| Owner | Filings | Most Recent |
|---|---|---|
| EDWARD J MINSKOFF EQUITIES | 112 | 07/08/2026 |
| SKYLINE SCAFFOLDING GROUP | 28 | 07/08/2026 |
| TRI BOROUGH SCAFFOLDING | 4 | 07/08/2026 |
| SCIAME CONSTRUCTION | 1 | 03/22/2026 |
| REPUBLIC EXTERIOR SERVICES | 2 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 03/23/2020 | $61.5M | — | PAF FERRY LLC → JAY STREET OFFICE LLC | — not available |
| 03/23/2020 | $61.5M | — | PAF FERRY LLC → JAY STREET OFFICE LLC | — not available |
| 03/23/2020 | $61.5M | — | PAF FERRY LLC → JAY STREET OFFICE LLC | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| SYNC ARCHITECTURE P.C | 1 | 05/01/2026 |
| YSRAEL A. SEINUK, P.C. | 4 | 07/18/2024 |
| WSP | 14 | 06/11/2024 |
| PCS ENGINEERING | 1 | 12/07/2023 |
| URBAN INTEGRATIONS | 2 | 09/22/2023 |
| URBAN FOUNDATION/ENGINEERING | 4 | 05/02/2023 |
| PLAN B ENGINEERING | 6 | 02/09/2023 |
| PAUL PERDEK, PROF. ENG. PLLC | 4 | 01/05/2023 |
| LOMBARDO PROFESSIONAL ENGINEERING | 2 | 09/28/2022 |
| WAVIC ENGINEERING PLLC | 2 | 08/02/2021 |
| PHILIP HABIB & ASSOCIATES | 1 | 05/18/2021 |
| FL&M ENGINEERING DESIGN &INSPECTION | 1 | 11/10/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| JAM CONSULTANTS, INC. | 46 | 03/21/2026 |
| GRS CONSULTING SERVICES | 4 | 03/21/2026 |
| A1 EXPEDITING SERVICE | 20 | 03/21/2026 |
| GREEN STUDIO | 2 | 03/21/2026 |
| RIGGING CONSULTANTS | 2 | 03/21/2026 |
| Rigid Structural Design, LLC | 2 | 03/21/2026 |
| LOMBARDO PROFESSIONAL ENGINEERING | 1 | 03/21/2026 |
| LOMBARDO BUILDING CONSULTANTS | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| SKYLINE SCAFFOLDING GROUP | General Contractor | 41 | 07/08/2026 |
| SCIAME CONSTRUCTION LLC | General Contractor | 15 | 07/08/2026 |
| KG SPRINKLER CORP | Fire Protection | 8 | 07/08/2026 |
| URBAN FOUNDATION ENGINEERING | General Contractor | 7 | 07/08/2026 |
| ARCON PLBG SOLUTIONS | Plumbing | 2 | 07/08/2026 |
| BREEZE NATIONAL INC | General Contractor | 2 | 07/08/2026 |
| FSG ELECTRIC INC | Electrical | 1 | 03/22/2026 |
| PROSTAR PLUMBING AND HEAT | Plumbing | 1 | 07/08/2026 |
| V. VASS ELECTRIC CORP | Electrical | 1 | 03/22/2026 |
| FSG ELECTRIC INC 004420 | General Contractor | 1 | 03/22/2026 |
| NEW ROC CONTRACTING CORP | General Contractor | 1 | 07/08/2026 |
| TRI BOROUGH SCAFFOLDING | General Contractor | 1 | 07/08/2026 |
| DONATO PLUMBING, INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| COLE TECHNOLOGIES/CONTROL | 1290 | 8 | 07/18/2024 |
| SOCOTEC, INC. | 301 | 2 | 07/18/2024 |
| YSRAEL A SEINUK, PC | 8473 | 3 | 07/18/2024 |
| SYNERGY ENGINEERING | 784 | 13 | 06/11/2024 |
| PCS ENGINEERING | 3745 | 1 | 12/07/2023 |
| MUESER RUTLEDGE CONSULTIN | 977 | 3 | 05/02/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sprinklers | Signed-off | H M SPRINKLER INC | 06/07/2024 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | SKYLINE SCAFFOLDING GROUP | 05/10/2024 |
| DOB NOW | Construction Fence | Signed-off | SKYLINE SCAFFOLDING GROUP | 05/10/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | SKYLINE SCAFFOLDING GROUP | 05/10/2024 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | SKYLINE SCAFFOLDING GROUP | 05/10/2024 |
| DOB NOW | Mechanical Systems | Signed-off | SCIAME CONSTRUCTION LLC | 05/01/2024 |
| DOB NOW | Boiler Equipment | Signed-off | CHAMPION COMBUSTION CORP | 04/02/2024 |
| DOB NOW | Plumbing | Signed-off | DONATO PLUMBING, INC | 03/22/2024 |
| DOB NOW | Structural | Permit Issued | SCIAME CONSTRUCTION LLC | 01/19/2024 |
| DOB NOW | Boiler Equipment | Signed-off | CHAMPION COMBUSTION CORP | 01/16/2024 |
| DOB NOW | Suspended Scaffold | Permit Issued | UNITED REST. AND DEV. COR | 01/10/2024 |
| DOB NOW | Suspended Scaffold | Permit Issued | NEW ROC CONTRACTING CORP | 12/18/2023 |
| DOB NOW | Boiler Equipment | Signed-off | PROSTAR PLUMBING AND HEAT | 12/14/2023 |
| DOB NOW | Support of Excavation | Signed-off | SCIAME CONSTRUCTION LLC | 12/04/2023 |
| DOB NOW | Curb Cut | Permit Issued | SCIAME CONSTRUCTION LLC | 11/24/2023 |
| DOB NOW | Mechanical Systems | Signed-off | SCIAME CONSTRUCTION LLC | 11/16/2023 |
| DOB NOW | Plumbing | Signed-off | ARCON PLBG SOLUTIONS | 10/05/2023 |
| DOB NOW | Standpipe | Signed-off | H M SPRINKLER INC | 06/06/2023 |
| DOB NOW | Sprinklers | Signed-off | H M SPRINKLER INC | 06/06/2023 |
| DOB NOW | Standpipe | Signed-off | H M SPRINKLER INC | 06/02/2023 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | SKYLINE SCAFFOLDING GROUP | 05/15/2023 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | SKYLINE SCAFFOLDING GROUP | 05/15/2023 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | SKYLINE SCAFFOLDING GROUP | 05/13/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | SKYLINE SCAFFOLDING GROUP | 05/12/2023 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | SKYLINE SCAFFOLDING GROUP | 05/12/2023 |
| DOB NOW | Construction Fence | Signed-off | SKYLINE SCAFFOLDING GROUP | 05/12/2023 |
| DOB NOW | Mechanical Systems | Signed-off | SCIAME CONSTRUCTION LLC | 04/24/2023 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | SKYLINE SCAFFOLDING GROUP | 04/03/2023 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | SKYLINE SCAFFOLDING GROUP | 02/17/2023 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | SKYLINE SCAFFOLDING GROUP | 01/11/2023 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | SKYLINE SCAFFOLDING GROUP | 01/06/2023 |
| DOB NOW | Construction Fence | Signed-off | SKYLINE SCAFFOLDING GROUP | 10/29/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | SKYLINE SCAFFOLDING GROUP | 10/25/2022 |
| DOB NOW | Plumbing | Signed-off | ARCON PLBG SOLUTIONS | 10/07/2022 |
| DOB NOW | Sprinklers | Signed-off | H M SPRINKLER INC | 10/05/2022 |
| DOB NOW | Standpipe | Signed-off | H M SPRINKLER INC | 10/05/2022 |
| DOB NOW | Support of Excavation | Signed-off | SCIAME CONSTRUCTION LLC | 09/28/2022 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | SCIAME CONSTRUCTION LLC | 09/28/2022 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | SCIAME CONSTRUCTION LLC | 09/16/2022 |
| DOB NOW | Standpipe | Signed-off | H M SPRINKLER INC | 09/16/2022 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/29/2024 | Signed-off | KG SPRINKLER CORP | 1,866 heads, 26 outlets |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/06/2025 | Complete | FSG ELECTRIC INC | General Wiring |
| 08/31/2022 | Complete | TOP SHELF ELECTRIC CORP | — |
| 05/23/2022 | Permit Issued | TRANSEL ELEV. & ELEC. INC | General Wiring |
| 11/19/2021 | Complete | FSG ELECTRIC INC | — |
| 10/08/2020 | Complete | V. VASS ELECTRIC CORP | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/18/2024 | Permit Issued | SCIAME CONSTRUCTION LLC | Concrete |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/07/2023 | Permit Issued | UNITED REST. AND DEV. COR | Suspended Scaffold (SC) |
| Date | Type | Result | Report |
|---|---|---|---|
| 06/24/2024 | Pass-Final SD - Fire Pump | Pass | View ↗ |
| 06/07/2024 | Certified Sprinkler-Dry Pipe Valve (SP)-Dry Pipe Valve Test | Certified | View ↗ |
| 06/07/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 06/05/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 05/16/2024 | Pass-Final SD - Fire Pump | Pass | View ↗ |
| 05/08/2024 | Pass-Final SD - Fire Pump | Pass | View ↗ |
| 04/30/2024 | Certified StandPipe-SD-Piping-Hydrostatic Test | Certified | View ↗ |
| 04/09/2024 | Pass-Final Boiler Equipment Inspection | Pass | View ↗ |
| 02/12/2024 | Pass-Final Boiler Equipment Inspection | Pass | View ↗ |
| 09/29/2023 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 08/02/2023 | Pass-Final PL - More than 10 Requested Floors | Pass | View ↗ |
| 05/12/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 02/09/2023 | Certified StandPipe - SD - Alarm Sys 64/09 - Finish | Certified | View ↗ |
| 02/09/2023 | Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet) | Certified | View ↗ |
| 12/15/2022 | Pass-Final PL - Underground | Pass | View ↗ |
| 10/24/2022 | Pass-Final PL - Underground | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/06/2024 | Structural Steel - Details | GEORGE ANDERSEN | special |
| 08/06/2024 | Concrete - Cast-In-Place | Damian Monteiro | special |
| 08/06/2024 | Fire-Resistant Penetrations and Joints | GEORGE ANDERSEN | special |
| 08/06/2024 | Masonry | GEORGE ANDERSEN | special |
| 08/06/2024 | Final | Damian Monteiro | progress |
| 08/06/2024 | Structural Steel - Welding | GEORGE ANDERSEN | special |
| 08/06/2024 | Wall Panels, Curtain Walls, and Veneers | Jennifer Sze | special |
| 06/26/2024 | Concrete - Cast-In-Place | Damian Monteiro | special |
| 06/26/2024 | Final | Damian Monteiro | progress |
| 06/26/2024 | Wall Panels, Curtain Walls, and Veneers | Jennifer Sze | special |
| 06/26/2024 | Structural Steel - Welding | GEORGE ANDERSEN | special |
| 06/26/2024 | Structural Steel - Details | GEORGE ANDERSEN | special |
| 06/26/2024 | Masonry | GEORGE ANDERSEN | special |
| 06/26/2024 | Fire-Resistant Penetrations and Joints | GEORGE ANDERSEN | special |
| 06/11/2024 | HVAC and service water heating equipment | Alec Strongin | energy_progress |
| 06/11/2024 | Shutoff dampers | Alec Strongin | energy_progress |
| 06/11/2024 | HVAC insulation and sealing | Alec Strongin | energy_progress |
| 06/11/2024 | Duct leakage testing | Alec Strongin | energy_progress |
| 06/11/2024 | Final | GARY POMERANTZ | progress |
| 06/11/2024 | Mechanical Systems | Alec Strongin | special |
| 06/11/2024 | Smoke Control Systems Testing | Alec Strongin | special |
| 06/11/2024 | Electrical motors | Alec Strongin | energy_progress |
| 06/11/2024 | HVAC and service water heating system controls | Alec Strongin | energy_progress |
| 06/11/2024 | Maintenance information | Alec Strongin | energy_progress |
| 06/04/2024 | Fire-Resistant Penetrations and Joints | GEORGE ANDERSEN | special |