💬 Discuss this project
1967Year Built
16Stories
D4Building Class
R6AZoning
136,070 sfGross Floor Area
126Units
LL97 CoveredRent Stabilized54 Active Violations 52 unresolved · 2 paperwork only 2 old, status unconfirmed ▸FISP: SAFEFDNY Report ↗
Elevator cooperative · Owner of record: Tilden Towers I · 53,100 sf lot · 2.56 FAR built · Flood zone X
Locations of Work
ArchitectureElectricalPlumbing
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
Roof1p · 1 filing · 3 docs
Floor 11 filing · 3 docs
CellarDirect replacement of cogen unitUnder Construction3p · 1 filing · 7 docs
Site & exteriorFacade repairs1p · 2 filings · 8 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Tilden Towers 11703/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
New York & Company105/23/2023
KMB Design Group111/01/2022
NY Restoration Technology207/02/2018
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
New York & Company203/21/2026
Xinos Construction403/21/2026
Construction Permit Services103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Outdoor InstallationsGeneral Contractor703/21/2026
Xinos ConstructionGeneral Contractor703/21/2026
Ebro ConstructionGeneral Contractor303/21/2026
New York Plumbing-Heating-CoolingPlumbing203/22/2026
Tristruxspecialty_contractor207/08/2026
Spring ScaffoldingGeneral Contractor203/21/2026
National Mechanical Services PlumbingPlumbing207/08/2026
The Metro Group PlumbingPlumbing107/08/2026
Bci CommuncationsGeneral Contractor103/21/2026
Trinity TechnologiesGeneral Contractor103/21/2026
Xinos ConstructionScaffold107/08/2026
Tristruxspecialty_contractor103/21/2026
American Ventilation ServiceGeneral Contractor108/11/2017
Apple Incinerator & CompactionPlumbing207/20/1993
Bci CommunicationsGeneral Contractor112/26/2008
Costrotta Construction MGGeneral Contractor112/09/2011
Leone ConstructionGeneral Contractor111/03/2003
Odyssia Global CommercialGeneral Contractor107/09/2012
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
New York Engineering Associates851105/23/2023
KMB Design Group513111/01/2022
Building Lifecycle
02/20/2027
Facade inspection report due (FISP Cycle 9, sub-cycle A)
The filing window opened 02/21/2025. No Cycle 9 filing on record yet
08/25/2026
Elevator Category 1 inspection report filed
07/15/2026
§ 27-2005 ADM CODE PROVIDE PROVIDE GLASS PANE AT BUILDING ENTRNANCE DOOR , 1st STORY
HPD violation · open
07/05/2026
§ 27-2005 ADM CODE PROVIDE GLASS AT BUILDING ENTRANCE DOOR AT PUBLIC HALL, 1st STORY
HPD violation · open
07/05/2026
§ 329, M/D LAW AND DEPT. RULES AND REGS. PROVIDE A COMPLETED CERTIFICATE OF INSPECTION VISITS IN A PROPER FRAME AT OR NEAR MAILBOXES, BOTTOM EDGE…
HPD violation · open
246 history events on file for this building. Sign in free to see the full history. Sign in · Create account
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedThe Metro Group Plumbing01/14/2026
DOB NOWPlumbingPermit IssuedNational Mechanical Services Plumbing05/10/2024
DOB NOWPlumbingPermit IssuedNational Mechanical Services Plumbing06/02/2023
DOB NOWAntennaSigned-offTristrux04/21/2023
DOB NOWAntennaSigned-offTristrux12/06/2022
DOB NOWSupported ScaffoldSigned-offXinos Construction03/14/2018
BISPLISSUEDNational Mechanical Services Plumbing05/16/2022
BISMHISSUEDXinos Construction02/19/2020
BISEQISSUEDXinos Construction05/02/2019
BISMHISSUEDXinos Construction03/04/2019
BISOTISSUEDXinos Construction03/04/2019
BISPLISSUEDNational Mechanical Services Plumbing07/06/2018
BISEQISSUEDXinos Construction03/20/2018
BISOTISSUEDXinos Construction02/21/2018
BISOTISSUEDXinos Construction02/21/2018
BISFBISSUEDRichard Mortman09/14/2017
BISEQISSUEDAmerican Ventilation Service08/11/2017
BISPLISSUEDNational Mechanical Services Plumbing05/23/2017
BISFBISSUEDRichard Mortman05/10/2017
BISOTISSUEDXinos Construction05/08/2017
BISMHISSUEDXinos Construction05/08/2017
BISEQISSUEDXinos Construction03/28/2017
BISOTISSUEDOdyssia Global Commercial07/09/2012
BISOTISSUEDCostrotta Construction MG12/09/2011
BISEQISSUEDOutdoor Installations05/10/2011
BISOTISSUEDEbro Construction04/15/2011
BISEQISSUEDOutdoor Installations03/21/2011
BISOTISSUEDEbro Construction03/29/2010
BISOTISSUEDEbro Construction03/29/2010
BISEQISSUEDOutdoor Installations03/26/2010
BISOTISSUEDTrinity Technologies02/01/2010
BISOTISSUEDEbro Construction08/11/2009
BISOTISSUEDEbro Construction08/11/2009
BISEQISSUEDOutdoor Installations04/14/2009
BISOTISSUEDBci Communications12/26/2008
BISEQISSUEDOutdoor Installations04/14/2008
BISOTISSUEDBci Communcations01/08/2008
BISOTISSUEDBci Communcations10/03/2007
BISEQISSUEDOutdoor Installations04/10/2007
BISEQISSUEDOutdoor Installations03/31/2006
+ 10 more permits on file
1 project · most recent 05/23/2023
Gas
FiledStatusContractorScope
05/23/2023Permit IssuedThe Metro Group PlumbingGas
2 projects · most recent 09/03/2021
Boiler Controls
FiledStatusContractorScope
09/03/2021CompleteResponse Electric—
05/30/2018CompleteItkin ElectricBoiler Controls
▾Special Inspection Requirements (DOB NOW) — 4
DateRequirementInspectorRole
05/23/2023Maintenance informationLOUIS ARENAenergy_progress
05/10/2023Tenant Protection Plan ComplianceLOUIS ARENAspecial
05/09/2023Energy Code Compliance InspectionsLOUIS ARENAprogress
07/02/2018FinalHamidreza Saghariprogress