| Owner | Filings | Most Recent |
|---|---|---|
| HUBBK | 127 | 09/01/2026 |
| CHELSEA NY REALTY | 3 | 08/01/2026 |
| BOZZUTO MANAGEMENT | 3 | 07/08/2026 |
| HUB ASSOCIATES | 79 | 03/22/2026 |
| STEINER | 1 | 03/22/2026 |
| COLGATE ENTERPRISES | 3 | 03/21/2026 |
| NEVINS REALTY | 5 | 03/21/2026 |
| FITZCON CONSTRUCTION | 2 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| ALWAYS FAST SERVICES CORP | 1 | 08/11/2026 |
| CPL ARCHITECTURE AND ENGINEERING | 2 | 07/22/2026 |
| JPT ARCHITECTS, P.C. | 1 | 07/22/2026 |
| S.M. BERGER ARCHITECTURE PC | 1 | 03/06/2026 |
| DESIMONE CONSULTING ENGINEERING | 1 | 03/06/2026 |
| BAZINI ENGINEERING, P.C. | 1 | 02/25/2026 |
| FLINT FIRE ENGINEERING, LLC | 1 | 07/10/2025 |
| OGP ARCHITECTS, LLP | 2 | 05/14/2025 |
| COLLECTIVE DESIGN ASSOCIATIES | 2 | 04/29/2025 |
| HIGH LINE ENGINEERING PC | 9 | 04/17/2025 |
| DATTNER ARCHITECTS | 3 | 04/17/2025 |
| LEON SKVIRSKY PE | 3 | 01/04/2023 |
| BMG DESIGN BUILD LLC | 1 | 06/09/2022 |
| TSF ENGINEERING, PC | 3 | 06/08/2022 |
| SELF EMPLOYED | 1 | 01/27/2022 |
| F.P.VILLANO CONSULTING ENGINEER LLC | 2 | 09/09/2021 |
| JACK STONE ENGINEERS, PC | 3 | 05/24/2021 |
| ALLEN + KILLCOYNE ARCHITECTS LLP | 1 | 05/24/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| JAM CONSULTANTS, INC. | 32 | 03/21/2026 |
| BUILDING BROTHERS | 6 | 03/21/2026 |
| BRICOLAGE DESIGNS | 1 | 03/21/2026 |
| LOUIS STRIAR | 4 | 03/21/2026 |
| DOMANI CONSULTING | 4 | 03/21/2026 |
| QUEENS JAMAICA CARE | 8 | 03/21/2026 |
| SKYLINE ACCESS | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| AIR DEPOT COMM. REFR. COR | General Contractor | 9 | 08/04/2026 |
| STEINER BUILDING NYC LLC | General Contractor | 6 | 07/29/2026 |
| COMMERCIAL CONSTRUCTION M | General Contractor | 6 | 07/08/2026 |
| G.N.T. MECHANICAL LLC | Fire Protection | 4 | 07/08/2026 |
| 123 MANAGEMENT INC | General Contractor | 4 | 07/08/2026 |
| PAUL SIGNS | Scaffold | 3 | 07/08/2026 |
| AGIR ELEC'L LTD. D/B/A | Electrical | 2 | 03/22/2026 |
| DOUGLAS C MASS | Electrical | 2 | 03/21/2026 |
| GRAY DAWG CONSTRUCTION | General Contractor | 2 | 07/08/2026 |
| JK NY INTERIOR INC | General Contractor | 2 | 04/09/2026 |
| NEW LINE STRUCTURES | General Contractor | 2 | 03/22/2026 |
| CITY SIGNS | Scaffold | 2 | 07/08/2026 |
| MARATHON MECHANICAL LLC | Plumbing | 1 | 07/08/2026 |
| PRIME PIPING & HEATING IN | Plumbing | 1 | 07/08/2026 |
| ANTONY GIRONTA | Electrical | 1 | 03/21/2026 |
| EMPIRE STATE ELECTL CORP | Electrical | 1 | 03/22/2026 |
| A PLUS PLUMBING CORP | Plumbing | 1 | 07/08/2026 |
| AGIR ELECL LTD D B A 002894 | General Contractor | 1 | 03/22/2026 |
| A + SPRINKLER CORP | Fire Protection | 1 | 07/08/2026 |
| ANDAMIO SCAFFOLDING LLC | General Contractor | 1 | 08/12/2026 |
| GARTH DESUZE | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| MEP INSPECTIONS, INC | 1102 | 1 | 07/22/2026 |
| CATALPA SPECIAL INSPECTIO | 2004 | 8 | 07/22/2026 |
| DELTA TESTING LABS | 687 | 1 | 02/25/2026 |
| HIGH LINE ENGINEERING PC | 2920 | 9 | 04/17/2025 |
| HRF SERVICES CORP | 5616 | 4 | 06/09/2022 |
| AA BUILDING & INSPECTION | 1519 | 1 | 01/27/2022 |
| ALLEN+KILLCOYNE ARCHITECT | 2697 | 1 | 05/24/2021 |
| PSI AGENCY INC. | 254 | 2 | 05/24/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sidewalk Shed | Permit Issued | ANDAMIO SCAFFOLDING LLC | 08/11/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | AIR DEPOT COMM. REFR. COR | 08/03/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | AIR DEPOT COMM. REFR. COR | 07/31/2026 |
| DOB NOW | General Construction | Permit Issued | STEINER BUILDING NYC LLC | 07/28/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | JK NY INTERIOR INC | 03/12/2026 |
| DOB NOW | General Construction | Permit Issued | JK NY INTERIOR INC | 03/12/2026 |
| DOB NOW | Construction Fence | Permit Issued | STEINER BUILDING NYC LLC | 03/10/2026 |
| DOB NOW | General Construction | Signed-off | STEINER BUILDING NYC LLC | 02/06/2026 |
| DOB NOW | Mechanical Systems | Signed-off | AIR DEPOT COMM REFR COR | 01/14/2026 |
| DOB NOW | Suspended Scaffold | Signed-off | SKYLINE RESTORATION INC | 07/05/2024 |
| DOB NOW | Sign | Signed-off | PAUL SIGNS, INC | 01/06/2023 |
| DOB NOW | Sign | Signed-off | PAUL SIGNS, INC | 01/06/2023 |
| DOB NOW | General Construction | Signed-off | 123 MANAGEMENT INC | 07/19/2022 |
| DOB NOW | Plumbing | Signed-off | PRIME PIPING & HEATING IN | 07/08/2022 |
| DOB NOW | Mechanical Systems | Signed-off | 123 MANAGEMENT INC | 07/06/2022 |
| DOB NOW | Sprinklers | Signed-off | G.N.T. MECHANICAL LLC | 06/27/2022 |
| DOB NOW | Mechanical Systems | Signed-off | GRAY DAWG CONSTRUCTION | 05/16/2022 |
| DOB NOW | Sprinklers | Signed-off | G.N.T. MECHANICAL LLC | 04/13/2022 |
| DOB NOW | Sprinklers | Signed-off | G.N.T. MECHANICAL LLC | 02/28/2022 |
| DOB NOW | Plumbing | Signed-off | A PLUS PLUMBING CORP | 02/17/2022 |
| DOB NOW | Sprinklers | Signed-off | A + SPRINKLER CORP | 02/17/2022 |
| DOB NOW | Mechanical Systems | Signed-off | AIR DEPOT COMM REFR COR | 02/10/2022 |
| DOB NOW | General Construction | Signed-off | GRAY DAWG CONSTRUCTION | 02/03/2022 |
| DOB NOW | General Construction | Signed-off | STEINER BUILDING NYC LLC | 02/01/2022 |
| DOB NOW | Sign | Signed-off | PAUL SIGNS, INC | 01/14/2022 |
| DOB NOW | General Construction | Signed-off | COMMERCIAL CONSTRUCTION M | 12/17/2021 |
| DOB NOW | Mechanical Systems | Signed-off | AIR DEPOT COMM REFR COR | 11/26/2021 |
| DOB NOW | Sign | Signed-off | ELMER DAWSON | 10/27/2021 |
| DOB NOW | Mechanical Systems | Signed-off | COMMERCIAL CONSTRUCTION M | 07/19/2021 |
| DOB NOW | General Construction | Signed-off | COMMERCIAL CONSTRUCTION M | 07/16/2021 |
| DOB NOW | Plumbing | Signed-off | MARATHON MECHANICAL LLC | 07/15/2021 |
| DOB NOW | Sprinklers | Signed-off | G.N.T. MECHANICAL LLC | 06/11/2021 |
| DOB NOW | Mechanical Systems | Signed-off | COMMERCIAL CONSTRUCTION M | 06/04/2021 |
| DOB NOW | General Construction | Signed-off | COMMERCIAL CONSTRUCTION M | 06/04/2021 |
| DOB NOW | General Construction | Signed-off | STEINER BUILDING NYC LLC | 05/06/2021 |
| DOB NOW | Mechanical Systems | Signed-off | AIR DEPOT COMM REFR COR | 04/16/2021 |
| DOB NOW | Sign | Signed-off | ELMER DAWSON | 02/26/2021 |
| BIS | MH | ISSUED | STEINER BUILDING NYC LLC | 08/05/2019 |
| BIS | OT | ISSUED | DNP BUILDERS LLC | 06/14/2019 |
| BIS | MH | ISSUED | DNP BUILDERS LLC | 06/14/2019 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 04/17/2025 | Signed-off | STEINER BUILDING NYC LLC | Heating and Air Conditioning Systems | Heat / Cool Daikin REYQ384AATJA 432,000 BTU · Vrf Outdoor ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/22/2026 | — | — | Sprinkler System |
| 07/10/2025 | — | — | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/22/2026 | — | — | — |
| 07/10/2025 | — | — | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/13/2026 | Permit Issued | DESUZE ELECTRIC CORP | General Wiring |
| 07/07/2026 | Permit Issued | BOROWIDE ELECT'L CONTR'S | — |
| 06/15/2026 | Complete | DESUZE ELECTRIC CORP | General Wiring |
| 04/12/2024 | Complete | AGIR ELEC'L LTD. D/B/A | 1 meters, 1 new_meters |
| 04/03/2024 | Complete | AGIR ELEC'L LTD. D/B/A | General Wiring |
| 12/13/2023 | Complete | AGIR ELEC'L LTD. D/B/A | General Wiring |
| 03/03/2023 | Complete | AGIR ELEC'L LTD. D/B/A | 1 meters, 1 new_meters |
| 01/11/2023 | Complete | EMPIRE STATE ELECTL CORP | — |
| 01/11/2023 | Complete | EMPIRE STATE ELECTL CORP | — |
| 03/02/2022 | Complete | TESTA ELECTRIC CO., INC | General Wiring |
| 01/18/2022 | Complete | EMPIRE STATE ELECTL CORP | — |
| 09/02/2021 | Complete | RAINBOW ELECTRIC CO., INC | — |
| 09/02/2021 | Complete | RAINBOW ELECTRIC CO., INC | — |
| 07/11/2021 | Complete | PRESTIGE ELECL CONTG CORP | General Wiring |
| 01/10/2020 | Complete | AGIR ELEC'L LTD. D/B/A | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/10/2025 | Permit Issued | JK NY INTERIOR INC | 1 scope_items |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/11/2026 | Permit Issued | ANDAMIO SCAFFOLDING LLC | Sidewalk Shed |
| 03/06/2026 | Permit Issued | STEINER BUILDING NYC LLC | Fence |
| Date | Type | Result | Report |
|---|---|---|---|
| 01/09/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 11/07/2022 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 10/03/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 09/21/2022 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 08/11/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/17/2022 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 05/12/2022 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 05/10/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 03/08/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 01/25/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 10/18/2021 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 10/14/2021 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 08/31/2021 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/21/2026 | Lighting controls | ERIC BERLENT | energy_progress |
| 07/21/2026 | Post-installed Anchors | ERIC BERLENT | special |
| 07/17/2026 | Tenant Protection Plan Compliance | ERIC BERLENT | special |
| 07/17/2026 | Mechanical Systems | ERIC BERLENT | special |
| 07/17/2026 | Tenant Protection Plan Compliance | ERIC BERLENT | special |
| 07/17/2026 | Final | ERIC BERLENT | progress |
| 07/17/2026 | Final | ERIC BERLENT | progress |
| 12/01/2025 | Seismic Isolation Systems | — | special |
| 10/01/2025 | Post-installed Anchors | — | special |
| 06/12/2025 | Tenant Protection Plan Compliance | — | special |
| 06/12/2025 | Fire-Resistant Penetrations and Joints | — | special |
| 06/09/2025 | Sprinkler Systems | — | special |
| 05/06/2025 | Public Assembly Emergency Lighting | ERIC BERLENT | progress |
| 04/24/2025 | Ventilation and air distribution system | ERIC BERLENT | energy_progress |
| 04/24/2025 | Lighting controls | ERIC BERLENT | energy_progress |
| 04/24/2025 | Duct leakage testing, insulation and design | ERIC BERLENT | energy_progress |
| 04/15/2025 | Tenant Protection Plan Compliance | ERIC BERLENT | special |
| 04/15/2025 | HVAC-R and service water heating system controls | Ruslan Nagorny | energy_progress |
| 04/15/2025 | Shutoff dampers | Ruslan Nagorny | energy_progress |
| 04/15/2025 | HVAC-R and service water piping design and insulation | Ruslan Nagorny | energy_progress |
| 04/15/2025 | Maintenance information | Ruslan Nagorny | energy_progress |
| 04/15/2025 | HVAC-R and service water heating equipment | Ruslan Nagorny | energy_progress |
| 04/15/2025 | Fire-Resistant Penetrations and Joints | Ruslan Nagorny | special |
| 04/15/2025 | Tenant Protection Plan Compliance | ERIC BERLENT | special |
| 04/14/2025 | Mechanical Systems | Ruslan Nagorny | special |