Condo, residential unit in elevator building
Andrew Jackson Condominium
35-20 LEVERICH STREET · Jackson Heights · BIN 4029273
💬 Discuss this project
1964Year Built
6Stories
R4Building Class
R7AZoning
170,708 sfGross Floor Area
214Units
LL97 CoveredRent Stabilized8 Active Violations 1 old, status unconfirmed ▸FISP: SAFE
Condo, residential unit in elevator building · Owner of record: Andrew Jackson Condo · 68,280 sf lot · 2.5 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingEquipmentGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
RoofFacade and garage roof repairs2p · 1 filing · 12 docs
Floor 6Gas riser and sprinkler system work7p · 1 filing · 12 docs
Floor 5Gas riser and sprinkler system work7p · 1 filing · 12 docs
Floor 4Unit A41212p · 2 filings · 20 docs
Floor 3Gas riser and sprinkler system work7p · 1 filing · 12 docs
Floor 2Unit B22111p · 3 filings · 20 docs
Floor 1Facade and garage roof repairs10p · 2 filings · 20 docs
CellarGas riser and sprinkler system work8p · 1 filing · 12 docs
Site & exteriorHeavy duty sidewalk shed installation8p · 2 filings · 14 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
David Associates103/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Kyu Lee Architect207/05/2023
Cowley Engineering205/12/2023
Sung Ho Shin Architect412/06/2022
Eric Foster107/24/2022
New York & Company310/14/2020
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Theresa Voltaggio203/21/2026
Rennon Construction103/21/2026
New York & Company603/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Veeva Construction JGeneral Contractor407/08/2026
MNR GroupGeneral Contractor307/08/2026
Rennon ConstructionScaffold207/08/2026
Budget Plumbing & HeatingPlumbing207/08/2026
AbileneGeneral Contractor103/21/2026
Everest ScaffoldingGeneral Contractor103/21/2026
North Coast PCS CommunicationGeneral Contractor103/21/2026
Skyline RestorationGeneral Contractor103/21/2026
Squan Construction ServicesGeneral Contractor103/21/2026
BMC PlumbingPlumbing103/21/2026
High Quality ElectricElectrical103/22/2026
Mes ConstructionPlumbing107/08/2026
P.L. Electrical ContractingElectrical103/22/2026
Cross State ConstructionGeneral Contractor108/02/2005
DM ContractingGeneral Contractor111/30/2017
Francisco SosaGeneral Contractor210/15/2018
Sasco Construction EnterprisesGeneral Contractor108/11/2016
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Kyu Lee Architect1978207/05/2023
Cowley Engineering186205/12/2023
New York Engineering Associates851310/14/2020
Building Lifecycle
02/20/2028
Facade inspection report due (FISP Cycle 9, sub-cycle B)
The filing window opened 02/21/2026. No Cycle 9 filing on record yet
09/17/2026
Boiler inspection report filed
Initial · no defects · Accepted
08/07/2026
Apartment 212 sold
06/09/2026
Apartment 226 sold
06/09/2026
Apartment A403 sold
300 history events on file for this building. Sign in free to see the full history. Sign in · Create account
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSidewalk ShedSigned-offRennon Construction08/30/2023
DOB NOWGeneral ConstructionSigned-offMNR Group07/10/2023
DOB NOWGeneral ConstructionSigned-offVeeva Construction J06/06/2023
DOB NOWGeneral ConstructionSigned-offVeeva Construction J12/13/2022
DOB NOWPlumbingSigned-offMes Construction12/07/2022
DOB NOWGeneral ConstructionSigned-offMNR Group07/27/2022
DOB NOWSidewalk ShedSigned-offRennon Construction07/25/2022
DOB NOWPlumbingSigned-offBudget Plumbing & Heating10/20/2020
DOB NOWPlumbingSigned-offBudget Plumbing & Heating10/17/2019
BISOTISSUEDVeeva Construction 211/26/2018
BISOTISSUEDFrancisco Sosa10/15/2018
BISOTISSUEDFrancisco Sosa10/04/2018
BISOTISSUEDVeeva Construction 205/01/2018
BISOTISSUEDDM Contracting11/30/2017
BISOTISSUEDSasco Construction Enterprises08/11/2016
BISOTISSUEDSquan Construction Services01/13/2016
BISPLISSUEDBell Fuel Oil03/25/2009
BISOTISSUEDAbilene03/25/2009
BISOTISSUEDSkyline Restoration04/05/2007
BISEQISSUEDEverest Scaffolding01/09/2007
BISEQISSUEDEverest Scaffolding07/28/2006
BISOTISSUEDSkyline Restoration07/26/2006
BISOTISSUEDCross State Construction08/02/2005
BISOTISSUEDNorth Coast PCS Communication04/03/2002
BISFSISSUEDManhattan Boiler & Equipment05/21/1999
6 projects · most recent 03/20/2024
General Wiring
FiledStatusContractorScope
03/20/2024CompleteQec Electrical SvceGeneral Wiring
06/20/2023CompleteP.L. Electrical ContractingGeneral Wiring
07/29/2022Permit IssuedHigh Quality Electric—
11/11/2021CompleteDemand Electric—
01/01/2020CompleteS.A.L. Electric—
01/30/2018Permit IssuedAll-Rite Electric Corp of NYGeneral Wiring
▾Field Inspections (DOB CAP) — 7
DateTypeResultReport
07/21/2023Pass-Final General Construction Non-Directive 14PassView ↗
06/21/2023Fail-Final General Construction Non-Directive 14FailView ↗
04/11/2023Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
03/20/2023Pass-Final General Construction Non-Directive 14PassView ↗
03/15/2023Fail-Final General Construction Non-Directive 14FailView ↗
03/10/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
03/07/2023Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 19
DateRequirementInspectorRole
07/19/2023Fire-Resistant Penetrations and JointsKyumyeon Leespecial
06/23/2023Fire-Resistant Penetrations and JointsKyumyeon Leespecial
05/15/2023Concrete - Cast-In-PlaceEric Cowleyspecial
05/15/2023Post-installed AnchorsEric Cowleyspecial
05/15/2023MasonryEric Cowleyspecial
05/15/2023Structural Stability – Alterations of existing buildingsEric Cowleyspecial
05/15/2023Sprayed fire-resistant materialsEric Cowleyspecial
05/15/2023FinalEric Cowleyprogress
05/15/2023Fire-Resistant Penetrations and JointsEric Cowleyspecial
04/27/2023FinalEric Cowleyprogress
04/27/2023Concrete - Cast-In-PlaceEric Cowleyspecial
04/27/2023Fire-Resistant Penetrations and JointsEric Cowleyspecial
04/27/2023MasonryEric Cowleyspecial
04/27/2023Post-installed AnchorsEric Cowleyspecial
04/27/2023Sprayed fire-resistant materialsEric Cowleyspecial
04/27/2023Structural Stability – Alterations of existing buildingsEric Cowleyspecial
10/15/2020Fire-Resistant Penetrations and JointsLOUIS ARENAspecial
09/14/2020Fire-Resistant Penetrations and JointsLOUIS ARENAspecial
03/11/2020Fire-Resistant Penetrations and JointsLOUIS ARENAspecial
137 filed documents on file for this building. Sign in free to see the full history. Sign in · Create account