← Back
BuildNYC
One family attached or semi-detached
35 KEEN COURT
BROOKLYN · BIN 3426637
💬 Discuss this project
2023Year Built
2Stories
A5Building Class
R4-1Zoning
1,225 sfGross Floor Area
1Units
0 Active ViolationsFDNY Report ↗
One family attached or semi-detached · Owner of record: 35 Keen CT · 1,665 sf lot · 0.74 FAR built · Flood zone AE
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire ProtectionCivilGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Roof11p · 1 filing · 20 docs
Floor 286p · 1 filing · 20 docs
Floor 1124p · 1 filing · 20 docs
Cellar94p · 1 filing · 20 docs
Site & exteriorConstruction fence project2p · 1 filing · 2 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
10/30/2025$900K—35 KEEN CT LLC → Private party$735/sf unit
09/10/2021$360K—Private party → 35 KEEN CT LLC$294/sf unit
10/16/2014$150K—35 KEEN COURT CORP. → Private party$122/sf unit
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Citiscape Consulting1601/12/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Citiscape Consulting3203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
G-NadoGeneral Contractor707/08/2026
NadkosGeneral Contractor403/22/2026
G-NadoScaffold403/21/2026
Jacobs DevelopmentScaffold107/08/2026
AmokFire Protection107/08/2026
AmokPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Zarina Kindo, RA49001401/12/2026
A&B World Consulting5704107/24/2023
Building Lifecycle
03/13/2026
Signed off — New Building
B00735236-I1
02/13/2026
Special inspection requirement — Masonry
ZARINA KINDO
02/13/2026
Special inspection requirement — Fenestration air leakage
ZARINA KINDO
02/13/2026
Special inspection requirement — Subgrade Inspections
ZARINA KINDO
02/13/2026
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
ZARINA KINDO
79 history events on file for this building. Sign in free to see the full history. Sign in · Create account
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWCurb CutSigned-offNadkos03/21/2025
DOB NOWGeneral ConstructionPermit IssuedG-Nado10/09/2024
DOB NOWConstruction FenceSigned-offG-Nado09/26/2024
DOB NOWPlumbingSigned-offAmok12/06/2023
DOB NOWSprinklersSigned-offAmok12/06/2023
DOB NOWGeneral ConstructionPermit IssuedG-Nado10/27/2023
DOB NOWFoundationSigned-offG-Nado10/10/2023
DOB NOWStructuralSigned-offG-Nado09/22/2023
DOB NOWConstruction FenceSigned-offG-Nado09/12/2023
DOB NOWConstruction FenceSigned-offJacobs Development12/22/2020
BIS—ISSUEDJacobs Development01/08/2021
BIS—ISSUEDJacobs Development01/07/2021
2 projects · most recent 11/06/2024
General Wiring
FiledStatusContractorScope
11/06/2024CompleteA.L. ElectricalGeneral Wiring
05/13/2024CompleteA.L. ElectricalGeneral Wiring
▾Field Inspections (DOB CAP) — 10
DateTypeResultReport
06/03/2025Pass-Final Curb Cut Non-Directive 14PassView ↗
04/08/2025Fail-Final Curb Cut Non-Directive 14FailView ↗
03/21/2025Pass-Final CND-Occupancy InspectionPassView ↗
11/08/2024Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
11/06/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
06/05/2024Certified Storm Drainage-ST-Piping-RoughingCertifiedView ↗
06/05/2024Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
06/05/2024Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
02/02/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
02/02/2024Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 116
DateRequirementInspectorRole
02/13/2026PreliminaryZARINA KINDOprogress
02/13/2026MasonryZARINA KINDOspecial
02/13/2026Concrete - Cast-In-PlaceZARINA KINDOspecial
02/13/2026Subgrade InspectionsZARINA KINDOspecial
02/13/2026Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationZARINA KINDOspecial
02/13/2026Fire-Resistant Penetrations and JointsZARINA KINDOspecial
02/13/2026Excavations - Sheeting, Shoring, and BracingZARINA KINDOspecial
02/13/2026Exterior Insulation and Finish Systems (EIFS)ZARINA KINDOspecial
02/13/2026UnderpinningZARINA KINDOspecial
02/13/2026Lowest Floor ElevationZARINA KINDOprogress
02/13/2026Energy Code Compliance InspectionsZARINA KINDOprogress
02/13/2026Fire-Resistance Rated ConstructionZARINA KINDOprogress
02/13/2026Fenestration air leakageZARINA KINDOenergy_progress
02/13/2026Fenestration and door U-factor and product ratingsZARINA KINDOenergy_progress
02/13/2026Fenestration areasZARINA KINDOenergy_progress
02/13/2026Air barrier — testing ZARINA KINDOenergy_progress
02/13/2026Protection of exposed foundation insulationZARINA KINDOenergy_progress
02/13/2026MeteringZARINA KINDOenergy_progress
02/13/2026Maintenance informationZARINA KINDOenergy_progress
02/13/2026Interior lighting powerZARINA KINDOenergy_progress
02/13/2026Electric vehicle service equipment requirementsZARINA KINDOenergy_progress
02/13/2026Air barrier - visual inspectionZARINA KINDOenergy_progress
02/13/2026Insulation placement and R valuesZARINA KINDOenergy_progress
02/13/2026Permanent certificateZARINA KINDOenergy_progress
06/24/2025Subgrade InspectionsZARINA KINDOspecial
Latest 25 of 116.
221 filed documents on file for this building. Sign in free to see the full history. Sign in · Create account