← Back
Elevator apt, luxury type
The Lucerne
350 EAST 79 STREET · Upper East Side-Lenox Hill-Roosevelt Island · BIN 1045256
💬 Discuss this project
1989Year Built
44Stories
D8Building Class
R10AZoning
364,690 sfGross Floor Area
240Units
LL97 CoveredRent Stabilized2 Open Violations ▸FISP: SWARMP
Elevator apt, luxury type · Owner of record: 79TH REALTY LLC · 21,649 sf lot · 16.85 FAR built · Flood zone X
Locations of Work
ArchitectureMechanical
Roof1p · 1 filing · 3 docs
Floor 14p · 1 filing · 3 docs
Cellar4p · 1 filing · 3 docs
Sub-Cellar4p · 1 filing · 3 docs
Site & exterior1p · 1 filing · 3 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
79 TH ST REAILTY2403/21/2026
GLENNWOOD MANAGEMENT1307/08/2026
VALENTINA ENTERPRISE407/08/2026
CRESCENT HOLDING403/21/2026
79TH ST303/21/2026
E 79 ST REALTY CORP203/21/2026
CRESCENT HOLDING CORP MEMBER203/21/2026
79TH REALTY203/21/2026
NATIONAL CORP103/21/2026
LUCERNE103/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
THE ORDERING FORCE105/28/2025
BKH ARCHITECT, PLLC108/18/2021
SALVATOR A. CARADONNA JR.109/12/2018
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
AM PROFESSIONALS103/21/2026
ALL IN PERMIT CONSULTANTS103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
RAMDATHSINGH, PURANElectrical303/21/2026
SCHNABOLK, CHARLESElectrical303/21/2026
KOPP ELECTRIC CORPElectrical203/22/2026
LCS RESTORATION CORPGeneral Contractor104/09/2026
UNIQUE MECHANICAL CORPGeneral Contractor107/08/2026
GUSTAVE DILEO, JR.Electrical103/21/2026
NATIONAL MAINTENANCEScaffold107/08/2026
RICHARD GRIMAElectrical103/21/2026
RICHARD MILLWATERElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
THE ORDERING FORCE9406105/28/2025
BKH ARCHITECT, PLLC6255108/18/2021
Building Lifecycle
All (80)Filed (3)Permit Issued (3)Signed Off (1)Facade (FISP) (12)Violation (60)Special Inspection (1)
06/11/2025
Permit issued — General Construction
M01215471-I1-GC
05/28/2025
Filed — Alteration
LIMITIED GARAGE REPAIRS. NO CHANGE TO EGRESS, USE, OR OCCUPANCY
M01215471-I1
11/19/2024
Violation issued (ECB, closed)
Construction
08/18/2023
Cycle 9 facade report signed — SWARMP
05/25/2023
Cycle 9 facade report submitted
05/09/2023
Cycle 9 facade inspection completed
09/20/2021
Signed off — Alteration
DIRECT REPLACE (2) AIR CONDITIONERS FOR COOLING OF THE 1st FLOOR STORE - AGATA & VALENTINA FOODS
M00555313-I1
08/23/2021
Permit issued — Mechanical Systems
M00555313-I1-MS
08/18/2021
Filed — Alteration
DIRECT REPLACE (2) AIR CONDITIONERS FOR COOLING OF THE 1st FLOOR STORE - AGATA & VALENTINA FOODS
M00555313-I1
04/30/2019
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
02/22/2019
Cycle 8 facade report submitted
02/21/2019
Cycle 8 facade inspection completed
02/14/2019
Cycle 8 facade report signed — SAFE
09/13/2018
Permit issued — Sign
M00069188-I1-SG
09/12/2018
Filed — Alteration
M00069188-I1
09/10/2018
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
08/08/2018
Special inspection requirement — Final
SALVATOR CARADONNA
11/14/2016
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
11/14/2016
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
11/14/2016
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
11/14/2016
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
09/08/2014
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
12/19/2013
Violation issued (ECB, closed)
Unknown
08/06/2013
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
02/08/2013
Cycle 7 facade report submitted
02/08/2013
Cycle 7 facade report signed — SAFE
01/15/2013
Cycle 7 facade inspection completed
08/11/2011
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
08/11/2011
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
08/11/2011
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
08/11/2011
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
08/11/2011
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
09/17/2010
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
09/17/2010
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
09/17/2010
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
09/17/2010
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
09/17/2010
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
07/09/2010
Violation issued (ECB, closed)
Construction
11/04/2009
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
11/04/2009
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
11/04/2009
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
11/04/2009
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
11/04/2009
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
09/18/2009
Violation issued (ECB, closed)
Boilers
03/27/2009
Violation issued (ECB, closed)
Local Law
07/15/2008
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
07/15/2008
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
07/15/2008
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
05/16/2008
Violation issued (ECB, closed)
Elevators
03/21/2008
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
03/21/2008
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
12/27/2007
Violation issued (ECB, closed)
Construction
11/30/2007
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
08/14/2007
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
08/14/2007
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
08/14/2007
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
08/14/2007
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
08/14/2007
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
04/02/2007
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
04/02/2007
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
Latest 60 of 80 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedLCS RESTORATION CORP06/11/2025
DOB NOWMechanical SystemsSigned-offUNIQUE MECHANICAL CORP08/23/2021
DOB NOWSignPermit IssuedNATIONAL MAINTENANCE, INC09/13/2018
BISMHISSUEDAFGO MECHANICAL SVCS INC04/10/2019
BISMHISSUEDAFGO MECHANICAL SVCS INC04/08/2019
BISPLISSUEDSEAN COAKLEY P & H INC03/17/2017
BISPLISSUEDCOPPER PLUMBING INC06/23/2016
BISMHISSUEDRAC MECHANICAL INC05/20/2015
BISOTISSUEDYORK RESTORATION CORP03/14/2014
BISEQISSUEDSPRING SCAFFOLDING LLC12/23/2013
BISOTISSUEDYORK RESTORATION CORP05/10/2013
BISOTISSUEDYORK RESTORATION CORP04/19/2013
BISEQISSUEDSPRING SCAFFOLDING LLC04/18/2013
BISPLISSUEDCOPPER PLUMBING INC12/16/2011
BISOTISSUEDATLANTIC CONTRACTING SVC11/21/2011
BISEQISSUEDOUTDOOR INSTALLATIONS LLC04/28/2011
BISFBISSUEDRICHARD MORTMAN03/11/2011
BISPLISSUEDNAT'L MECH. SVCS PLBG LLC03/09/2011
BISMHISSUEDG.A.M.C.N.Y. LLC02/02/2010
BISOTISSUEDCPM BUILDERS INC08/20/2009
BISOTISSUEDYORK RESTORATION CORP12/01/2007
BISEQISSUEDOUTDOOR INSTALLATIONS LLC.09/06/2007
BISOTISSUEDYORK RESTORATION CORP08/23/2007
BISEQISSUEDOUTDOOR INSTALLATIONS LLC08/20/2007
BISPLISSUEDSAFETY PLMBG & HTG LLC04/28/2006
BISOTISSUEDGLOWER DESIGNS & CONSTRUCTION08/02/2005
BISSPISSUEDTMS PLUMBING & HTG CORP04/21/2005
BISPLISSUEDSAFETY PLMBG & HTG LLC03/28/2005
BISOTISSUEDGLOWER DESIGNS & CONSTRUCTION03/03/2005
BISOTISSUEDGLOWER DESIGNS & CONSTRUCTION04/28/2004
BISMHISSUEDAFGO MECHANICAL SVCS INC03/19/2001
BISMHISSUED79TH_REALTY_CO.11/15/1999
BISFPISSUEDIDEAL FIRE CONTROL07/15/1999
BISPLISSUEDHADERA PLMB & HTNG CORP02/20/1998
BISOTISSUEDBRONX STORE EQUIPMENT CO.,INC.01/16/1998
BISMHISSUEDBRONX STORE EQUIPMENT CO.,INC.01/16/1998
BIS—ISSUED79TH REALTY CO08/05/1997
BISPLISSUEDACTION JACK PLUMBING11/19/1993
BISMHISSUEDBRONX STORE EQUIPMENT CO.,INC.07/21/1993
BISPLISSUEDM&J PLG & MECH CORP03/19/1993
+ 7 more permits on file
3 projects · most recent 11/28/2025
General Wiring
FiledStatusContractorScope
11/28/2025CompleteKOPP ELECTRIC CORPGeneral Wiring
10/16/2024Permit IssuedHYLAN DATACOM & ELECL LLC2 meters, 1 new_meters
04/21/2023CompleteRIGID ELECTRIC, INC.General Wiring
▾Special Inspection Requirements (DOB NOW) — 1
DateRequirementInspectorRole
08/08/2018FinalSALVATOR CARADONNAprogress
▾Documents — 239 on file (BIS + DOB NOW)
▸Plans & Drawings3
▸DOB NOWPlans/Sketch3
09/06/2026M00069188-I1Request digital key ↗
09/03/2026M00555313-I1Request digital key ↗
08/23/2026M01215471-I1Request digital key ↗
▸Applications & Permits48
▸BISWORK PERMIT APPLICATION24
08/07/2019123047078Open ↗
05/14/2019140831063Open ↗
04/04/2019140831063Open ↗
Showing 3 of 24 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION22
07/10/2019123047078Open ↗
06/27/2019123047078Open ↗
06/18/2019123047078Open ↗
Showing 3 of 22 on file for this type
▸BISNon-Directive 14 Construction Sign Off Including Sign Applications2
07/14/2014140070973Open ↗
10/08/2011120673949Open ↗
▸Seals & Professional Certifications48
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION19
12/04/2019140830616Open ↗
07/18/2019140831063Open ↗
08/15/2016120849074Open ↗
Showing 3 of 19 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST9
03/20/2017123047078Open ↗
06/25/2015122365500Open ↗
04/27/2015122365500Open ↗
Showing 3 of 9 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT5
04/04/2019140831063Open ↗
04/04/2019140830616Open ↗
03/20/2017123047078Open ↗
Showing 3 of 5 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM5
05/04/2011120673949Open ↗
03/14/2011120604729Open ↗
Showing 2 of 5 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY3
04/04/2019140831063Open ↗
04/04/2019140830616Open ↗
04/17/2013140070973Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION3
04/04/2019140831063Open ↗
04/04/2019140830616Open ↗
04/17/2013140070973Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature3
08/13/2026M00069188-I1Open ↗
08/13/2026M01215471-I1Open ↗
08/13/2026M00555313-I1Open ↗
▸DOB NOWProgress Inspector Seal & Signature1
08/22/2026M00069188-I1Open ↗
▸Trade Schedules & Equipment29
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE7
07/10/2019123047078Open ↗
06/27/2019123047078Open ↗
06/18/2019123047078Open ↗
Showing 3 of 7 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT7
12/04/2019140830616Open ↗
12/04/2019140830616Open ↗
07/16/2019140831063Open ↗
Showing 3 of 7 on file for this type
▸BISEQUIPMENT USE PERMITS5
07/16/2019140831063Open ↗
12/13/2010120250496Open ↗
10/26/2010120250496Open ↗
Showing 3 of 5 on file for this type
▸BISSELF-CERT PLUMBING NOTICE5
01/14/2013120849074Open ↗
02/15/2012120604729Open ↗
11/16/2011120604729Open ↗
Showing 3 of 5 on file for this type
▸BISSCHEDULE B - PLUMBING3
10/06/2011120849074Open ↗
03/14/2011120604729Open ↗
Showing 2 of 3 on file for this type
▸BISBOILERS - SUPPORTING DOCUMENTATION1
11/16/2011120604729Open ↗
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT1
03/14/2011120604729Open ↗
▸Safety & Tenant Protection2
▸BISTENANT PROTECTION PLAN AND NOTES2
04/04/2019140831063Open ↗
04/04/2019140830616Open ↗
▸Environmental & Asbestos9
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'5
10/06/2011120849074Open ↗
03/14/2011120604729Open ↗
Showing 2 of 5 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER2
05/04/2011120673949Open ↗
Showing 1 of 2 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
03/20/2017123047078Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026M01215471-I1Open ↗
▸Energy Compliance26
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS12
12/04/2019140830616Open ↗
10/31/2019123047078Open ↗
10/31/2019123047078Open ↗
Showing 3 of 12 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS6
12/04/2019140830616Open ↗
11/18/2019123047078Open ↗
07/18/2019140831063Open ↗
Showing 3 of 6 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY3
04/08/2019140831063Open ↗
04/04/2019140831063Open ↗
04/04/2019140830616Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS2
04/04/2019140831063Open ↗
04/04/2019140830616Open ↗
▸BISELECTRICAL APPLICATION FOR SIDEWALK SHED LIGHTING1
04/17/2013140070973Open ↗
▸BISTECHNICAL REPORT: ENERGY1
11/22/2011120849074Open ↗
▸DOB NOWEN2: As Built Energy Analysis.1
08/13/2026M00555313-I1Open ↗
▸Inspections & Test Reports3
▸BISTECHNICAL REPORT: RESPONSIBILITY3
04/10/2019140830616Open ↗
04/04/2019140831063Open ↗
04/04/2019140830616Open ↗
▸Approvals, Objections & Sign-offs26
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST14
12/04/2019140830616Open ↗
11/18/2019123047078Open ↗
10/31/2019123047078Open ↗
Showing 3 of 14 on file for this type
▸BISADMINISTRATIVE OBJECTIONS6
02/13/2013121524895Open ↗
05/04/2011120673949Open ↗
03/14/2011120604729Open ↗
Showing 3 of 6 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION5
12/04/2019140830616Open ↗
07/18/2019140831063Open ↗
09/24/2013120604729Open ↗
Showing 3 of 5 on file for this type
▸BISCCD1-Construction Code Determination1
07/29/2013121524895Open ↗
▸Cost, Insurance & Ownership20
▸BISCOST AFFIDAVIT20
12/04/2019140830616Open ↗
11/18/2019123047078Open ↗
10/31/2019123047078Open ↗
Showing 3 of 20 on file for this type
▸Filing & Intake Forms24
▸BISEFILING COVER SHEET9
03/20/2017123047078Open ↗
04/27/2015122365500Open ↗
02/13/2013121524895Open ↗
Showing 3 of 9 on file for this type
▸BISBOROUGH INTAKE FORM7
12/04/2019140830616Open ↗
11/18/2019123047078Open ↗
10/31/2019123047078Open ↗
Showing 3 of 7 on file for this type
▸BISADDITIONAL INFORMATION5
09/26/2019123047078Open ↗
07/10/2019123047078Open ↗
10/23/2017123047078Open ↗
Showing 3 of 5 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET3
04/04/2019140831063Open ↗
04/04/2019140830616Open ↗
04/17/2013140070973Open ↗
▸Other Documents1
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION1
11/16/2011120604729Open ↗