| Owner | Filings | Most Recent |
|---|---|---|
| HEARTFELT BUILDERS | 3 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| JFA ARCHITECTS & ENGINEERS DPC | 9 | 04/03/2026 |
| DUY HOANG | 1 | 01/30/2026 |
| Representative | Filings | Most Recent |
|---|---|---|
| BAC Developers Group | 8 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| HEARTFELT TOWNHOUSE BUILD | General Contractor | 6 | 09/26/2026 |
| MPI PLUMBING CORP | Plumbing | 3 | 09/26/2026 |
| POWER DIRECT ELECTRIC INC | Electrical | 2 | 03/22/2026 |
| M.R. ELEC'L SERVICE LLC | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| HRF SERVICES CORP | 5616 | 1 | 01/06/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Structural | Permit Issued | HEARTFELT TOWNHOUSE BUILD | 09/25/2026 |
| DOB NOW | Plumbing | Permit Issued | MPI PLUMBING CORP | 09/25/2026 |
| DOB NOW | Support of Excavation | Permit Issued | HEARTFELT TOWNHOUSE BUILD | 09/25/2026 |
| DOB NOW | Foundation | Permit Issued | HEARTFELT TOWNHOUSE BUILD | 09/25/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | HEARTFELT TOWNHOUSE BUILD | 09/25/2026 |
| DOB NOW | Standpipe | Permit Issued | MPI PLUMBING CORP | 09/24/2026 |
| DOB NOW | Standpipe | Permit Issued | MPI PLUMBING CORP | 09/24/2026 |
| DOB NOW | Construction Fence | Permit Issued | HEARTFELT TOWNHOUSE BUILD | 02/04/2026 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/21/2026 | Permit Issued | POWER DIRECT ELECTRIC INC | General Wiring |
| 12/18/2025 | Permit Issued | M.R. ELEC'L SERVICE LLC | General Wiring |
| 12/15/2025 | Permit Issued | POWER DIRECT ELECTRIC INC | General Wiring |
| 12/15/2025 | Permit Issued | POWER DIRECT ELECTRIC INC | 69 meters, 69 new_meters |
| 12/15/2025 | Permit Issued | POWER DIRECT ELECTRIC INC | 1 meters, 1 new_meters |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/16/2026 | Air barrier continuity plan testing | — | energy_progress |
| 04/16/2026 | Electrical motors and elevators | — | energy_progress |
| 04/14/2026 | Construction Operations Influencing Adjacent Structures | — | special |
| 04/14/2026 | Excavations - Sheeting, Shoring, and Bracing | — | special |
| 04/14/2026 | Subsurface Conditions – Fill Placement & In-Place Density | — | special |
| 04/14/2026 | Subsurface Investigations (Borings/Test Pits) | — | special |
| 04/03/2026 | Excavations - Sheeting, Shoring, and Bracing | — | special |
| 03/26/2026 | Construction Operations Influencing Adjacent Structures | — | special |
| 03/26/2026 | Subsurface Conditions – Fill Placement & In-Place Density | — | special |
| 03/26/2026 | Subsurface Investigations (Borings/Test Pits) | — | special |
| 12/29/2025 | HVAC-R and service water heating equipment | — | energy_progress |
| 12/29/2025 | Fire-Resistant Penetrations and Joints | — | special |
| 12/29/2025 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | — | special |
| 12/29/2025 | Energy Code Compliance Inspections | — | progress |
| 12/29/2025 | HVAC-R and service water heating system controls | — | energy_progress |
| 12/29/2025 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 12/29/2025 | Maintenance information | — | energy_progress |
| 12/29/2025 | Post-installed Anchors | — | special |
| 12/29/2025 | Sprinkler Systems | — | special |
| 12/29/2025 | Standpipe Systems | — | special |
| 12/29/2025 | Fire-Resistant Penetrations and Joints | — | special |
| 12/29/2025 | Fire-Resistant Penetrations and Joints | SHAHRIAR QUAYYUM | special |
| 12/29/2025 | Heating Systems | SHAHRIAR QUAYYUM | special |
| 12/29/2025 | Mechanical Systems | SHAHRIAR QUAYYUM | special |
| 12/29/2025 | Energy Code Compliance Inspections | SHAHRIAR QUAYYUM | progress |