← Back
BuildNYC
Miscellaneous two family
351 WEST 120TH STREET
MANHATTAN · BIN 1059132
💬 Discuss this project
1901Year Built
3Stories
B9Building Class
R7BZoning
4,406 sfGross Floor Area
2Units
Rent Stabilized0 Active ViolationsFDNY Report ↗
Miscellaneous two family · Owner of record: 351 Property Holdings · 1,817 sf lot · 2.42 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralEquipmentGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Floor 32p · 1 filing · 10 docs
Floor 2
Floor 11 filing · 3 docs
Site & exterior8p · 1 filing · 4 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
351 Property Holdings1207/08/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
09/03/2020$4.0M—Private party → 351 Property Holdings$896/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Ashraf106/04/2025
Mumtaz Enterprises106/04/2025
Clarke Engineering Services306/28/2023
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Sheikh Expediting403/21/2026
Eurocelt Expediting403/21/2026
A1 Expediting Service203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Hydro ConstructionGeneral Contractor307/08/2026
Hatzel and BuehlerElectrical203/21/2026
Balog ConstructionGeneral Contractor203/21/2026
M.M. Construction & BuildersGeneral Contractor207/08/2026
M.M. Construction & BuildersScaffold203/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Mumtaz Enterprises9459106/04/2025
Clarke Engineering Services3795306/28/2023
Building Lifecycle
All (29)Filed (5)Permit Issued (6)Signed Off (4)Violation (10)Special Inspection (4)
09/11/2026
Signed off — Alteration
CONSTRUCTION EQUIPMENT - SCAFFOLD PROPOSED INSTALLATION OF PIPE SCAFFOLD FOR REMEDIAL REPAIRS AS PER PLANS. PIPE SCAFFOLD SHALL COMPLY WITH CHAPTER#33 OF 2014 THE NY BUILDING CODE. NO CHANGE IN USE OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
M01235375-I1
06/01/2026
Permit issued — General Construction
M01235375-I1-GC
08/23/2025
Signed off — Alteration
CONSTRUCTION EQUIPMENT - SCAFFOLD PROPOSED INSTALLATION OF PIPE SCAFFOLD FOR REMEDIAL REPAIRS AS PER PLANS. PIPE SCAFFOLD SHALL COMPLY WITH CHAPTER#33 OF 2014 THE NY BUILDING CODE. NO CHANGE IN USE OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
M01235375-S1
06/13/2025
Permit issued — General Construction
M01235375-I1-GC
06/11/2025
Permit issued — Supported Scaffold
M01235375-S1-SF
06/04/2025
Filed — Alteration
CONSTRUCTION EQUIPMENT - SCAFFOLD PROPOSED INSTALLATION OF PIPE SCAFFOLD FOR REMEDIAL REPAIRS AS PER PLANS. PIPE SCAFFOLD SHALL COMPLY WITH CHAPTER#33 OF 2014 THE NY BUILDING CODE. NO CHANGE IN USE OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
M01235375-I1
06/04/2025
Filed — Alteration
CONSTRUCTION EQUIPMENT - SCAFFOLD PROPOSED INSTALLATION OF PIPE SCAFFOLD FOR REMEDIAL REPAIRS AS PER PLANS. PIPE SCAFFOLD SHALL COMPLY WITH CHAPTER#33 OF 2014 THE NY BUILDING CODE. NO CHANGE IN USE OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
M01235375-S1
10/30/2023
Signed off — Alteration
Structural and General Construction Work for window opening @ 3rd floor as per plans. No change in use, egress or occupancy under this application.
M00891003-I1
10/27/2023
Signed off — Alteration
Structural & General Construction Work for window opening and rear deck modification. No change in use, occupancy or egress under this application.
M00676776-I1
07/05/2023
Permit issued — Structural
M00891003-I1-ST
07/05/2023
Permit issued — Structural
M00891003-I1-GC
06/29/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
Brian Clarke
06/29/2023
Special inspection requirement — Final
Brian Clarke
06/28/2023
Filed — Alteration
Structural and General Construction Work for window opening @ 3rd floor as per plans. No change in use, egress or occupancy under this application.
M00891003-P1
06/28/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
Brian Clarke
06/28/2023
Special inspection requirement — Final
Brian Clarke
06/22/2023
Filed — Alteration
Structural and General Construction Work for window opening @ 3rd floor as per plans. No change in use, egress or occupancy under this application.
M00891003-I1
03/18/2022
Permit issued — General Construction
M00676776-I1-GC-CX
03/10/2022
Filed — Alteration
Structural & General Construction Work for window opening and rear deck modification. No change in use, occupancy or egress under this application.
M00676776-I1
02/03/2015
Violation issued (HPD, closed)
I
02/27/2001
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
02/07/2000
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
03/16/1999
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
05/04/1998
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
09/16/1997
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
02/10/1997
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
08/29/1995
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
03/18/1994
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
03/18/1993
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offM.M. Construction & Builders06/01/2026
DOB NOWGeneral ConstructionSigned-offM.M. Construction & Builders06/13/2025
DOB NOWSupported ScaffoldSigned-offM.M. Construction & Builders06/11/2025
DOB NOWStructuralSigned-offHydro Construction07/05/2023
DOB NOWStructuralSigned-offHydro Construction07/05/2023
DOB NOWGeneral ConstructionSigned-offBalog Construction03/18/2022
BIS—ISSUEDAvr Contracting11/20/2013
BISPLISSUEDDPH Plumbing & Heating11/18/2013
BISOTISSUEDMercury Solar Systems11/14/2012
BISPLISSUEDDPH Plumbing & Heating09/14/2012
BIS—ISSUEDAvr Contracting09/12/2012
BIS—ISSUEDAJ Internbational Construction06/27/2001
BIS—ISSUEDAJ Internbational Construction03/15/2000
BISPLISSUEDFlytiger P & H01/10/2000
BIS—ISSUEDAJ Internbational Construction09/14/1999
1 project · most recent 06/04/2025
Scaffold
FiledStatusContractorScope
06/04/2025Signed-offM.M. Construction & BuildersScaffold
▾Special Inspection Requirements (DOB NOW) — 4
DateRequirementInspectorRole
06/29/2023Structural Stability – Alterations of existing buildingsBrian Clarkespecial
06/29/2023FinalBrian Clarkeprogress
06/28/2023Structural Stability – Alterations of existing buildingsBrian Clarkespecial
06/28/2023FinalBrian Clarkeprogress
▾Documents — 70 on file (BIS + DOB NOW)
▸Plans & Drawings5
▸DOB NOWPlans/Sketch5
09/02/2026M00676776-I1Request digital key ↗
08/30/2026M00891003-P1Request digital key ↗
08/30/2026M00891003-I1Request digital key ↗
Showing 3 of 5 on file for this type
▸Applications & Permits10
▸BISWORK PERMIT APPLICATION5
11/29/2013121102387Open ↗
11/21/2013121102387Open ↗
11/19/2012121326396Open ↗
Showing 3 of 5 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION4
01/07/2014121102387Open ↗
10/18/2012121326396Open ↗
10/16/2012121102387Open ↗
Showing 3 of 4 on file for this type
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION1
06/18/2013121102387Open ↗
▸Seals & Professional Certifications13
▸DOB NOWDPL-1: Design Professional Seal & Signature5
09/02/2026M00676776-I1Open ↗
08/30/2026M00891003-I1Open ↗
08/23/2026M01235375-I1Open ↗
Showing 3 of 5 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION4
09/15/2017121102387Open ↗
06/08/2012121102387Open ↗
03/07/2013121326396Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWProgress Inspector Seal & Signature2
10/18/2026M00891003-I1Open ↗
08/23/2026M00891003-P1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
10/18/2026M00891003-I1Open ↗
08/23/2026M00891003-P1Open ↗
▸Trade Schedules & Equipment4
▸BISSELF-CERT PLUMBING NOTICE2
03/10/2014121102387Open ↗
11/26/2012121102387Open ↗
▸BISSCHEDULE B - PLUMBING1
10/16/2012121102387Open ↗
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE1
01/07/2014121102387Open ↗
▸Safety & Tenant Protection2
▸BISSTREET TREE CHECKLIST2
08/09/2017121102387Open ↗
08/27/2012121102387Open ↗
▸Environmental & Asbestos6
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
09/02/2026M00676776-I1Open ↗
08/30/2026M00891003-I1Open ↗
08/13/2026M00891003-P1Open ↗
▸BISACP5 ASBESTOS: CERTIFICATION (DEP ACP5)2
10/23/2012121326396Open ↗
10/18/2012121326396Open ↗
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
06/07/2012121102387Open ↗
▸Energy Compliance10
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS4
09/15/2017121102387Open ↗
08/09/2017121102387Open ↗
08/27/2012121102387Open ↗
Showing 3 of 4 on file for this type
▸BISSOLAR TAX ABATEMENT APPLICATION (PTA4)3
03/06/2013121326396Open ↗
10/23/2012121326396Open ↗
10/18/2012121326396Open ↗
▸BISTR8: Energy Code Progress Inspections2
03/07/2013121326396Open ↗
10/23/2012121326396Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
08/09/2017121102387Open ↗
▸Approvals, Objections & Sign-offs10
▸BISSCHEDULE A - OCCUPANCY / USE4
05/21/2014121102387Open ↗
06/07/2012121102387Open ↗
06/07/2012121102387Open ↗
Showing 3 of 4 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST3
09/15/2017121102387Open ↗
08/10/2017121102387Open ↗
03/07/2013121326396Open ↗
▸BISUtility Company PV System Interconnection Acknowledgement Letter1
03/07/2013121326396Open ↗
▸BISADMINISTRATIVE OBJECTIONS1
06/07/2012121102387Open ↗
▸BISLETTERS - SUPPORTING DOCUMENTATION1
03/07/2013121326396Open ↗
▸Cost, Insurance & Ownership4
▸BISCOST AFFIDAVIT4
09/15/2017121102387Open ↗
03/07/2013121326396Open ↗
10/23/2012121326396Open ↗
Showing 3 of 4 on file for this type
▸Filing & Intake Forms6
▸BISADDITIONAL INFORMATION4
11/05/2013121102387Open ↗
03/07/2013121326396Open ↗
10/19/2012121102387Open ↗
Showing 3 of 4 on file for this type
▸BISeFiling Job Application Cover Sheet1
10/18/2012121326396Open ↗
▸BISEFILING COVER SHEET1
06/07/2012121102387Open ↗