← Back
Office with commercial, 7-19 stories
352 7 AVENUE
MANHATTAN · BIN 1014291
💬 Discuss this project
1923Year Built
16Stories
O6Building Class
M1-9A/R12Zoning
127,488 sfGross Floor Area
19Units
LL97 Covered18 Open Violations ▸FISP: SWARMP
Office with commercial, 7-19 stories · Owner of record: 352 ACQUISITION COMPANY, · 7,484 sf lot · 17.03 FAR built · Flood zone X
Locations of Work
ArchitectureMechanicalPlumbingFire ProtectionLandscape
Roof4p · 3 filings · 16 docs
Floor 144p · 2 filings · 10 docs
Floor 1310p · 2 filings · 6 docs
Floor 121p · 1 filing · 3 docs
Floor 11
Floor 10
Floor 917p · 4 filings · 18 docs
Floor 8
Floor 7
Floor 6
Floor 5
Floor 422p · 4 filings · 20 docs
Floor 3
Floor 2
Floor 1
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
352 ACQUISITION COMPANY7003/22/2026
A.M. PROPERTIES803/22/2026
SIDNEY J. BERNSTEIN INC403/22/2026
VERIZON WIRELESS103/21/2026
AM PROPERTY HOLDING II4203/21/2026
AM HOLDING803/21/2026
AM PROPERTIES HOLDINGS903/21/2026
T-MOBILE103/21/2026
AM PROPERTY503/21/2026
ACQUISITION203/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
OUTSOURCE CONSULTANTS, INC.4003/21/2026
D R BROWN403/21/2026
GREEN STUDIO203/21/2026
YOUN DESIGN CORP203/21/2026
CCM CONSULTING GROUP, INC.103/21/2026
CONSTRUCTION PERMIT SERVICES203/21/2026
JM ZONING, LLC.203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
DAIN CONSTRUCTION CORPGeneral Contractor1107/08/2026
SAFETY FIRE SPRINKLER CORPFire Protection407/08/2026
PHOENIX SUTTON STR INCGeneral Contractor307/08/2026
BEDROCK PLBG. & HTG., INCPlumbing207/08/2026
JPI PLUMBING & HEATING INPlumbing207/08/2026
TRANSCANADAElectrical103/21/2026
FLOW-RIGHT FIRE SUPP CORPFire Protection107/08/2026
CHIAPPA RICHARDElectrical103/21/2026
HIMALAYA TOWERSGeneral Contractor107/08/2026
LCS RESTORATION CORPGeneral Contractor107/08/2026
VARIANT SERVICES INCGeneral Contractor107/08/2026
DV PLUMBING INCPlumbing107/08/2026
CEL TECH ELECTRIC INCGeneral Contractor107/08/2026
ELPO ELECTRICAL CONTG INCElectrical103/22/2026
HOLNESS, GEORGEElectrical103/21/2026
RICHARD CHIAPPAElectrical103/21/2026
RICHARD NEUElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
JACK GREEN ASSOCIATES4221702/12/2025
R MARSAC CONSULTING LLC329107/19/2022
Building Lifecycle
All (173)Filed (29)Permit Issued (24)Signed Off (10)Facade (FISP) (12)Violation (60)Inspection (8)Special Inspection (30)
05/27/2026
Signed off — Alteration
INDUSTRIAL ROPE ACCESS INITIAL CD5 FOR FISP INSPECTION
M01388992-I1
04/30/2026
Permit issued — Suspended Scaffold
M01388992-I1-SC
04/17/2026
Filed — Alteration
INDUSTRIAL ROPE ACCESS INITIAL CD5 FOR FISP INSPECTION
M01388992-I1
02/04/2026
Signed off — Alteration
M01158754-I1
01/15/2026
Permit issued — Mechanical Systems
M01158754-I1-MS
07/29/2025
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
02/12/2025
Filed — Alteration
M01158754-I1
01/28/2025
Special inspection requirement — Shutoff dampers
JACK GREEN
01/14/2025
Special inspection requirement — HVAC-R and service water heating equipment
JACK GREEN
01/14/2025
Special inspection requirement — HVAC-R and service water heating system controls
JACK GREEN
01/14/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
JACK GREEN
12/20/2024
Special inspection requirement — Mechanical Systems
JACK GREEN
12/20/2024
Special inspection requirement — Final
JACK GREEN
12/01/2024
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
06/04/2024
Signed off — Alteration
M00912920-I1
03/22/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
03/18/2024
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
03/11/2024
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
03/11/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
01/18/2024
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
01/18/2024
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
01/05/2024
Filed — Alteration
M00972950-I1
01/05/2024
Filed — Alteration
M00972971-I1
01/01/2024
Special inspection requirement — Final
RENEE RAJAPPA
12/01/2023
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
10/24/2023
Permit issued — Sprinklers
M00912912-I1-EW-SP
10/19/2023
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
10/11/2023
Filed — Alteration
SPRINKLER MODIFICATIONS AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M00912912-I1
09/21/2023
Permit issued — General Construction
M00912942-I1-GC
09/21/2023
Permit issued — Mechanical Systems
M00912924-I1-MS
09/15/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
08/30/2023
Permit issued — Plumbing
M00912920-I1-PL
08/21/2023
Filed — Alteration
M00912920-I1
08/21/2023
Filed — Alteration
MECHANICAL MODIFICATIONS AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M00912924-I1
08/11/2023
Filed — Alteration
INTERIOR RENOVATIONS. PARTTIONS, DOORS AND CEILING MODIFICATIONS AND RELATED FINISHES AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M00912942-I1
08/07/2023
Special inspection requirement — Fire-Resistance Rated Construction
JACK GREEN
08/03/2023
Special inspection requirement — Lighting controls
JACK GREEN
08/03/2023
Special inspection requirement — Shutoff dampers
JACK GREEN
08/03/2023
Special inspection requirement — Maintenance information
JACK GREEN
08/03/2023
Special inspection requirement — Energy Code Compliance Inspections
JACK GREEN
08/03/2023
Special inspection requirement — Interior lighting power
JACK GREEN
08/03/2023
Special inspection requirement — HVAC-R and service water piping design and insulation
JACK GREEN
08/03/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
JACK GREEN
08/02/2023
Special inspection requirement — Final
Adam Snyder
08/01/2023
Special inspection requirement — Mechanical Systems
JACK GREEN
08/01/2023
Special inspection requirement — Final
JACK GREEN
06/30/2023
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
06/30/2023
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
01/23/2023
Signed off — Alteration
M00764948-I1
11/05/2022
Signed off — Alteration
installation of temporary fence
M00147997-I1
08/23/2022
Permit issued — Antenna
M00764948-I1-AN
07/19/2022
Filed — Alteration
M00764948-I1
02/15/2022
Cycle 9 facade report submitted
01/05/2022
Cycle 9 facade inspection completed
12/01/2021
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
09/10/2021
Permit issued — Mechanical Systems
M00292472-I1-MS
09/08/2021
Signed off — Alteration
MECHANICAL WORK AS SHOWN ON PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION
M00292471-I1
09/03/2021
Cycle 9 facade report signed — SWARMP
07/12/2021
Signed off — Alteration
MODIFICATIONS TO AN EXISTING SPRINKLER SYSTEMS TO INCLUDE INSTALLATION OF TEMP LOOP, AS SHOWN ON PLANS FILED HEREWITH.
M00382930-I1
03/30/2021
Filed — Alteration
INSTALLATION OF SIDEWALK SHED AS PER PLANS, SIDEWALK SHED LIVE LOAD WILL BE 300 PSF. SHALL COMPLY WITH CHAPTER # 33 OF THE CODE 2014, NO CHANGES TO USE, EGRESS AND OCCUPANCY.
M00494254-I1
Latest 60 of 173 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSuspended ScaffoldSigned-offSATO CONSTRUCTION CO. INC04/30/2026
DOB NOWMechanical SystemsSigned-offDAIN CONSTRUCTION01/15/2026
DOB NOWSprinklersPermit IssuedFLOW-RIGHT FIRE SUPP CORP10/24/2023
DOB NOWGeneral ConstructionPermit IssuedDAIN CONSTRUCTION09/21/2023
DOB NOWMechanical SystemsPermit IssuedDAIN CONSTRUCTION09/21/2023
DOB NOWPlumbingSigned-offDV PLUMBING INC08/30/2023
DOB NOWAntennaSigned-offHIMALAYA TOWERS08/23/2022
DOB NOWMechanical SystemsPermit IssuedDAIN CONSTRUCTION09/10/2021
DOB NOWSidewalk ShedPermit IssuedLCS RESTORATION CORP03/30/2021
DOB NOWPlumbingSigned-offJPI PLUMBING & HEATING IN11/10/2020
DOB NOWPlumbingSigned-offBEDROCK PLBG. & HTG., INC10/22/2020
DOB NOWSprinklersPermit IssuedSAFETY FIRE SPRINKLER CORP09/30/2020
DOB NOWMechanical SystemsSigned-offDAIN CONSTRUCTION09/29/2020
DOB NOWSprinklersPermit IssuedSAFETY FIRE SPRINKLER CORP08/28/2020
DOB NOWSprinklersSigned-offSAFETY FIRE SPRINKLER CORP08/26/2020
DOB NOWPlumbingSigned-offJPI PLUMBING & HEATING IN08/24/2020
DOB NOWMechanical SystemsSigned-offDAIN CONSTRUCTION08/24/2020
DOB NOWMechanical SystemsPermit IssuedDAIN CONSTRUCTION06/15/2020
DOB NOWSprinklersPermit IssuedSAFETY FIRE SPRINKLER CORP04/13/2020
DOB NOWPlumbingSigned-offBEDROCK PLBG. & HTG., INC01/21/2020
DOB NOWSidewalk ShedPermit IssuedPHOENIX SUTTON STR INC08/05/2019
DOB NOWSidewalk ShedPermit IssuedPHOENIX SUTTON STR INC08/05/2019
DOB NOWConstruction FencePermit IssuedVARIANT SERVICES INC05/17/2019
DOB NOWAntennaSigned-offCEL TECH ELECTRIC INC11/09/2018
BISOTISSUEDDAIN CONSTRUCTION CORP07/17/2020
BISOTISSUEDDAIN CONSTRUCTION CORP09/13/2019
BISSPISSUEDSAFETY FIRE SPRINKLER CORP05/21/2019
BISOTISSUEDVARIANT SERVICES INC04/22/2019
BISMHISSUEDVARIANT SERVICES INC04/22/2019
BISBLISSUEDDNA PLUMBING CONTR. INC01/31/2019
BISBLISSUEDDNA PLUMBING CONTR. INC10/05/2018
BISBLISSUEDDNA PLUMBING CONTR. INC03/14/2018
BISPLISSUEDDNA PLUMBING CONTR. INC03/14/2018
BISOTISSUEDJERRICK ASSOCIATES INC09/25/2017
BISSPISSUEDPLUMBING NYC, INC09/25/2017
BISPLISSUEDPLUMBING NYC INC09/25/2017
BISMHISSUEDDAIN CONSTRUCTION CORP09/07/2017
BISEQISSUEDJERRICK ASSOCIATES INC08/31/2017
BISEQISSUEDJERRICK ASSOCIATES INC08/28/2017
BISOTISSUEDDAIN CONSTRUCTION CORP03/31/2017
+ 34 more permits on file
2 projects · most recent 08/21/2023
Associated Ducts and Piping Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
08/21/2023Permit IssuedDAIN CONSTRUCTION CORPAssociated Ducts and Piping
Ducts & Piping
Anemostat PG-22-A ×6
X2VO 1,230 CFM ×1
10/19/2020Permit IssuedDAIN CONSTRUCTION CORPAssociated Ducts and Piping, Ventilation Systems
Ventilation
Inline GN146 75 CFM · Exhaust Fan ×2
Ducts & Piping
N/A N/A 1 BTU ×2
3 projects · most recent 10/11/2023
FiledStatusContractorScope
10/11/2023Permit IssuedFLOW-RIGHT FIRE SUPP CORP—
12/17/2020Permit IssuedSAFETY FIRE SPRINKLER COR92 heads
01/21/2020Permit IssuedSAFETY FIRE SPRINKLER COR140 heads
2 projects · most recent 10/19/2020
Water/Sanitary
FiledStatusContractorScope
10/19/2020Signed-offBEDROCK PLBG. & HTG., INCWater/Sanitary
01/17/2020Signed-offBEDROCK PLBG. & HTG., INCWater/Sanitary
4 projects · most recent 05/12/2021
General Wiring
FiledStatusContractorScope
05/12/2021Permit IssuedRICHARD NEU—
07/24/2019Permit IssuedELPO ELECTRICAL CONTG INC—
05/14/2019Permit IssuedALL PRO ELEC. OF N.Y. INCGeneral Wiring
05/05/2019CompleteJONG HYUN KIM—
1 project · most recent 03/30/2021
Sidewalk Shed
FiledStatusContractorScope
03/30/2021Permit IssuedLCS RESTORATION CORPSidewalk Shed
1 project · most recent 04/17/2026
FiledStatusContractorScope
04/17/2026Signed-offSATO CONSTRUCTION CO. INC—
▾Field Inspections (DOB CAP) — 8
DateTypeResultReport
03/22/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
03/18/2024Fail-Final PL - Up to 3 Requested FloorsFailView ↗
03/11/2024Certified Gas-Gas-Piping-RoughingCertifiedView ↗
03/11/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
01/18/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
01/18/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
10/19/2023Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
09/15/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 54
DateRequirementInspectorRole
01/28/2025Shutoff dampersJACK GREENenergy_progress
01/14/2025HVAC-R and service water heating equipmentJACK GREENenergy_progress
01/14/2025HVAC-R and service water heating system controlsJACK GREENenergy_progress
01/14/2025HVAC-R and service water piping design and insulationJACK GREENenergy_progress
12/20/2024Mechanical SystemsJACK GREENspecial
12/20/2024FinalJACK GREENprogress
01/01/2024FinalRENEE RAJAPPAprogress
08/07/2023Fire-Resistance Rated ConstructionJACK GREENprogress
08/03/2023Lighting controlsJACK GREENenergy_progress
08/03/2023Shutoff dampersJACK GREENenergy_progress
08/03/2023Maintenance informationJACK GREENenergy_progress
08/03/2023Energy Code Compliance InspectionsJACK GREENprogress
08/03/2023Interior lighting powerJACK GREENenergy_progress
08/03/2023HVAC-R and service water piping design and insulationJACK GREENenergy_progress
08/03/2023Fire-Resistant Penetrations and JointsJACK GREENspecial
08/02/2023FinalAdam Snyderprogress
08/01/2023Mechanical SystemsJACK GREENspecial
08/01/2023FinalJACK GREENprogress
12/18/2020Fire-Resistant Penetrations and JointsJACK GREENspecial
12/18/2020Sprinkler SystemsJACK GREENspecial
12/14/2020Fire-Resistant Penetrations and JointsJACK GREENspecial
12/14/2020Sprinkler SystemsJACK GREENspecial
10/20/2020Fire-Resistant Penetrations and JointsJACK GREENspecial
10/20/2020Mechanical SystemsJACK GREENspecial
10/20/2020Energy Code Compliance InspectionsJACK GREENprogress
Latest 25 of 54.
▾Documents — 662 on file (BIS + DOB NOW)
▸Plans & Drawings30
▸DOB NOWPlans/Sketch11
09/06/2026M00073442-I1Request digital key ↗
09/03/2026M00494254-I1Request digital key ↗
09/02/2026M00764948-I1Request digital key ↗
Showing 3 of 11 on file for this type
▸DOB NOWPlans/Sketch - Sprinkler6
09/04/2026M00382930-I1Request digital key ↗
09/04/2026M00292424-I1Request digital key ↗
08/15/2026M00272439-I1Request digital key ↗
Showing 3 of 6 on file for this type
▸DOB NOWPlans/Sketch - Mechanical Systems5
09/04/2026M00382831-I1Request digital key ↗
09/04/2026M00292471-I1Request digital key ↗
09/04/2026M00292472-I1Request digital key ↗
Showing 3 of 5 on file for this type
▸DOB NOWPlans/Sketch - Plumbing4
09/05/2026M00272455-I1Request digital key ↗
09/05/2026M00292443-P1Request digital key ↗
09/05/2026M00292443-I1Request digital key ↗
Showing 3 of 4 on file for this type
▸DOB NOWPlans/Sketch - Construction Fence1
09/05/2026M00147997-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Supported Scaffold1
09/05/2026M00204275-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Sidewalk Shed1
09/05/2026M00204275-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Sign1
09/05/2026M00167404-I1Request digital key ↗
▸Applications & Permits128
▸BISPLAN / WORK APPROVAL APPLICATION77
11/16/2021100979782Open ↗
11/10/2021100979782Open ↗
05/19/2021100979782Open ↗
Showing 3 of 77 on file for this type
▸BISWORK PERMIT APPLICATION49
05/10/2021140996055Open ↗
07/17/2020140924392Open ↗
09/13/2019123744261Open ↗
Showing 3 of 49 on file for this type
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION1
03/08/2019100979782Open ↗
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION1
05/03/2021100979782Open ↗
▸Seals & Professional Certifications187
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION53
09/13/2019123744261Open ↗
09/13/2019123744261Open ↗
08/01/2019123709932Open ↗
Showing 3 of 53 on file for this type
▸DOB NOWProgress Inspector Seal & Signature34
09/01/2026M00292471-I1Open ↗
09/01/2026M00292471-I1Open ↗
09/01/2026M00292471-I1Open ↗
Showing 3 of 34 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature28
09/05/2026M00167404-I1Open ↗
09/05/2026M00272465-I1Open ↗
09/05/2026M00272439-I1Open ↗
Showing 3 of 28 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT20
03/25/2021141000351Open ↗
12/29/2020140996055Open ↗
07/16/2020140924392Open ↗
Showing 3 of 20 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST19
09/13/2019123744261Open ↗
08/01/2019123709932Open ↗
04/19/2019123889453Open ↗
Showing 3 of 19 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature14
09/13/2026M00292443-I1Open ↗
09/01/2026M00292471-I1Open ↗
08/31/2026M01158754-I1Open ↗
Showing 3 of 14 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM7
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 7 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY6
03/25/2021141000351Open ↗
12/29/2020140996055Open ↗
07/16/2020140924392Open ↗
Showing 3 of 6 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION6
03/25/2021141000351Open ↗
12/29/2020140996055Open ↗
07/16/2020140924392Open ↗
Showing 3 of 6 on file for this type
▸Trade Schedules & Equipment23
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE16
04/19/2019123889453Open ↗
05/08/2018120939459Open ↗
05/08/2018120939459Open ↗
Showing 3 of 16 on file for this type
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT3
03/14/2018120939459Open ↗
03/14/2018120939459Open ↗
Showing 2 of 3 on file for this type
▸BISSELF-CERT PLUMBING NOTICE2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISSCHEDULE B - PLUMBING1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISFA - FDNY APPROVAL : FD-FAA1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Safety & Tenant Protection4
▸BISTenant Protection Plan and Notes2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISTPP1: TENANT PROTECTION PLAN1
05/10/2021140996055Open ↗
▸DOB NOWTenant Protection Plan1
08/13/2026M00204275-I1Open ↗
▸Environmental & Asbestos55
▸BISASBESTOS: CERTIFICATION (DEP ACP5)26
12/29/2020140996055Open ↗
07/16/2020140924392Open ↗
03/03/2020123744261Open ↗
Showing 3 of 26 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report21
09/05/2026M00272465-I1Open ↗
09/05/2026M00272439-I1Open ↗
09/05/2026M00292443-P1Open ↗
Showing 3 of 21 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Energy Compliance53
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS28
09/13/2019123744261Open ↗
08/01/2019123709932Open ↗
04/23/2019123889453Open ↗
Showing 3 of 28 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS12
02/24/2022123709932Open ↗
02/19/2021140924392Open ↗
08/21/2018122386140Open ↗
Showing 3 of 12 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY3
10/12/2021140996055Open ↗
12/29/2020140996055Open ↗
07/16/2020140924392Open ↗
▸BISTECHNICAL REPORT: ENERGY3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISENERGY CODE COMPLIANCE INSPECTIONS2
02/24/2022123709932Open ↗
05/10/2021140996055Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)2
06/27/2022123709932Open ↗
10/12/2021140996055Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS2
12/29/2020140996055Open ↗
07/16/2020140924392Open ↗
▸BISELECTRICAL APPLICATION FOR SIDEWALK SHED LIGHTING1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Inspections & Test Reports13
▸BISTECHNICAL REPORT: RESPONSIBILITY12
02/24/2022123709932Open ↗
10/12/2021140996055Open ↗
03/25/2021141000351Open ↗
Showing 3 of 12 on file for this type
▸BISSTRUCTURAL STABILITY - EXISTING BUILDINGS1
05/10/2021140996055Open ↗
▸Approvals, Objections & Sign-offs44
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST23
10/12/2021140996055Open ↗
02/22/2021140924392Open ↗
02/22/2021140924392Open ↗
Showing 3 of 23 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE8
11/16/2021100979782Open ↗
11/10/2021100979782Open ↗
11/10/2021100979782Open ↗
Showing 3 of 8 on file for this type
▸BISADMINISTRATIVE OBJECTIONS7
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 7 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION3
05/03/2021100979782Open ↗
Showing 1 of 3 on file for this type
▸BISFINAL2
05/10/2021140996055Open ↗
07/17/2020140924392Open ↗
▸BISSUPERSEDING LETTER1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Cost, Insurance & Ownership53
▸BISCOST AFFIDAVIT48
03/25/2021141000351Open ↗
12/29/2020140996055Open ↗
11/02/2020123709932Open ↗
Showing 3 of 48 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW33
03/04/2022123709932Open ↗
10/12/2021140996055Open ↗
02/22/2021140924392Open ↗
▸BISLL58-88 CIVIL PENALTY AFFIDAVIT2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Filing & Intake Forms67
▸BISEFILING COVER SHEET29
09/13/2019123744261Open ↗
08/01/2019123709932Open ↗
04/19/2019123889453Open ↗
Showing 3 of 29 on file for this type
▸BISADDITIONAL INFORMATION18
11/22/2021100979782Open ↗
10/06/2021100979782Open ↗
10/06/2021100979782Open ↗
Showing 3 of 18 on file for this type
▸BISBOROUGH INTAKE FORM13
02/13/2020123744261Open ↗
03/25/2019140687763Open ↗
03/14/2019100979782Open ↗
Showing 3 of 13 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET7
03/25/2021141000351Open ↗
12/29/2020140996055Open ↗
07/16/2020140924392Open ↗
Showing 3 of 7 on file for this type
▸Other Documents5
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION3
12/19/2022100979782Open ↗
Showing 1 of 3 on file for this type
▸BISCONSTRUCTION - SUPPORTING DOCUMENTATION1
05/03/2021100979782Open ↗
▸DOB NOWIRA Certification1
08/13/2026M01388992-I1Open ↗