← Back
BuildNYC
Three families
3533 BARNES AVENUE
BRONX · BIN 2057770
💬 Discuss this project
1915Year Built
3Stories
C0Building Class
R6AZoning
3,432 sfGross Floor Area
3Units
Rent Stabilized19 Active Violations ▸FDNY Report ↗
Three families · Owner of record: SHG 3533 Barnes · 3,150 sf lot · 1.09 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire ProtectionGeneralOther
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Roof19p · 1 filing · 20 docs
Bulkhead1p · 1 filing · 20 docs
Floor 353p · 1 filing · 20 docs
Floor 253p · 1 filing · 20 docs
Floor 1Unit 1C52p · 1 filing · 20 docs
Basement58p · 1 filing · 20 docs
Site & exterior34p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
SHG 3533 Barnes203/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
08/15/2023$800K—Private party → SHG 3533 BARNES LLC$233/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Adb Associates1203/20/2024
Vasilios Artemiou PE209/06/2023
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Express Filing2803/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Builders Group USAGeneral Contractor203/21/2026
D & W ElectricalElectrical103/22/2026
Builders Group USAspecialty_contractor107/08/2026
A. M. Plumbing CompanyPlumbing107/08/2026
Prime Piping & HeatingFire Protection107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
HRF Services5616803/20/2024
Building Lifecycle
08/31/2026
§ 27-2017.3 HMC: TRACE AND REPAIR THE SOURCE AND ABATE THE VISIBLE MOLD CONDITION... MORE THAN 30 SQUARE FEET OF MOLD AT SOUTH WALL IN THE 4th ROOM…
HPD violation · open
08/31/2026
§ 27-2017.3 HMC: TRACE AND REPAIR THE SOURCE AND ABATE THE VISIBLE MOLD CONDITION... LESS THAN 10 SQUARE FEET OF MOLD AT WASHBASIN CABINET DOOR IN…
HPD violation · open
08/31/2026
§ 27-2017.3 HMC: TRACE AND REPAIR THE SOURCE AND ABATE THE VISIBLE MOLD CONDITION... LESS THAN 10 SQUARE FEET OF MOLD AT EAST, SOUTH, AND WEST…
HPD violation · open
07/27/2026
Elevator Category 1 inspection report filed
04/29/2026
(a) § hmc:file annual bedbug report in accordance with HPD rule as described on the back of this notice of violation or as described on HPDs…
HPD violation · closed
105 history events on file for this building. Sign in free to see the full history. Sign in · Create account
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsSigned-offBuilders Group USA09/15/2023
DOB NOWPlumbingSigned-offA. M. Plumbing Company09/13/2023
DOB NOWSprinklersSigned-offAmb Mechanical09/13/2023
DOB NOWGeneral ConstructionPermit IssuedBuilders Group USA09/13/2023
1 project · most recent 03/20/2024
Heating and Air Conditioning Systems
FiledStatusContractorScope
03/20/2024Signed-offBuilders Group USAHeating and Air Conditioning Systems
1 project · most recent 03/20/2024
Sprinkler System
FiledStatusContractorScope
03/20/2024Signed-offPrime Piping & HeatingSprinkler System
1 project · most recent 03/20/2024
Gas Storm Water/Sanitary
FiledStatusContractorScope
03/20/2024Signed-offA. M. Plumbing CompanyGas, Storm, Water/Sanitary
5 projects · most recent 12/18/2024
General Wiring
FiledStatusContractorScope
12/18/2024CompleteFried ElectricGeneral Wiring
09/17/2024CompleteFried ElectricGeneral Wiring
08/14/2024CompleteFried ElectricGeneral Wiring
07/15/2024CompleteD & W Electrical—
04/11/2024CompleteD & W ElectricalGeneral Wiring
▾Field Inspections (DOB CAP) — 7
DateTypeResultReport
12/09/2024Pass-Final CND-Occupancy InspectionPassView ↗
02/09/2024Pass-Final CND-Occupancy InspectionPassView ↗
01/30/2024Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
01/25/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
12/11/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
11/22/2023Pass-Final PL - Up to 9 Requested FloorsPassView ↗
11/13/2023Pass-Final PL - UndergroundPassView ↗
▾Special Inspection Requirements (DOB NOW) — 113
DateRequirementInspectorRole
03/22/2024Exterior Insulation and Finish Systems (EIFS)FAHAD FATEHspecial
03/22/2024Fire-Resistant Penetrations and JointsFAHAD FATEHspecial
03/22/2024Fire-Resistance Rated ConstructionFAHAD FATEHprogress
03/22/2024Energy Code Compliance InspectionsFAHAD FATEHprogress
03/22/2024Exterior lighting powerFAHAD FATEHenergy_progress
03/22/2024Fenestration and door U-factor and product ratingsFAHAD FATEHenergy_progress
03/22/2024Maintenance informationFAHAD FATEHenergy_progress
03/22/2024MeteringFAHAD FATEHenergy_progress
03/22/2024Lighting in dwelling unitsFAHAD FATEHenergy_progress
03/22/2024Air barrier - visual inspectionFAHAD FATEHenergy_progress
03/22/2024Insulation placement and R valuesFAHAD FATEHenergy_progress
03/22/2024Lighting controlsFAHAD FATEHenergy_progress
03/22/2024Fenestration areasFAHAD FATEHenergy_progress
03/22/2024Interior lighting powerFAHAD FATEHenergy_progress
03/22/2024Fenestration air leakageFAHAD FATEHenergy_progress
03/19/2024MeteringFAHAD FATEHenergy_progress
03/19/2024Fire-Resistant Penetrations and JointsFAHAD FATEHspecial
03/19/2024Energy Code Compliance InspectionsFAHAD FATEHprogress
03/19/2024Fire-Resistance Rated ConstructionFAHAD FATEHprogress
03/19/2024Exterior lighting powerFAHAD FATEHenergy_progress
03/19/2024Lighting in dwelling unitsFAHAD FATEHenergy_progress
03/19/2024Insulation placement and R valuesFAHAD FATEHenergy_progress
03/19/2024Lighting controlsFAHAD FATEHenergy_progress
03/19/2024Interior lighting powerFAHAD FATEHenergy_progress
03/19/2024Air barrier - visual inspectionFAHAD FATEHenergy_progress
Latest 25 of 113.
80 filed documents on file for this building. Sign in free to see the full history. Sign in · Create account