| Owner | Filings | Most Recent |
|---|---|---|
| ARLIA 35 W. 75TH STREET REALTY | 1 | 03/22/2026 |
| ARILA 35 WEST 75TH STREET REALTY LLC | 1 | 03/22/2026 |
| ARLIA 35 WEST 75TH STREET REALTY | 2 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| GREGG ROTHSTEIN ARCHITECT | 4 | 07/06/2023 |
| BAILEYS ENGINEERING PC | 2 | 07/05/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| AE DESIGN SOLUTION | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| EVEREST SCAFFOLDING INC | General Contractor | 5 | 07/08/2026 |
| COD PLUMBING CORP | Plumbing | 2 | 07/08/2026 |
| AJF ELECTRIC INC. | Electrical | 1 | 03/22/2026 |
| JOHN & JOSEPH BONANNO CON | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| GREGG ROTHSTEIN ARCHITECT | 195 | 2 | 07/06/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | VIN-RAY PLUMBING & HEATIN | 02/09/2023 |
| DOB NOW | Plumbing | Signed-off | VIN-RAY PLUMBING & HEATIN | 11/14/2022 |
| DOB NOW | General Construction | Signed-off | JOHN & JOSEPH BONANNO CON | 10/26/2022 |
| DOB NOW | Supported Scaffold | Signed-off | EVEREST SCAFFOLDING INC | 07/26/2018 |
| DOB NOW | Sidewalk Shed | Signed-off | EVEREST SCAFFOLDING INC | 07/26/2018 |
| DOB NOW | Sidewalk Shed | Signed-off | EVEREST SCAFFOLDING INC | 07/06/2018 |
| DOB NOW | Supported Scaffold | Signed-off | EVEREST SCAFFOLDING INC | 07/06/2018 |
| BIS | OT | ISSUED | JOHN & JOSEPH BONANNO CON | 10/08/2019 |
| BIS | PL | ISSUED | COD PLUMBING CORP | 06/13/2019 |
| BIS | MH | ISSUED | JOHN & JOSEPH BONANNO CON | 06/06/2019 |
| BIS | OT | ISSUED | JOHN & JOSEPH BONANNO CON | 11/03/2017 |
| BIS | MH | ISSUED | JOHN & JOSEPH BONANNO CON | 05/16/2017 |
| BIS | PL | ISSUED | COD PLUMBING CORP | 05/16/2017 |
| BIS | PL | ISSUED | VINRAY PLMB. & HTNG INC | 11/21/1995 |
| BIS | OT | ISSUED | BRUSCO CONTACTING CORP. | 11/01/1995 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/07/2023 | Complete | AJF ELECTRIC INC. | General Wiring |
| 08/30/2019 | Complete | AJF ELECTRIC INC. | General Wiring |
| 06/04/2018 | Complete | BOROWIDE ELECT'L CONTR'S | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/07/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/05/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/27/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/15/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 12/23/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/06/2023 | Fire-Resistant Penetrations and Joints | Gregg Rothstein | special |
| 07/06/2023 | Final | Gregg Rothstein | progress |
| 07/05/2023 | Fire-Resistant Penetrations and Joints | Gregg Rothstein | special |
| 07/05/2023 | Final | Gregg Rothstein | progress |
| 06/04/2018 | Final | PAUL BAILEY | progress |