| Owner | Filings | Most Recent |
|---|---|---|
| AMAZON | 13 | 07/08/2026 |
| NORTH 12TH ASSOCIATES LLC | 1 | 03/22/2026 |
| G4 CAPITAL PARTNERS | 16 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| W.E. III ENGINEERS, PLLC | 4 | 11/20/2025 |
| INTERIOR ARCHITECTS | 2 | 11/20/2025 |
| GILSANZ MURRAY STEFICEK LLP | 1 | 02/28/2024 |
| CCPE | 1 | 02/21/2024 |
| TULLER/MCNEALUS/FELD | 1 | 06/15/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| MUNICIPAL BUILDING CONSULTANTS | 1 | 03/21/2026 |
| A1 EXPEDITING SERVICE CORP. | 8 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| L&K PARTNERS, INC | General Contractor | 8 | 04/09/2026 |
| POLO ELECTRIC CORP. D/B/A | Electrical | 1 | 03/22/2026 |
| PSI PARTNERS, LLC | Fire Protection | 1 | 07/08/2026 |
| MAC FELDER INC | Plumbing | 1 | 07/08/2026 |
| PAR PLUMBING CO., INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| MILROSE CONSULTANTS LLC | 2003 | 4 | 11/20/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | PAR PLUMBING CO., INC | 11/25/2025 |
| DOB NOW | General Construction | Signed-off | L&K PARTNERS, INC | 11/25/2025 |
| DOB NOW | Mechanical Systems | Signed-off | L&K PARTNERS, INC | 11/25/2025 |
| DOB NOW | Plumbing | Signed-off | MAC FELDER INC | 05/01/2024 |
| DOB NOW | Sprinklers | Signed-off | MORA FIRE PROTECTION LLC | 04/19/2024 |
| DOB NOW | Structural | Signed-off | L&K PARTNERS, INC | 03/01/2024 |
| DOB NOW | Mechanical Systems | Signed-off | L&K PARTNERS, INC | 02/29/2024 |
| DOB NOW | General Construction | Signed-off | L&K PARTNERS, INC | 02/20/2024 |
| BIS | MH | ISSUED | AMAZON.COM | 05/30/2017 |
| BIS | SP | ISSUED | DEPENDABLE MECHANICAL COR | 06/14/2013 |
| BIS | OT | ISSUED | LET ME BUILD, LLC | 05/16/2013 |
| BIS | PL | ISSUED | A&H EXPRESS PLBG&HTG CORP | 04/30/2013 |
| BIS | — | ISSUED | LET ME BUILD, LLC | 04/18/2013 |
| BIS | EQ | ISSUED | LET ME BUILD, LLC | 03/22/2013 |
| BIS | EQ | ISSUED | LET ME BUILD, LLC | 02/14/2013 |
| BIS | MH | ISSUED | TM MECH CORP | 06/22/2006 |
| BIS | PL | ISSUED | GJ PLUMBING LLC | 06/22/2006 |
| BIS | FS | ISSUED | M.A.N. MECHANICAL CORP | 04/17/2000 |
| BIS | PL | RE-ISSUED | GJ PLUMBING LLC | 03/27/2000 |
| BIS | OT | ISSUED | TM MECH CORP | 03/27/2000 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/11/2025 | Permit Issued | POLO ELECTRIC CORP. D/B/A | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 12/29/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 12/05/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/12/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 08/12/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/06/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 07/16/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 07/10/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 10/08/2025 | Final | Stephen Furnstahl | progress |
| 02/07/2024 | Concrete - Cast-In-Place | Christopher Drutjons | special |
| 02/07/2024 | Post-installed Anchors | Christopher Drutjons | special |
| 01/17/2024 | Mechanical Systems | Christopher Drutjons | special |
| 01/17/2024 | Final | Christopher Drutjons | progress |
| 01/17/2024 | Sprinkler Systems | Christopher Drutjons | special |
| 01/17/2024 | Final | Christopher Drutjons | progress |