CompleteAccurate ElectricalGeneral Wiring
04/29/2025CompletePower Direct Electric—
02/21/2025CompleteRichard Neu—
01/08/2025CompletePower Direct Electric—
01/06/2025CompleteSolas Electrical—
1 project · most recent 09/14/2026
Concrete
FiledStatusContractorScope
09/14/2026Permit IssuedCity Wide Builders GroupConcrete
▾Field Inspections (DOB CAP) — 5
DateTypeResultReport
04/17/2026Fail-Final Curb Cut Non-Directive 14FailView ↗
03/12/2026Fail-Final Curb Cut Non-Directive 14FailView ↗
05/20/2025Fail-Final PL - Up to 9 Requested FloorsFailView ↗
04/10/2025Pass-Final PL - Up to 9 Requested FloorsPassView ↗
12/09/2024Pass-Final PL - UndergroundPassView ↗
▾Special Inspection Requirements (DOB NOW) — 147
DateRequirementInspectorRole
05/18/2026Exterior Insulation and Finish Systems (EIFS)SOORJBALLY HARILALLspecial
05/18/2026Interior lighting powerSOORJBALLY HARILALLenergy_progress
05/18/2026Lighting in dwelling unitsSOORJBALLY HARILALLenergy_progress
05/18/2026Air barrier continuity plan testingSOORJBALLY HARILALLenergy_progress
05/18/2026Insulation placement and R valuesSOORJBALLY HARILALLenergy_progress
05/18/2026Fenestration areasSOORJBALLY HARILALLenergy_progress
05/18/2026Lighting controlsSOORJBALLY HARILALLenergy_progress
05/18/2026Electrical motors and elevatorsSOORJBALLY HARILALLenergy_progress
05/18/2026Exterior lighting powerSOORJBALLY HARILALLenergy_progress
05/18/2026Air barrier - visual inspectionSOORJBALLY HARILALLenergy_progress
05/18/2026Fenestration air leakageSOORJBALLY HARILALLenergy_progress
05/18/2026Maintenance informationSOORJBALLY HARILALLenergy_progress
05/18/2026MeteringSOORJBALLY HARILALLenergy_progress
05/18/2026Fenestration and door U-factor and product ratingsSOORJBALLY HARILALLenergy_progress
05/18/2026Protection of exposed foundation insulationSOORJBALLY HARILALLenergy_progress
05/18/2026Fire-Resistance Rated ConstructionSOORJBALLY HARILALLprogress
05/18/2026Energy Code Compliance InspectionsSOORJBALLY HARILALLprogress
05/18/2026Wall Panels, Curtain Walls, and VeneersSOORJBALLY HARILALLspecial
05/18/2026Fire-Resistant Penetrations and JointsSOORJBALLY HARILALLspecial
03/13/2026Fire-Resistant Penetrations and JointsSOORJBALLY HARILALLspecial
03/13/2026Air barrier continuity plan testingSOORJBALLY HARILALLenergy_progress
03/13/2026Fenestration and door U-factor and product ratingsSOORJBALLY HARILALLenergy_progress
03/13/2026Lighting controlsSOORJBALLY HARILALLenergy_progress
03/13/2026Maintenance informationSOORJBALLY HARILALLenergy_progress
03/13/2026Fenestration air leakageSOORJBALLY HARILALLenergy_progress
Latest 25 of 147.
▾Documents — 221 on file (BIS + DOB NOW)
▸Plans & Drawings28
▸DOB NOWPlans/Sketch28
08/26/2026Q00669283-I1Request digital key ↗
08/26/2026Q00688635-P2Request digital key ↗
08/26/2026Q00688635-I1Request digital key ↗
Showing 3 of 28 on file for this type
▸Applications & Permits13
▸BISPLAN / WORK APPROVAL APPLICATION8
07/29/2025440706372Open ↗
09/18/2024440706372Open ↗
07/19/2022421805586Open ↗
Showing 3 of 8 on file for this type
▸BISWORK PERMIT APPLICATION2
06/30/2022421805586Open ↗
06/30/2022421805586Open ↗
▸DOB NOWHPD - Permit Notice2
08/13/2026Q00650506-I1Open ↗
08/13/2026Q00650506-S2Open ↗
▸BISBPP-5 - Authorization to the Department of Transportation1
03/12/2022440706372Open ↗
▸Zoning, Tax Lot & Property Records24
▸DOB NOWRestrictive Declaration/Easement 111
08/16/2026Q00650506-A5Open ↗
08/16/2026Q00650506-A4Open ↗
08/16/2026Q00650506-S4Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWZD1: DOB Zoning Diagram7
08/16/2026Q00650506-A5Open ↗
08/16/2026Q00650506-P8Open ↗
08/16/2026Q00650506-I1Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWZoning Exhibit form (1-5)5
08/16/2026Q00650506-A2Open ↗
08/16/2026Q00650506-A5Open ↗
08/16/2026Q00650506-A4Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026Q00650506-I1Open ↗
▸Seals & Professional Certifications69
▸DOB NOWDPL-1: Design Professional Seal & Signature28
08/26/2026Q00669283-I1Open ↗
08/26/2026Q00688635-P3Open ↗
08/26/2026Q00688635-P1Open ↗
Showing 3 of 28 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature21
10/07/2026Q00650506-P4Open ↗
10/07/2026Q00650506-P4Open ↗
09/27/2026Q00688635-P2Open ↗
Showing 3 of 21 on file for this type
▸DOB NOWProgress Inspector Seal & Signature18
10/07/2026Q00650506-P4Open ↗
09/27/2026Q00688635-P2Open ↗
09/27/2026Q00688635-P2Open ↗
Showing 3 of 18 on file for this type
▸BISAPPLICANT OWNER SIGNATURE1
03/12/2022440706372Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
03/12/2022440706372Open ↗
▸Trade Schedules & Equipment8
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)5
08/16/2026Q00650506-P8Open ↗
08/16/2026Q00650506-P5Open ↗
08/16/2026Q00650506-I1Open ↗
Showing 3 of 5 on file for this type
▸BISGAS CUT-OFF1
06/30/2022421805586Open ↗
▸BISSEWER CUT-OFF1
06/30/2022421805586Open ↗
▸DOB NOWStandpipe Alarms Drawings1
08/16/2026Q00650506-I1—
▸Safety & Tenant Protection13
▸DOB NOWStreet Tree Checklist7
08/16/2026Q00650506-A5Open ↗
08/16/2026Q00650506-A4Open ↗
08/16/2026Q00650506-A2Open ↗
Showing 3 of 7 on file for this type
▸BISSTREET TREE CHECKLIST2
11/13/2024440706372Open ↗
03/12/2022440706372Open ↗
▸BISEXCAVATION OR DEMOLITION: 5-DAY NOTICE1
06/30/2022421805586Open ↗
▸BISDEMOLITION SUBMITTAL CERTIFICATION FORM1
06/30/2022421805586Open ↗
▸BISSRO MD ANTI-HARASSMENT CHECKLIST1
06/30/2022421805586Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026Q00650506-I1Open ↗
▸Environmental & Asbestos17
▸DOB NOWOER: Notice to Proceed9
08/16/2026Q00650506-P3Open ↗
08/16/2026Q00650506-S2Open ↗
08/16/2026Q00650506-I1Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWOER: Notice of Satisfaction6
08/16/2026Q00650506-I1Open ↗
08/13/2026Q00688635-I1Open ↗
08/13/2026Q00650506-I1Open ↗
Showing 3 of 6 on file for this type
▸BISENVIRONMENTAL RESTRICTIONS - OER NOTICE TO PROCEED1
11/13/2024440706372Open ↗
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
06/30/2022421805586Open ↗
▸Energy Compliance2
▸DOB NOWEN2: As Built Energy Analysis2
08/13/2026Q00688635-I1Open ↗
08/13/2026Q00688569-I1Open ↗
▸Inspections & Test Reports5
▸DOB NOWSOIL REPORT3
08/16/2026Q00650506-P3Open ↗
08/16/2026Q00650506-S2Open ↗
08/13/2026Q00650506-P4Open ↗
▸DOB NOWTR4 Plot Diagram1
08/13/2026Q00650506-S2Open ↗
▸DOB NOWTR4 Test Report and Plot Diagram1
08/13/2026Q00650506-S2Open ↗
▸Approvals, Objections & Sign-offs4
▸BISLETTERS - SUPPORTING DOCUMENTATION3
07/20/2022421805586Open ↗
06/30/2022421805586Open ↗
06/30/2022421805586Open ↗
▸BISTAP LETTER - DOM SVC : DEP-DOM1
06/30/2022421805586Open ↗
▸Cost, Insurance & Ownership2
▸BISDEPT OF FINANCE VERIFICATION1
06/30/2022421805586Open ↗
▸BISPROJECT SPECIFIC GENERAL LIABILITY INSURANCE1
06/30/2022421805586Open ↗
▸Filing & Intake Forms10
▸BISEFILING COVER SHEET4
07/19/2022421805586Open ↗
05/09/2022421805586Open ↗
05/06/2022421805586Open ↗
Showing 3 of 4 on file for this type
▸BISBOROUGH INTAKE FORM3
07/19/2022421805586Open ↗
06/30/2022421805586Open ↗
06/30/2022421805586Open ↗
▸BISBPP: CHECKLIST IN LIEU OF PLANS-ALT31
03/12/2022440706372Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
03/12/2022440706372Open ↗
▸BISADDITIONAL INFORMATION1
08/05/2025440706372Open ↗
▸Other Documents26
▸DOB NOWSite Survey: Initial7
08/16/2026Q00650506-A5Open ↗
08/16/2026Q00650506-A4Open ↗
08/16/2026Q00650506-A2Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWProperty Ownership Certification7
08/16/2026Q00650506-P8Open ↗
08/16/2026Q00650506-A5Open ↗
08/16/2026Q00650506-A4Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone7
08/16/2026Q00650506-A2Open ↗
08/16/2026Q00650506-A5Open ↗
08/16/2026Q00650506-A4Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWAdjoining Owners Notification2
08/13/2026Q00650506-S2Open ↗
08/13/2026Q00650506-S6Open ↗
▸BISNEW CC1
11/13/2024440706372Open ↗
▸DOB NOWProject Specific General Liability (PGL1)1
08/13/2026Q00650506-I1Open ↗
▸DOB NOWCPC Certification for FRESH1
08/13/2026Q00650506-I1Open ↗