Roof
Fire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Foundation · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Supported Scaffold · Support of Excavation
Floor 9
ArchitectureFire ProtectionPlumbingStructural
Issued Permit Scope
Foundation · General Construction · Plumbing · Protection and Mechanical Methods · Sprinklers · Supported Scaffold · Support of Excavation
Floor 8
ArchitectureFire ProtectionPlumbingStructural
Issued Permit Scope
Foundation · General Construction · Plumbing · Protection and Mechanical Methods · Sprinklers · Supported Scaffold · Support of Excavation
Floor 7
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Construction Fence · Foundation · General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Structural · Supported Scaffold · Support of Excavation
Floor 6
ArchitectureFire ProtectionPlumbingStructural
Issued Permit Scope
Construction Fence · Foundation · General Construction · Plumbing · Protection and Mechanical Methods · Sprinklers · Structural · Supported Scaffold · Support of Excavation
Floor 51 filing
ArchitectureFire ProtectionPlumbingStructural
Issued Permit Scope
Construction Fence · Foundation · General Construction · Plumbing · Protection and Mechanical Methods · Sprinklers · Structural · Supported Scaffold · Support of Excavation
INSTALLATION OF TEMPORARY NEEDLE BEAM AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents
Floor 4
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Construction Fence · Foundation · General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Structural · Supported Scaffold · Support of Excavation
Floor 3
ArchitectureFire ProtectionPlumbingStructural
Issued Permit Scope
Construction Fence · Foundation · General Construction · Plumbing · Protection and Mechanical Methods · Sprinklers · Structural · Supported Scaffold · Support of Excavation
Floor 2
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Foundation · General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Supported Scaffold · Support of Excavation
Floor 1
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Foundation · General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Supported Scaffold · Support of Excavation
Site & exterior4 filings
ArchitectureFire ProtectionPlumbing
Issued Permit Scope
Construction Fence · General Construction · Plumbing · Protection and Mechanical Methods · Sidewalk Shed · Sprinklers · Supported Scaffold
INSTALLATION OF TEMPORARY NEEDLE BEAM AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents
INSTALLATION OF TEMPORARY OVERHEAD PROTECTION AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
1 document
Latest 3 of 4 filings on this floor.