| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/27/2025 | Permit Issued | ACCURATE MECHANICAL INC | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/06/2025 | Complete | JIN ELECTRICAL CONT INC | — |
| Owner | Filings | Most Recent |
|---|---|---|
| MELIN GROUP 3491 | 27 | 07/08/2026 |
| LIME CONSTRUCTION NY | 4 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 10/19/2021 | $2.8M | — | — → — | $706/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| LEE ENGINEERING & CONSULTING LLC | 6 | 02/12/2025 |
| LB ENGINEERING PC | 2 | 09/07/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| LEE ENGINEERING CONSULTING | 12 | 03/21/2026 |
| G.PLAN DESIGN & CONSULTING INC | 2 | 03/21/2026 |
| G PLAN BUILDING CONSULTING | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| LIME CONSTRUCTION NY CORP | General Contractor | 7 | 07/08/2026 |
| ACCURATE MECHANICAL INC | Plumbing | 1 | 06/28/2026 |
| CK PLUMBING & MECH INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| IP CONCRETE TESTING AND I | 6252 | 5 | 01/27/2025 |
| LB ENGINEERING PC | 3122 | 2 | 09/07/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Structural | Signed-off | LIME CONSTRUCTION NY CORP | 03/04/2026 |
| DOB NOW | General Construction | Permit Issued | LIME CONSTRUCTION NY CORP | 06/25/2025 |
| DOB NOW | Plumbing | Permit Issued | ANTHONY DISABATO | 05/06/2025 |
| DOB NOW | Plumbing | Permit Issued | CK PLUMBING & MECH INC | 03/05/2025 |
| DOB NOW | Mechanical Systems | Signed-off | LIME CONSTRUCTION NY CORP | 02/28/2025 |
| DOB NOW | Construction Fence | Signed-off | LIME CONSTRUCTION NY CORP | 02/14/2025 |
| DOB NOW | Structural | Signed-off | LIME CONSTRUCTION NY CORP | 04/02/2024 |
| BIS | OT | ISSUED | MACK SIGN & AWNINGS | 02/07/2003 |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 11/25/2024 | Fire-Resistant Penetrations and Joints | INDARDEO PARBHUNATH | special |
| 11/18/2024 | HVAC-R and service water piping design and insulation | Greg Lee | energy_progress |
| 11/18/2024 | Energy Code Compliance Inspections | Greg Lee | progress |
| 11/18/2024 | HVAC-R and service water heating system controls | Greg Lee | energy_progress |
| 11/18/2024 | Duct leakage testing, insulation and design | Greg Lee | energy_progress |
| 11/18/2024 | HVAC-R and service water heating equipment | Greg Lee | energy_progress |
| 10/21/2024 | Final | Greg Lee | progress |
| 10/21/2024 | Mechanical Systems | INDARDEO PARBHUNATH | special |
| 10/15/2024 | HVAC-R and service water heating equipment | Greg Lee | energy_progress |
| 10/15/2024 | HVAC-R and service water piping design and insulation | Greg Lee | energy_progress |
| 10/15/2024 | HVAC-R and service water heating system controls | Greg Lee | energy_progress |
| 10/15/2024 | Fire-Resistant Penetrations and Joints | INDARDEO PARBHUNATH | special |
| 10/15/2024 | Energy Code Compliance Inspections | Greg Lee | progress |
| 10/07/2024 | Fire-Resistance Rated Construction | Greg Lee | progress |
| 10/07/2024 | Fire-Resistant Penetrations and Joints | INDARDEO PARBHUNATH | special |
| 10/07/2024 | Energy Code Compliance Inspections | Greg Lee | progress |
| 10/07/2024 | Insulation placement and R values | Greg Lee | energy_progress |
| 10/07/2024 | Lighting controls | Greg Lee | energy_progress |
| 10/07/2024 | Air barrier - visual inspection | Greg Lee | energy_progress |
| 10/07/2024 | Fenestration air leakage | Greg Lee | energy_progress |
| 10/07/2024 | Interior lighting power | Greg Lee | energy_progress |
| 10/07/2024 | Vestibules | Greg Lee | energy_progress |
| 10/07/2024 | Electrical motors and elevators | Greg Lee | energy_progress |
| 10/07/2024 | Fenestration and door U-factor and product ratings | Greg Lee | energy_progress |
| 09/26/2022 | Structural Stability – Alterations of existing buildings | INDARDEO PARBHUNATH | special |