| Owner | Filings | Most Recent |
|---|---|---|
| CONSTRUCTION SAFETY PRO | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 05/24/2023 | $980K | — | — → — | $311/sf building |
| 07/28/2022 | $950K | — | 35-46 100TH STREET REALTY LLC → ZY ENTITY LLC | $302/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| NA | 6 | 03/12/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| BUILD TEAM | 12 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| SAFETY PRO CONSTRUCTION | General Contractor | 3 | 03/21/2026 |
| AL-LECTRIC ELECT'L CONTRG | Electrical | 1 | 03/22/2026 |
| WATSON'S PLBG, HTG, & BDG | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| HSU & ASSOCIATES | 8025 | 3 | 12/14/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Foundation | Permit Issued | SAFETY PRO CONSTRUCTION | 10/24/2023 |
| DOB NOW | Plumbing | Signed-off | WATSON'S PLBG, HTG, & BDG | 10/20/2023 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/12/2024 | Signed-off | WATSON'S PLBG, HTG, & BDG | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/27/2023 | Complete | AL-LECTRIC ELECT'L CONTRG | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/12/2024 | Permit Issued | SAFETY PRO CONSTRUCTION | Masonry, Wood |
| Date | Type | Result | Report |
|---|---|---|---|
| 10/16/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 03/27/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/22/2024 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 03/15/2024 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 03/11/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 11/02/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/02/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 01/02/2024 | HVAC-R and service water piping design and insulation | Chih Hsu | energy_progress |
| 01/02/2024 | HVAC-R and service water heating equipment | Chih Hsu | energy_progress |
| 01/02/2024 | HVAC-R and service water heating system controls | Chih Hsu | energy_progress |
| 01/02/2024 | Permanent certificate | Chih Hsu | energy_progress |
| 01/02/2024 | Fire-Resistant Penetrations and Joints | Chih Hsu | special |
| 12/07/2023 | Fire-Resistant Penetrations and Joints | Chih Hsu | special |
| 12/07/2023 | Permanent certificate | Chih Hsu | energy_progress |
| 12/07/2023 | HVAC-R and service water heating system controls | Chih Hsu | energy_progress |
| 12/07/2023 | HVAC-R and service water piping design and insulation | Chih Hsu | energy_progress |
| 12/07/2023 | HVAC-R and service water heating equipment | Chih Hsu | energy_progress |
| 10/06/2023 | Insulation placement and R values | Chih Hsu | energy_progress |
| 10/06/2023 | Fenestration air leakage | Chih Hsu | energy_progress |
| 10/05/2023 | Metering | Chih Hsu | energy_progress |
| 09/09/2023 | Structural Stability – Alterations of existing buildings | — | special |
| 09/08/2023 | Structural Stability – Alterations of existing buildings | Chih Hsu | special |
| 09/08/2023 | Fire-Resistant Penetrations and Joints | Chih Hsu | special |
| 09/08/2023 | Final | Chih Hsu | progress |
| 09/08/2023 | Footing and Foundation | Chih Hsu | progress |
| 09/08/2023 | Energy Code Compliance Inspections | Chih Hsu | progress |
| 09/08/2023 | Fire-Resistance Rated Construction | Chih Hsu | progress |
| 09/08/2023 | Structural Wood Frame | Chih Hsu | progress |
| 09/08/2023 | Concrete - Cast-In-Place | Chih Hsu | special |
| 09/08/2023 | Masonry | Chih Hsu | special |
| 09/08/2023 | Fenestration and door U-factor and product ratings | Chih Hsu | energy_progress |
| 09/08/2023 | HVAC-R and service water heating equipment | — | energy_progress |