| Owner | Filings | Most Recent |
|---|---|---|
| C&L CONRACTING CORP | 12 | 03/22/2026 |
| NYC DEPARTMENT OF DESIGN-CONST | 5 | 03/21/2026 |
| NYC DEPARTMENT OF DESIGN AND CON | 1 | 03/21/2026 |
| DEPARTMENT OF ENVIRONMENTAL PROT | 19 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| GRIMSHAW ARCHITECTS PC | 3 | 08/03/2026 |
| BUROHAPPOLD | 2 | 05/09/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| MUNICIPAL BUILDING CONSULTANTS | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| EASTERN PLBG & MECH CONTR | Plumbing | 22 | 03/22/2026 |
| RISER PLBG & HTG CORP | Plumbing | 2 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| TECTONIC ENGINEERING CONS | 106 | 2 | 05/09/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Boiler Equipment | Signed-off | RISER PLBG & HTG CORP | 12/13/2024 |
| DOB NOW | Boiler Equipment | Signed-off | RISER PLBG & HTG CORP | 04/30/2024 |
| BIS | — | ISSUED | C & L CONTRACTING CORP | 03/18/2026 |
| BIS | PL | ISSUED | EASTERN PLBG & MECH CONTR | 01/28/2026 |
| BIS | — | ISSUED | C & L CONTRACTING CORP | 12/08/2025 |
| BIS | EQ | ISSUED | C & L CONTRACTING CORP | 11/25/2025 |
| BIS | — | ISSUED | C & L CONTRACTING CORP | 07/24/2025 |
| BIS | SP | ISSUED | CMA PLUMBING & HEATING IN | 06/26/2025 |
| BIS | PL | ISSUED | EASTERN PLBG & MECH CONTR | 01/21/2025 |
| BIS | — | ISSUED | C & L CONTRACTING CORP | 01/03/2025 |
| BIS | — | ISSUED | C & L CONTRACTING CORP | 12/20/2024 |
| BIS | EQ | ISSUED | C & L CONTRACTING CORP | 11/26/2024 |
| BIS | SP | ISSUED | CMA PLUMBING & HEATING IN | 06/17/2024 |
| BIS | PL | ISSUED | EASTERN PLBG & MECH CONTR | 01/24/2024 |
| BIS | EQ | ISSUED | C & L CONTRACTING CORP | 12/18/2023 |
| BIS | — | ISSUED | C & L CONTRACTING CORP | 12/18/2023 |
| BIS | PL | ISSUED | EASTERN PLBG & MECH CONTR | 01/24/2023 |
| BIS | EQ | ISSUED | C & L CONTRACTING CORP | 12/30/2022 |
| BIS | — | ISSUED | C & L CONTRACTING CORP | 12/30/2022 |
| BIS | PL | ISSUED | EASTERN PLBG & MECH CONTR | 01/24/2022 |
| BIS | — | ISSUED | C & L CONTRACTING CORP | 12/20/2021 |
| BIS | EQ | ISSUED | C & L CONTRACTING CORP | 12/20/2021 |
| BIS | PL | ISSUED | EASTERN PLBG & MECH CONTR | 01/22/2021 |
| BIS | — | ISSUED | C & L CONTRACTING CORP | 12/23/2020 |
| BIS | EQ | ISSUED | C & L CONTRACTING CORP | 12/23/2020 |
| BIS | PL | ISSUED | EASTERN PLBG & MECH CONTR | 02/20/2020 |
| BIS | EQ | ISSUED | C & L CONTRACTING CORP | 02/11/2020 |
| BIS | — | ISSUED | C & L CONTRACTING CORP | 01/17/2020 |
| BIS | PL | ISSUED | EASTERN PLBG & MECH CONTR | 02/22/2019 |
| BIS | — | ISSUED | C & L CONTRACTING CORP | 02/07/2019 |
| BIS | EQ | ISSUED | C & L CONTRACTING CORP | 02/07/2019 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/22/2026 | Permit Issued | RNW ELECTRIC CORP | General Wiring |
| 01/03/2022 | Complete | RNW ELECTRIC CORP | 1 meters |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/22/2026 | Public Assembly Emergency Lighting | Mark Husser | progress |
| 05/15/2025 | Heating Systems | GEORGE GHEBRYAL | special |
| 05/15/2025 | Maintenance information | GEORGE GHEBRYAL | energy_progress |
| 05/15/2025 | HVAC-R and service water heating system controls | GEORGE GHEBRYAL | energy_progress |
| 05/15/2025 | HVAC-R and service water piping design and insulation | GEORGE GHEBRYAL | energy_progress |
| 05/15/2025 | HVAC-R and service water heating equipment | GEORGE GHEBRYAL | energy_progress |
| 11/07/2024 | Public Assembly Emergency Lighting | Mark Husser | progress |
| 11/07/2024 | Public Assembly Emergency Lighting | Mark Husser | progress |