LL97 CoveredRent Stabilized66 Open Violations ▸FISP: SWARMP
Elevator cooperative · Owner of record: EMILY TOWERS OWNERS CORP · 27,600 sf lot · 3.7 FAR built · Flood zone X
Locations of Work
No floor-level scope or drawing coverage on file for this building.
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
EBMG707/08/2026
EMILY TOWER OWNERS CORP1403/22/2026
TOWERS, EMILY OWNERS C203/22/2026
EMILY TOWER QUNERS CORP203/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
ACCARDO ENGINEERING, PLLC103/05/2021
ASHRAF CORP101/05/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
D D EXPEDITORS203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
EVEREST SCAFFOLDING INCGeneral Contractor203/21/2026
SCHNELLBACHER-SENDON GRO*General Contractor207/08/2026
BOROWIDE ELECT'L CONTR'SElectrical103/22/2026
ANDAMIO SCAFFOLDING LLCGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
ACCARDO ENGINEERING, PLLC1247103/05/2021
Building Lifecycle
All (81)Filed (2)Permit Issued (4)Signed Off (2)Facade (FISP) (9)Violation (60)Objection (4)
05/07/2026
Violation issued (HPD, closed)
A
11/21/2025
Violation issued (HPD, closed)
I
11/26/2022
Violation issued (HPD, closed)
A
11/26/2022
Violation issued (HPD, closed)
A
11/26/2022
Violation issued (HPD, open)
C
09/22/2022
Violation issued (ECB, closed)
Elevators
09/22/2022
Violation issued (ECB, closed)
Elevators
09/07/2022
Cycle 9 facade report submitted
09/07/2022
Cycle 9 facade report signed — SWARMP
08/16/2022
Cycle 9 facade inspection completed
07/28/2022
Signed off — Alteration
Facade repair/replacement to include masonry, pointing, sills, concrete patching, scrape/paint fire escapes, partial parapet repair, caulking, A/C sleeve.
Q00475783-I1
05/18/2022
Signed off — Alteration
Q00446855-I1
03/04/2022
Violation issued (HPD, closed)
I
03/04/2022
Violation issued (HPD, closed)
A
09/16/2021
Permit issued — Sidewalk Shed
Q00446855-I1-SH
09/09/2021
Violation issued (HPD, open)
C
09/09/2021
Violation issued (HPD, open)
B
09/09/2021
Violation issued (HPD, open)
B
09/09/2021
Violation issued (HPD, open)
C
09/09/2021
Violation issued (HPD, open)
C
09/09/2021
Violation issued (HPD, open)
C
09/09/2021
Violation issued (HPD, open)
B
09/09/2021
Violation issued (HPD, open)
B
06/03/2021
Permit issued — General Construction
Q00475783-I1-GC
05/13/2021
Permit issued — General Construction
Q00475783-I1-GC
03/18/2021
Objection raised — Inspections
03/18/2021
Objection resolved — Addressed
03/18/2021
Objection raised — Other
03/18/2021
Objection resolved — Addressed
03/05/2021
Filed — Alteration
Facade repair/replacement to include masonry, pointing, sills, concrete patching, scrape/paint fire escapes, partial parapet repair, caulking, A/C sleeve.
Q00475783-I1
01/06/2021
Permit issued — Sidewalk Shed
Q00446855-I1-SH
01/05/2021
Filed — Alteration
Q00446855-I1
03/09/2020
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
03/09/2020
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
02/19/2019
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
02/19/2019
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
10/21/2018
Cycle 8 facade report signed — SWARMP
10/21/2018
Cycle 8 facade report signed — SWARMP
07/31/2018
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
07/12/2018
Cycle 8 facade report submitted
07/12/2018
Cycle 8 facade report submitted
06/11/2018
Cycle 8 facade inspection completed
06/11/2018
Cycle 8 facade inspection completed
12/04/2017
Violation issued (HPD, closed)
I
05/03/2017
Violation issued (HPD, open)
B
01/04/2017
Violation issued (HPD, closed)
B
01/04/2017
Violation issued (HPD, closed)
B
01/04/2017
Violation issued (HPD, closed)
C
08/02/2015
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
05/02/2015
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
05/15/2014
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
10/07/2011
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
10/07/2011
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
04/21/2011
Violation issued (HPD, open)
B
04/21/2011
Violation issued (HPD, open)
B
04/21/2011
Violation issued (HPD, open)
B
04/21/2011
Violation issued (HPD, open)
B
03/13/2009
Violation issued (ECB, closed)
Unknown
12/06/2007
Violation issued (DOB, closed)
VW*-VIOLATION - WORK W/O PERMIT DISMISSED
09/27/2007
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
Latest 60 of 81 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSidewalk ShedSigned-offANDAMIO SCAFFOLDING LLC09/16/2021
DOB NOWGeneral ConstructionSigned-offSCHNELLBACHER-SENDON GRO*06/03/2021
DOB NOWGeneral ConstructionSigned-offSCHNELLBACHER-SENDON GRO*05/13/2021
DOB NOWSidewalk ShedSigned-offEVEREST SCAFFOLDING INC01/06/2021
BISFSISSUEDC C CONTROLLED COMBUSTION09/09/2014
BISPLISSUEDCC CONTROLLED PLBG CO INC09/09/2014
BISEQISSUEDMARK CONSTRUCTION CO02/29/2008
BISEQISSUEDMARK CONSTRUCTION CO10/16/2006
BISOTISSUEDMARK CONSTRUCTION CO06/13/2006
BISBLISSUEDSTAR INDUST. SVC CO INC09/16/2005
1 project · most recent 01/08/2021
FiledStatusContractorScope
01/08/2021CompleteBOROWIDE ELECT'L CONTR'S—
Nothing on file for this building.
▾Documents — 37 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch - Sidewalk Shed1
08/27/2026Q00446855-I1Request digital key ↗
▸DOB NOWPlans/Sketch - General Construction1
08/15/2026Q00475783-I1Request digital key ↗
▸Applications & Permits6
▸BISWORK PERMIT APPLICATION4
09/22/2014421026516Open ↗
09/22/2014421026516Open ↗
09/22/2014421026516Open ↗
Showing 3 of 4 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION2
04/10/2017421026516Open ↗
09/22/2014421026516Open ↗
▸Seals & Professional Certifications11
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION4
05/04/2017421026516Open ↗
09/22/2014421026516Open ↗
09/22/2014421026516Open ↗
Showing 3 of 4 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST2
09/22/2014421026516Open ↗
02/11/2008410065441Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/27/2026Q00446855-I1Open ↗
08/27/2026Q00475783-I1Open ↗
▸BISPC FULL REPORT1
02/11/2008410065441Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
09/22/2014421026516Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM1
02/11/2008410065441Open ↗
▸Trade Schedules & Equipment2
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE1
09/22/2014421026516Open ↗
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT1
09/22/2014421026516Open ↗
▸Environmental & Asbestos3
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER1
02/11/2008410065441Open ↗
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
09/22/2014421026516Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/15/2026Q00475783-I1Open ↗
▸Energy Compliance5
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS3
05/04/2017421026516Open ↗
09/22/2014421026516Open ↗
09/22/2014421026516Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
05/04/2017421026516Open ↗
▸DOB NOWEN2: As Built Energy Analysis.1
08/13/2026Q00475783-I1Open ↗
▸Approvals, Objections & Sign-offs2
▸BISADMINISTRATIVE OBJECTIONS1
02/11/2008410065441Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
05/04/2017421026516Open ↗
▸Cost, Insurance & Ownership3
▸BISCOST AFFIDAVIT2
05/04/2017421026516Open ↗
09/22/2014421026516Open ↗
▸BISLL58/88-CIVIL PENALTY AFFIDAVIT1
02/29/2008410065441Open ↗
▸Filing & Intake Forms3
▸BISADDITIONAL INFORMATION2
04/13/2017421026516Open ↗
04/10/2017421026516Open ↗
▸BISEFILING COVER SHEET1
09/22/2014421026516Open ↗