| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 12/28/2016 | $1.1M | — | — → — | $570/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| HIRISE CONTRACTING GROUP, INC | 9 | 06/02/2026 |
| SQUARE ARCH, LLC | 2 | 09/08/2025 |
| TAN ARCHITECT P.C | 2 | 05/27/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| AMERILAND BROOK LLC | 16 | 03/21/2026 |
| AMERGY SOLAR | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| THC CONSTRUCTION INC | General Contractor | 21 | 07/08/2026 |
| STREAM ROCK CONTSRUCTION* | General Contractor | 2 | 04/09/2026 |
| AMERGY SOLAR INC | General Contractor | 1 | 07/08/2026 |
| WATSON'S PLBG, HTG, & BDG | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| HIRISE CONTRACTING GROUP, | 8228 | 3 | 06/02/2026 |
| SQ. ARCH, LLC | 4802 | 2 | 09/08/2025 |
| AMERILAND BROOK LLC | 1506 | 1 | 06/30/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Permit Issued | STREAM ROCK CONTSRUCTION* | 03/02/2026 |
| DOB NOW | Construction Fence | Signed-off | STREAM ROCK CONTSRUCTION* | 02/17/2026 |
| DOB NOW | Foundation | Permit Issued | THC CONSTRUCTION INC | 05/14/2025 |
| DOB NOW | Construction Fence | Signed-off | THC CONSTRUCTION INC | 05/14/2025 |
| DOB NOW | Solar | Signed-off | AMERGY SOLAR INC | 04/22/2025 |
| DOB NOW | Plumbing | Signed-off | WATSON'S PLBG, HTG, & BDG | 12/31/2024 |
| DOB NOW | General Construction | Permit Issued | THC CONSTRUCTION INC | 12/09/2024 |
| DOB NOW | Earth Work | Permit Issued | THC CONSTRUCTION INC | 12/09/2024 |
| DOB NOW | General Construction | Permit Issued | THC CONSTRUCTION INC | 12/09/2024 |
| DOB NOW | Foundation | Permit Issued | THC CONSTRUCTION INC | 12/09/2024 |
| DOB NOW | General Construction | Permit Issued | THC CONSTRUCTION INC | 12/09/2024 |
| DOB NOW | Support of Excavation | Signed-off | THC CONSTRUCTION INC | 12/06/2024 |
| DOB NOW | Construction Fence | Signed-off | THC CONSTRUCTION INC | 11/04/2024 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 06/02/2026 | Permit Issued | STREAM ROCK CONTSRUCTION* | Heating Systems | Heating Rheem PROPE50 M2 RH92 CS 48,000 BTU · Electric Heater ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/02/2024 | — | — | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/02/2026 | Signed-off | WATSON'S PLBG, HTG, & BDG | Storm, Water/Sanitary |
| 04/02/2024 | — | — | Plumbing-Sprinkler, Storm, Water/Sanitary |
| 05/27/2022 | — | — | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/16/2025 | Complete | I.P. ELECTRIC INC | — |
| 01/02/2025 | Complete | AL-LECTRIC ELECT'L CONTRG | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 04/10/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/08/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 04/29/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/25/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 03/28/2025 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 03/28/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 03/28/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/28/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 03/26/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/27/2026 | Fire-Resistant Penetrations and Joints | ROBERT ERVOLINA | special |
| 04/27/2026 | Chimneys and vents | ROBERT ERVOLINA | special |
| 04/27/2026 | Fenestration and door U-factor and product ratings | ROBERT ERVOLINA | energy_progress |
| 04/27/2026 | Duct leakage testing, insulation and design | ROBERT ERVOLINA | energy_progress |
| 04/27/2026 | Fenestration air leakage | ROBERT ERVOLINA | energy_progress |
| 04/27/2026 | Interior lighting power | ROBERT ERVOLINA | energy_progress |
| 04/27/2026 | Ventilation and air distribution system | ROBERT ERVOLINA | energy_progress |
| 04/27/2026 | Insulation placement and R values | ROBERT ERVOLINA | energy_progress |
| 04/27/2026 | Fenestration areas | ROBERT ERVOLINA | energy_progress |
| 04/27/2026 | Air barrier — testing | ROBERT ERVOLINA | energy_progress |
| 04/27/2026 | HVAC-R and service water piping design and insulation | ROBERT ERVOLINA | energy_progress |
| 04/27/2026 | Permanent certificate | ROBERT ERVOLINA | energy_progress |
| 04/27/2026 | Electric vehicle service equipment requirements | ROBERT ERVOLINA | energy_progress |
| 04/27/2026 | HVAC-R and service water heating system controls | ROBERT ERVOLINA | energy_progress |
| 04/27/2026 | Air barrier - visual inspection | ROBERT ERVOLINA | energy_progress |
| 04/27/2026 | Maintenance information | ROBERT ERVOLINA | energy_progress |
| 04/27/2026 | HVAC-R and service water heating equipment | ROBERT ERVOLINA | energy_progress |
| 04/27/2026 | Metering | ROBERT ERVOLINA | energy_progress |
| 04/27/2026 | Fire-Resistance Rated Construction | ROBERT ERVOLINA | progress |
| 04/27/2026 | Final | ROBERT ERVOLINA | progress |
| 04/27/2026 | Energy Code Compliance Inspections | ROBERT ERVOLINA | progress |
| 04/27/2026 | Structural Stability – Alterations of existing buildings | ROBERT ERVOLINA | special |
| 04/27/2026 | Mechanical Systems | ROBERT ERVOLINA | special |
| 04/27/2026 | Heating Systems | ROBERT ERVOLINA | special |
| 09/08/2025 | Energy Code Compliance Inspections | Chun Feng | progress |